Amazon Energy Way Tech Campus: $10B Richmond County Data Center

Data Center News by Data Center News
September 23, 2026
in Project Tracker
Amazon Energy Way Tech Campus $10B Richmond County Data Center

Amazon Energy Way Tech Campus $10B Richmond County Data Center

Share on FacebookShare on Twitter

Amazon Energy Way Tech Campus is a major Amazon Web Services data center development in Hamlet, Richmond County, North Carolina. Amazon announced plans to invest approximately $10 billion in cloud computing and artificial intelligence infrastructure in the county, with at least 500 new high-skilled jobs expected.

The project has also become one of the clearest examples of how power infrastructure can shape a modern data center build. North Carolina regulators issued Amazon an air-quality permit covering hundreds of emergency backup engines, while Duke Energy received separate authorization for temporary bridge-power generation intended to serve the campus before its permanent grid connection is complete.

Last updated: September 23, 2026
Current status: Development / permitted / construction-stage project

For other projects in the state, see the North Carolina Data Center Projects Tracker and the U.S. Data Center Projects Tracker.

Table of Contents

Toggle
  • Amazon Energy Way Tech Campus at a Glance
  • Where Is the Amazon Energy Way Tech Campus?
  • How Much Is Amazon Investing in Richmond County?
  • Amazon Energy Way Tech Campus and Backup Power
  • Why Duke Energy Is Using Temporary Bridge Power
  • What Is the Current Status of the Amazon Energy Way Tech Campus?
  • How Much Power Will the Amazon Energy Way Tech Campus Use?
  • Jobs and Workforce Development
  • How to Track the Amazon Energy Way Tech Campus
  • Frequently Asked Questions About the Amazon Energy Way Tech Campus
    • Where is the Amazon Energy Way Tech Campus?
    • How much is Amazon investing?
    • How many jobs are planned?
    • Is the campus operational?
    • How much power will it use?
  • Bottom Line

Amazon Energy Way Tech Campus at a Glance

DetailCurrent Information
CompanyAmazon / AWS / Amazon Data Services
LocationHamlet, Richmond County, North Carolina
Announced investmentApprox. $10 billion
Permanent jobs announcedAt least 500 high-skilled jobs
StatusDevelopment / permitted / construction-stage
MW capacityNot publicly disclosed in the reviewed sources

Where Is the Amazon Energy Way Tech Campus?

The Amazon Energy Way Tech Campus is being developed in Hamlet, North Carolina, in Richmond County. State and company announcements describe the project as a major new cloud and AI infrastructure campus.

Amazon announced the Richmond County investment in 2025 and later held a groundbreaking event for the project. See Amazon’s official North Carolina investment announcement.

How Much Is Amazon Investing in Richmond County?

The Amazon Energy Way Tech Campus is part of an approximately $10 billion planned Amazon investment in North Carolina cloud computing and AI infrastructure.

Amazon says the project is expected to create at least 500 new high-skilled positions, including data center engineers, network specialists, operations managers and security roles.

For context, see How Many Jobs Do Data Centers Create? and Data Center Property Tax Revenue Explained.

Amazon Energy Way Tech Campus and Backup Power

The Amazon Energy Way Tech Campus has required major backup-power planning. North Carolina air-quality permitting covers a large number of emergency backup engines associated with the Amazon campus.

These engines are intended primarily for outages, testing and maintenance. They should not be described as operating continuously under normal conditions.

Why Duke Energy Is Using Temporary Bridge Power

Power delivery is a major issue for the Amazon Energy Way Tech Campus. Duke Energy also received authorization for temporary generation designed to provide bridge power before permanent electric-grid infrastructure is fully available.

This arrangement illustrates why a data center can be under construction while still waiting for permanent transmission, substation or distribution upgrades.

Read Data Center Substations Explained and Why Data Centers Need New Transmission Lines.

What Is the Current Status of the Amazon Energy Way Tech Campus?

The Amazon Energy Way Tech Campus should currently be described as a development and construction-stage project with major environmental and power-related permits issued.

The campus is not yet best described as a fully completed, mature operating facility. Large AWS campuses are commonly built in phases.

See How Long Does It Take to Build a Data Center?.

How Much Power Will the Amazon Energy Way Tech Campus Use?

A verified full-build-out MW figure for the Amazon Energy Way Tech Campus was not identified in the official sources reviewed.

Until Amazon, Duke Energy or another authoritative utility filing provides a project-specific capacity figure, Data Center News should avoid estimating the site’s final power requirement.

See How Much Power Does a Data Center Use?.

Jobs and Workforce Development

Amazon says the Amazon Energy Way Tech Campus investment will create at least 500 high-skilled jobs and support additional construction and supply-chain employment.

Permanent operations jobs and temporary construction jobs should be reported separately because they represent different long-term economic effects.

How to Track the Amazon Energy Way Tech Campus

Future updates are likely to appear in NC DEQ records, Duke Energy utility filings, Richmond County records and Amazon community updates.

See How to Find Data Center Building Permits, Site Plans & Zoning Records.

Frequently Asked Questions About the Amazon Energy Way Tech Campus

Where is the Amazon Energy Way Tech Campus?

The campus is in Hamlet, Richmond County, North Carolina.

How much is Amazon investing?

Amazon announced approximately $10 billion of planned investment in North Carolina cloud and AI infrastructure centered on Richmond County.

How many jobs are planned?

Amazon announced at least 500 new high-skilled jobs.

Is the campus operational?

The project is in development and construction-stage activity and should not yet be described as a fully completed operating campus.

How much power will it use?

A verified full-build-out MW figure has not been publicly disclosed.

Bottom Line

The Amazon Energy Way Tech Campus is one of North Carolina’s largest new data center investments, with approximately $10 billion announced for Richmond County and at least 500 high-skilled jobs expected.

Data Center News will continue updating this profile as Amazon, Duke Energy, Richmond County and North Carolina regulators release additional information.

ShareTweet

join the DataCenterNews.org newsletter

Stay Connected

Email field is required to subscribe.

x

You Have Successfully Subscribed to the Newsletter

Data Center News

Data Center News

The Data Center News Research Desk produces research-driven coverage of data center development, power infrastructure, water use, construction, AI demand, policy, and community impacts. Our work draws on public records, government data, utility and regulatory filings, company disclosures, planning documents, and other primary sources whenever available.

Related Posts

Project Flex Data Center Lyon Township Michigan Plans & Status
Project Tracker

Project Flex Data Center: Lyon Township Michigan Plans & Status

September 25, 2026

The Project Flex data center is a proposed hyperscale campus in Lyon Township, Michigan, being developed by Verrus in partnership...

Read moreDetails
Project Cherry Blossom Data Center Frenchtown Michigan Plans
Project Tracker

Project Cherry Blossom Data Center: Frenchtown Michigan Plans

September 25, 2026

The Project Cherry Blossom data center is a proposed large-scale data center campus being developed by Cloverleaf Infrastructure in Frenchtown...

Read moreDetails
Data Center News

Data center news, projects, and analysis covering power grids, water use, AI demand, incentives, and community impact behind the world’s growing cloud infrastructure.

Navigation

  • About
  • Authors & Editors
  • Contact
  • Editorial Policy
  • Home
  • Privacy Policy
  • Terms of Service

Topics

  • AI & Cloud
  • Infrastructure & Construction
  • News
  • Policy & Community
  • Power & Grid
  • Project Tracker
  • Projects
  • Water & Environment

Join the free newsletter

Stay Connected

Email field is required to subscribe.

x

You Have Successfully Subscribed to the Newsletter

© 2026 Data Center News

No Result
View All Result
  • Home
  • News
    • Project News
  • Project Tracker
  • Power & Grid
  • Water & Environment
  • Policy & Community
  • AI & Cloud

© 2026 Data Center News