AWS New Carlisle Data Center: $11B Indiana Campus

Data Center News by Data Center News
September 25, 2026
in Project Tracker
AWS New Carlisle Data Center $11B Indiana Campus

AWS New Carlisle Data Center $11B Indiana Campus

Share on FacebookShare on Twitter

The AWS New Carlisle data center development is an approximately $11 billion Amazon Web Services campus in St. Joseph County, Indiana, representing one of the state’s largest-ever individual capital investment announcements.

AWS announced the project in April 2024 and later broke ground in the New Carlisle area.

The campus is being developed within the Indiana Enterprise Center and is expected to create at least 1,000 jobs.

AWS says construction and related economic activity could support thousands of additional positions across the data center supply chain.

The campus is one of several major developments listed in our Indiana Data Center Projects tracker.

Table of Contents

Toggle
  • AWS New Carlisle Data Center at a Glance
  • Where Is the AWS Indiana Data Center?
  • Why AWS Chose St. Joseph County
  • How Much Is AWS Investing?
  • How Many Jobs Will AWS Create?
  • Is Amazon Investing Another $15 Billion in Indiana?
  • Roads and Infrastructure
  • Power Requirements
  • Current Status
  • Frequently Asked Questions
    • Where is the AWS New Carlisle data center?
    • How much is AWS investing?
    • How many jobs will the AWS campus create?
    • Is the $15 billion AWS Indiana announcement the same project?
    • Is the campus under construction?
  • Bottom Line

AWS New Carlisle Data Center at a Glance

DetailCurrent Information
CompanyAmazon Web Services
LocationNew Carlisle area
CountySt. Joseph County
Development AreaIndiana Enterprise Center
Announced InvestmentApproximately $11 billion
Announced JobsAt least 1,000
Groundbreaking2024
Development PeriodMulti-year
StatusDevelopment / Construction

Where Is the AWS Indiana Data Center?

AWS is building the campus in St. Joseph County near New Carlisle, west of South Bend.

Amazon identifies the project as being located in the Indiana Enterprise Center.

The area has been positioned for large industrial development because of its available land and infrastructure.

Amazon says the project will be developed over multiple years rather than as one single building opening simultaneously.

Read Amazon’s official $11 billion Indiana announcement.

Why AWS Chose St. Joseph County

Large cloud and AI campuses require a specific combination of resources.

Those generally include:

  • Large contiguous sites
  • High-capacity electricity
  • Fiber connectivity
  • Transportation access
  • Water infrastructure
  • Skilled construction labor
  • Long-term utility capacity

AWS specifically cited its partnership with Indiana and local St. Joseph County organizations when announcing the investment.

The Indiana Enterprise Center is expected to host the campus over roughly a decade of development.

How Much Is AWS Investing?

AWS announced approximately $11 billion of planned investment in the St. Joseph County campus.

At the time, Indiana described it as the largest capital investment announcement in state history.

Amazon later projected that the investment could add approximately $4.7 billion to Indiana’s GDP.

That economic-impact projection should not be confused with the $11 billion capital investment itself.

The figures measure different things.

How Many Jobs Will AWS Create?

Amazon says the $11 billion project is expected to create at least 1,000 new jobs.

Positions can include:

  • Data center engineers
  • Operations technicians
  • Network specialists
  • Security personnel
  • Engineering operations staff
  • Technical managers

AWS has also projected broader employment effects.

The company estimated its investment could support more than 3,000 full-time-equivalent jobs on an annual average basis, including supply-chain and community employment.

That broader estimate includes jobs outside AWS itself.

Is Amazon Investing Another $15 Billion in Indiana?

Yes—but it is important not to combine the two announcements incorrectly.

In late 2025, Amazon announced an additional $15 billion investment in Northern Indiana for new AI and cloud data center campuses.

Amazon explicitly described the newer investment as additional to the earlier $11 billion St. Joseph County project.

The later program is expected to add approximately 2.4 GW of data center capacity across new Northern Indiana sites.

Therefore:

$11 billion = original St. Joseph County/New Carlisle project.

$15 billion = separate additional Northern Indiana expansion.

They are related as part of AWS’s growing Indiana footprint, but they should not be presented as a single $26 billion New Carlisle campus.

Roads and Infrastructure

AWS committed up to $7 million toward road infrastructure improvements surrounding the original St. Joseph County development.

Transportation upgrades can become significant around hyperscale campuses because construction may involve years of:

  • Heavy equipment
  • Concrete trucks
  • Electrical equipment deliveries
  • Transformers
  • Steel
  • Server equipment
  • Construction workers

Infrastructure obligations are therefore an important part of evaluating projects beyond the headline investment figure.

Power Requirements

AWS has not presented the original $11 billion New Carlisle project as one simple public MW figure in its primary project announcement.

That makes it important not to estimate power use solely from capital investment.

Amazon’s later $15 billion Northern Indiana announcement does provide a separate capacity figure of 2.4 GW, but that capacity belongs to the later expansion program and should not be attributed specifically to New Carlisle.

For context on MW and GW measurements, see How Much Power Does a Data Center Use?.

Current Status

The AWS St. Joseph County campus has progressed beyond an initial announcement.

Amazon participated in a groundbreaking event in 2024 and continues developing data center infrastructure in the New Carlisle area.

Because the project is expected to be built over many years, the campus should be viewed as a phased development rather than a single near-term building.

Frequently Asked Questions

Where is the AWS New Carlisle data center?

The project is in St. Joseph County near New Carlisle, Indiana, within the Indiana Enterprise Center.

How much is AWS investing?

Amazon announced approximately $11 billion for the St. Joseph County development.

How many jobs will the AWS campus create?

AWS expects at least 1,000 new jobs directly associated with the investment.

Is the $15 billion AWS Indiana announcement the same project?

No. Amazon describes the later $15 billion investment as additional to the existing $11 billion St. Joseph County project.

Is the campus under construction?

Development began following the project’s 2024 announcement and groundbreaking.

Bottom Line

The AWS New Carlisle data center is a cornerstone of Indiana’s rapidly growing cloud infrastructure market.

Its $11 billion investment, 1,000-job commitment and long-term development inside the Indiana Enterprise Center make it one of the state’s most significant technology projects—and it is now being supplemented by billions more in separate AWS investments across Northern Indiana.

ShareTweet

join the DataCenterNews.org newsletter

Stay Connected

Email field is required to subscribe.

x

You Have Successfully Subscribed to the Newsletter

Data Center News

Data Center News

The Data Center News Research Desk produces research-driven coverage of data center development, power infrastructure, water use, construction, AI demand, policy, and community impacts. Our work draws on public records, government data, utility and regulatory filings, company disclosures, planning documents, and other primary sources whenever available.

Related Posts

Project Flex Data Center Lyon Township Michigan Plans & Status
Project Tracker

Project Flex Data Center: Lyon Township Michigan Plans & Status

September 25, 2026

The Project Flex data center is a proposed hyperscale campus in Lyon Township, Michigan, being developed by Verrus in partnership...

Read moreDetails
Project Cherry Blossom Data Center Frenchtown Michigan Plans
Project Tracker

Project Cherry Blossom Data Center: Frenchtown Michigan Plans

September 25, 2026

The Project Cherry Blossom data center is a proposed large-scale data center campus being developed by Cloverleaf Infrastructure in Frenchtown...

Read moreDetails
Data Center News

Data center news, projects, and analysis covering power grids, water use, AI demand, incentives, and community impact behind the world’s growing cloud infrastructure.

Navigation

  • About
  • Authors & Editors
  • Contact
  • Editorial Policy
  • Home
  • Privacy Policy
  • Terms of Service

Topics

  • AI & Cloud
  • Infrastructure & Construction
  • News
  • Policy & Community
  • Power & Grid
  • Project Tracker
  • Projects
  • Water & Environment

Join the free newsletter

Stay Connected

Email field is required to subscribe.

x

You Have Successfully Subscribed to the Newsletter

© 2026 Data Center News

No Result
View All Result
  • Home
  • News
    • Project News
  • Project Tracker
  • Power & Grid
  • Water & Environment
  • Policy & Community
  • AI & Cloud

© 2026 Data Center News