Amazon Project Eagle Data Center: Wharton County Plans & Status

Data Center News by Data Center News
September 22, 2026
in Project Tracker
Amazon Project Eagle Data Center Wharton County Plans & Status

Amazon Project Eagle Data Center Wharton County Plans & Status

Share on FacebookShare on Twitter

Amazon Project Eagle data center development near Boling in Wharton County, Texas is a major multi-building campus being developed by Amazon Data Services.

Texas Department of Licensing and Regulation records identify multiple Project Eagle buildings owned by Amazon Data Services. Individual registrations reviewed for Buildings A through D each list approximately 189,060 square feet and an estimated construction cost of $300 million. View Project Eagle Building A, Building B, Building C, and Building D.

Additional state registrations indicate the campus extends beyond those first four buildings. Because Texas records are being updated as individual packages are filed, the safest current description is a large multi-building AWS campus rather than a fixed final building count unless every registration is re-verified at publication time.

Last updated: September 21, 2026

Current status: Registered / construction-stage multi-building development

See our Texas Data Center Projects tracker for other projects in the state and the U.S. Data Center Projects tracker for nationwide coverage.

The Amazon Project Eagle data center profile will be updated as additional project-specific filings, utility records and company disclosures become available.

Table of Contents

Toggle
  • Amazon Project Eagle Data Center at a Glance
  • Amazon Project Eagle Data Center: Where Is Project Eagle?
  • How Many Buildings Are Planned at Project Eagle?
  • How Big Is Each Project Eagle Building?
  • How Much Is Amazon Spending on Project Eagle?
  • Project Eagle Construction Timeline
  • Power and Grid Infrastructure
  • Water and Cooling
  • Jobs, Taxes and Community Impact
  • Frequently Asked Questions
    • What is Amazon Project Eagle?
    • Where is Project Eagle located?
    • How large are the Project Eagle buildings?
    • How much do the buildings cost?
    • Is Project Eagle under construction?
    • How many Project Eagle buildings are there?

Amazon Project Eagle Data Center at a Glance

DetailCurrent Information
CompanyAmazon Data Services, Inc.
Project nameProject Eagle
LocationBoling, Wharton County, Texas
Public addressesEaglewood Road, Boling
Building sizeApprox. 189,060 sq. ft. per identified primary building registration
Listed construction cost$300M per identified primary building registration
OwnerAmazon Data Services, Inc.
Design firmM. Arthur Gensler & Associates
StatusReview complete / registered / construction-stage development

Amazon Project Eagle Data Center: Where Is Project Eagle?

The Amazon Project Eagle data center is located near Boling in Wharton County. State records place individual buildings along Eaglewood Road.

Wharton County is southwest of the Houston metropolitan area. The location gives Amazon access to a large Texas power market while providing the land needed for a multi-building campus.

How Many Buildings Are Planned at Project Eagle?

Project Eagle is clearly larger than a two-building project. State registrations identify a sequence of buildings under the same project name, and the filings reviewed for this profile confirm Buildings A, B, C and D with matching ownership, approximate size and design team.

Other Project Eagle registrations have also appeared in the state database, indicating continued campus expansion. Because those records can change and new packages can be added, the tracker should be updated from the latest TDLR search rather than hard-coding an outdated count.

How Big Is Each Project Eagle Building?

The primary building registrations reviewed list approximately 189,060 square feet per building.

At multi-building scale, total campus size can become very large even when each individual structure is similar. It is also important to distinguish building area from site acreage and electrical capacity. See How Big Is a Data Center?.

How Much Is Amazon Spending on Project Eagle?

The reviewed building registrations each list an estimated construction cost of $300 million.

Those permit-level figures demonstrate the substantial scale of the project, but adding them together still may not equal Amazon’s total campus investment. Land, servers, power infrastructure and later phases may be accounted for separately.

Project Eagle Construction Timeline

Buildings A through D were registered in June 2026. The records list August 2026 start dates, with completion dates ranging into 2027.

That staggered schedule is consistent with phased campus construction. Large campuses can bring individual buildings online while later structures remain under development. See our construction timeline guide.

Power and Grid Infrastructure

Public TDLR records do not disclose a campus-wide MW requirement for Project Eagle.

A multi-building AWS campus can require major electrical infrastructure, but project-specific substation and transmission information should be sourced from utility, ERCOT or regulatory records before being stated as fact. See Data Center Substations Explained for what those systems typically include.

Water and Cooling

The state building registrations do not publish the cooling system or expected water consumption. Those should remain listed as not publicly disclosed until environmental, water-utility or company records provide reliable details.

Jobs, Taxes and Community Impact

No verified Project Eagle-specific job estimate or complete local tax arrangement was identified in the construction registrations used here.

Those figures should be researched separately rather than inferred from Amazon’s other campuses. The most useful local questions include permanent jobs, taxable property, sales-tax treatment, road infrastructure, utility upgrades and emergency-services impacts.

For readers tracking the Amazon Project Eagle data center, the most important next records will be construction filings, power and interconnection details, water or cooling disclosures, and confirmed build-out milestones.

Frequently Asked Questions

What is Amazon Project Eagle?

Project Eagle is a multi-building Amazon Data Services data center development near Boling in Wharton County, Texas.

Where is Project Eagle located?

Texas records place the project along Eaglewood Road in Boling, Wharton County.

How large are the Project Eagle buildings?

Primary registrations reviewed for multiple buildings list approximately 189,060 square feet each.

How much do the buildings cost?

The reviewed registrations list an estimated construction cost of $300 million per building. Those are construction-registration figures, not necessarily the total campus investment.

Is Project Eagle under construction?

The state records support describing the project as registered and in construction-stage development, with schedules extending into 2027.

How many Project Eagle buildings are there?

The project extends beyond the original two buildings shown on the tracker. Multiple additional registrations have been filed, so the live TDLR database should be used when stating an exact current count.

ShareTweet

join the DataCenterNews.org newsletter

Stay Connected

Email field is required to subscribe.

x

You Have Successfully Subscribed to the Newsletter

Data Center News

Data Center News

The Data Center News Research Desk produces research-driven coverage of data center development, power infrastructure, water use, construction, AI demand, policy, and community impacts. Our work draws on public records, government data, utility and regulatory filings, company disclosures, planning documents, and other primary sources whenever available.

Related Posts

Project Flex Data Center Lyon Township Michigan Plans & Status
Project Tracker

Project Flex Data Center: Lyon Township Michigan Plans & Status

September 25, 2026

The Project Flex data center is a proposed hyperscale campus in Lyon Township, Michigan, being developed by Verrus in partnership...

Read moreDetails
Project Cherry Blossom Data Center Frenchtown Michigan Plans
Project Tracker

Project Cherry Blossom Data Center: Frenchtown Michigan Plans

September 25, 2026

The Project Cherry Blossom data center is a proposed large-scale data center campus being developed by Cloverleaf Infrastructure in Frenchtown...

Read moreDetails
Data Center News

Data center news, projects, and analysis covering power grids, water use, AI demand, incentives, and community impact behind the world’s growing cloud infrastructure.

Navigation

  • About
  • Authors & Editors
  • Contact
  • Editorial Policy
  • Home
  • Privacy Policy
  • Terms of Service

Topics

  • AI & Cloud
  • Infrastructure & Construction
  • News
  • Policy & Community
  • Power & Grid
  • Project Tracker
  • Projects
  • Water & Environment

Join the free newsletter

Stay Connected

Email field is required to subscribe.

x

You Have Successfully Subscribed to the Newsletter

© 2026 Data Center News

No Result
View All Result
  • Home
  • News
    • Project News
  • Project Tracker
  • Power & Grid
  • Water & Environment
  • Policy & Community
  • AI & Cloud

© 2026 Data Center News