California data center bill SB 886 has reached Gov. Gavin Newsom after clearing the state Legislature, putting a major set of proposed data center electricity rules one step away from becoming law.
The California Legislature formally enrolled SB 886 on September 4, 2026, and legislative records show it was presented to the governor at 2 p.m. on September 9. The measure, formally called the California Technology Innovation and Ratepayer Protection Act, would require the California Public Utilities Commission to establish new rules for large data centers connecting at the transmission level.
The central issue is increasingly familiar across the United States: when a data center requires billions of dollars in new power infrastructure, who ultimately pays for it?
Data Center News explains that issue in more detail in our guide to who pays for grid upgrades for data centers.
What the California Data Center Bill Would Change
The California data center bill directs the CPUC to establish new tariffs or update existing electric-service rules by January 1, 2028.
Those rules must evaluate how large new customers affect existing utility customers and are specifically required to prevent stranded costs or cost shifts from being imposed on customers that did not create the new demand.
That matters because hyperscale and AI data centers can require hundreds of megawatts of electricity.
Serving a project of that size can involve:
- New substations
- Large transformers
- New or rebuilt transmission lines
- Additional generation
- Distribution infrastructure
- Utility easements and switching equipment
For more background on the physical infrastructure involved, see our guide to data center substations.
SB 886 Would Assign Transmission Upgrade Costs to Data Centers
One of the strongest provisions in SB 886 involves transmission infrastructure.
The enrolled bill requires the CPUC tariff to assign responsibility for transmission-facility upgrades and usage to participating customers. To the extent federal law allows, that could include shared transmission-network upgrades needed to accommodate the new data center.
The legislation therefore goes beyond the simple question of whether a data center pays for the power line connecting its property.
It attempts to address broader infrastructure that may need to be constructed because of the project’s electricity demand.
Supporters argue that approach is necessary to protect residential and small-business customers.
State Sen. Steve Padilla, one of the bill’s authors, has framed SB 886 as part of a broader effort to keep the cost of data center development from being shifted onto California families.
Readers can review the official California Legislature text of SB 886.
Data Centers Would Face Load-Ramp and Early-Termination Rules
SB 886 also addresses a less visible problem: what happens if enormous projected data center demand never materializes?
Utilities may begin planning or constructing infrastructure years before a project reaches full operation.
If a proposed 500 MW campus ultimately uses only a fraction of that capacity—or never opens—other customers could potentially be left paying for infrastructure built around a load forecast that did not materialize.
SB 886 directs the CPUC to establish an early-termination fee for participating customers that leave the electrical system within 10 years of initial interconnection or fail to achieve an adequate load ramp.
The bill says that fee should not be less than the revenue gap associated with the originally projected demand and energy consumption over the minimum 10-year period.
That could make speculative power reservations significantly more expensive.
California Would Publish Data Center Power-Capacity Maps
Another provision could directly affect data center site selection.
SB 886 would require electrical corporations to publish and update maps showing locations where large customers could connect without triggering significant, costly and time-consuming transmission upgrades.
That addresses one of the biggest misconceptions in data center development:
A transmission line near a property does not necessarily mean power is available.
The line, substation and upstream grid must all have adequate capacity.
As AI infrastructure grows, available megawatts are increasingly determining where data centers can actually be built.
The California Data Center Bill Would Apply to New Transmission-Level Connections
The new interconnection tariff would apply to qualifying data centers entering new agreements for transmission-level retail electric service on or after January 1, 2027.
SB 886 would also require applicants to disclose whether they have submitted an application for the same data center in another utility territory or jurisdiction.
That provision targets another challenge facing utilities: the possibility that the same prospective data center load appears in multiple planning pipelines.
Duplicate or speculative requests can distort forecasts and potentially cause utilities to plan infrastructure for demand that will never exist.
SB 886 Is Part of a Broader California Data Center Push
SB 886 is not California’s only data center measure.
Padilla has also advanced SB 887, which focuses more heavily on environmental review and local participation in data center development.
The senator’s office says the legislative package is intended to address electricity costs as well as environmental and community impacts.
These debates mirror questions increasingly appearing at local data center hearings nationwide.
Our guide to data center town hall questions outlines the power, water, noise, tax and infrastructure questions communities should ask when a major project is proposed.
What Happens Next With California Data Center Bill SB 886?
As of September 11, SB 886 has been presented to Gov. Gavin Newsom but has not yet been signed into law. California legislative records show the measure reached the governor on September 9.
If Newsom signs it, the focus would shift to the California Public Utilities Commission.
The CPUC would then have to translate the legislation into detailed tariffs governing cost allocation, large-load interconnection and protections for other electricity customers.
Those implementation proceedings could ultimately be more consequential to the data center industry than the statutory language itself.
For developers, SB 886 could increase financial responsibility for the power infrastructure required by new projects.
For consumers, the test will be whether the resulting rules actually prevent large data center projects from shifting infrastructure risk into residential and small-business electricity rates.
Data Center News will continue tracking SB 886 as the governor considers the bill.
External sources: California Legislature — SB 886 bill text · California Legislature — SB 886 history · Sen. Steve Padilla — data center legislation announcement


