Amazon Pecos County Data Center: Fort Stockton Plans & Status

Data Center News by Data Center News
September 22, 2026
in Project Tracker
Amazon Pecos County Data Center Fort Stockton Plans & Status
Share on FacebookShare on Twitter

Amazon Pecos County data center development is moving forward near Fort Stockton, Texas, where Amazon Data Services has registered new data center buildings in 2026.

Texas Department of Licensing and Regulation records identify two separate new data center buildings at 6000 TX-18, Fort Stockton. Each registration lists Amazon Data Services, Inc. as the owner, 189,060 square feet of new construction and an estimated construction cost of $300 million. View the official Building A registration and Building B registration.

Last updated: September 21, 2026

Current status: Registered / construction-stage development

For other projects in the state, see our Texas Data Center Projects tracker. For nationwide coverage, visit the U.S. Data Center Projects tracker.

Table of Contents

Toggle
  • Amazon Pecos County Data Center at a Glance
  • Where Is Amazon Building in Pecos County?
  • How Big Is the Amazon Fort Stockton Project?
  • How Much Is Amazon Investing?
  • What Is the Current Construction Status?
  • Power and Grid Infrastructure
  • Water and Cooling
  • Jobs and Economic Impact
  • Permitting and Records to Watch
  • Frequently Asked Questions
    • Is Amazon building a data center in Pecos County, Texas?
    • Where is the Amazon Pecos County data center?
    • How large is the Fort Stockton project?
    • How much do the buildings cost?
    • How much power will the Amazon Pecos County data center use?
    • Where can I track other Texas data centers?

Amazon Pecos County Data Center at a Glance

DetailCurrent Information
CompanyAmazon Data Services, Inc.
Location6000 TX-18, Fort Stockton, Pecos County, Texas
Buildings identifiedBuilding A and Building B
Registered size189,060 sq. ft. per building; 378,120 sq. ft. combined
Listed construction cost$300M per building; $600M combined in the two registrations
OwnerAmazon Data Services, Inc.
Design firmM. Arthur Gensler & Associates
Current statusRegistered / new construction

Where Is Amazon Building in Pecos County?

The two public registrations place the project at 6000 TX-18 in Fort Stockton. The filings identify Pecos County as the location county and Amazon Data Services as owner.

Fort Stockton is part of a rapidly developing West Texas data center corridor. Microsoft is separately developing a major approximately 2 GW AI campus in Pecos, while Meta is building a 1 GW campus in El Paso. That concentration makes West Texas increasingly important to the state’s AI and cloud infrastructure buildout.

How Big Is the Amazon Fort Stockton Project?

Building A and Building B are each listed at 189,060 square feet. Together, the two identified registrations represent approximately 378,120 square feet of building area.

Square footage is useful, but it does not tell us the project’s eventual electrical demand, server capacity or full campus footprint. Public records reviewed for this profile do not yet disclose a campus-wide MW figure. Our guide to how big data centers are explains why acreage, square footage and MW measure different aspects of a project.

How Much Is Amazon Investing?

TDLR lists an estimated construction cost of $300 million for each of the two buildings, or $600 million in listed construction cost across Building A and Building B.

That figure should not automatically be described as Amazon’s total investment in Pecos County. State construction registrations can represent specific building packages and may exclude land, servers, substations, generation, networking equipment and later phases.

What Is the Current Construction Status?

Both registrations were filed on August 4, 2026 and list an August 1, 2026 start date with a December 1, 2026 completion date. The public TDLR pages classify the projects as registered.

Construction schedules in state registrations can change. Large data center campuses are also frequently delivered in multiple overlapping phases. See how long data centers take to build for more context on phased construction.

Power and Grid Infrastructure

The TDLR registrations do not publish a MW requirement or identify the project’s utility interconnection. That is a significant unknown for a hyperscale project in West Texas.

Large facilities can require dedicated substations, transformers and new transmission infrastructure. Our guide to data center substations explains the equipment involved, while Why Data Centers Need New Transmission Lines covers the grid side of large-load development.

Water and Cooling

The state construction filings reviewed here do not identify cooling technology or expected water consumption. Those details should be tracked as additional local, utility or environmental records become public.

Cooling design can materially change direct water demand. See How Much Water Does a Data Center Use? for the difference between evaporative, dry, hybrid and closed-loop systems.

Jobs and Economic Impact

No verified project-specific construction-job or permanent-job estimate was included in the TDLR records reviewed for this article. That means the project should not be assigned employment numbers based on other Amazon data centers.

When estimates do become available, construction and permanent operational employment should be reported separately. Our guide to how many jobs data centers create explains why those figures can differ dramatically.

Permitting and Records to Watch

The strongest public evidence for the project currently comes from Texas architectural-barrier registrations. Additional records worth monitoring include Pecos County property records, local site plans, utility filings, transmission projects and environmental permits.

Our guide to finding data center permits, site plans and zoning records explains how these sources can reveal project details before a company issues a full public announcement.

Frequently Asked Questions

Is Amazon building a data center in Pecos County, Texas?

Yes. Texas records identify Amazon Data Services as the owner of at least two new data center building registrations near Fort Stockton.

Where is the Amazon Pecos County data center?

The public registrations list 6000 TX-18, Fort Stockton, Texas 79735.

How large is the Fort Stockton project?

Two identified buildings are each 189,060 square feet, for 378,120 square feet combined.

How much do the buildings cost?

Each registration lists an estimated construction cost of $300 million. That is a building-registration figure, not necessarily the total campus investment.

How much power will the Amazon Pecos County data center use?

A verified project-wide MW figure has not been publicly identified in the records reviewed for this profile.

Where can I track other Texas data centers?

See the Texas Data Center Projects tracker.

ShareTweet

join the DataCenterNews.org newsletter

Stay Connected

Email field is required to subscribe.

x

You Have Successfully Subscribed to the Newsletter

Data Center News

Data Center News

The Data Center News Research Desk produces research-driven coverage of data center development, power infrastructure, water use, construction, AI demand, policy, and community impacts. Our work draws on public records, government data, utility and regulatory filings, company disclosures, planning documents, and other primary sources whenever available.

Related Posts

Project Flex Data Center Lyon Township Michigan Plans & Status
Project Tracker

Project Flex Data Center: Lyon Township Michigan Plans & Status

September 25, 2026

The Project Flex data center is a proposed hyperscale campus in Lyon Township, Michigan, being developed by Verrus in partnership...

Read moreDetails
Project Cherry Blossom Data Center Frenchtown Michigan Plans
Project Tracker

Project Cherry Blossom Data Center: Frenchtown Michigan Plans

September 25, 2026

The Project Cherry Blossom data center is a proposed large-scale data center campus being developed by Cloverleaf Infrastructure in Frenchtown...

Read moreDetails
Data Center News

Data center news, projects, and analysis covering power grids, water use, AI demand, incentives, and community impact behind the world’s growing cloud infrastructure.

Navigation

  • About
  • Authors & Editors
  • Contact
  • Editorial Policy
  • Home
  • Privacy Policy
  • Terms of Service

Topics

  • AI & Cloud
  • Infrastructure & Construction
  • News
  • Policy & Community
  • Power & Grid
  • Project Tracker
  • Projects
  • Water & Environment

Join the free newsletter

Stay Connected

Email field is required to subscribe.

x

You Have Successfully Subscribed to the Newsletter

© 2026 Data Center News

No Result
View All Result
  • Home
  • News
    • Project News
  • Project Tracker
  • Power & Grid
  • Water & Environment
  • Policy & Community
  • AI & Cloud

© 2026 Data Center News