Data center projects in the United States range from individual buildings to campuses covering hundreds of acres and requiring gigawatts of electricity. This tracker follows major U.S. data center projects through proposal, permitting, approval, construction and operation, with direct links to the government, utility or company records behind the projects.
Artificial intelligence, cloud computing and high-performance computing are driving a major wave of data center construction. New projects increasingly arrive as multi-building campuses measured in megawatts or gigawatts rather than simply square feet, and they can require new substations, transmission lines, backup generators, cooling systems and water infrastructure.
The projects below are tracked because of what they mean locally: electricity demand, permitting, water use, tax treatment, jobs, infrastructure and proximity to surrounding communities.
Last updated: September 14, 2026
Scope: This page tracks selected major data center projects with significant implications for power, water, permitting, jobs, taxes or surrounding communities. It is not a complete census of every U.S. data center. Hundreds of additional facilities are operating, under construction or moving through development.
Accuracy: Acreage, investment figures, megawatts, building counts and schedules reflect the most recent publicly available records we were able to verify. Data center project details can change substantially during development. Found something out of date? Email info@datacenternews.org with the page URL and supporting documentation.
- How we verify data center project information
- Major data center projects in the U.S.
- Data center projects by state
- What each project status means
- How to find data center projects near you
- What to establish about any data center project
- Data center project research guides
- Data center projects: frequently asked questions
How We Verify Data Center Project Information
Every data center project on this page is sourced from a primary record rather than relying only on secondary reporting.
We prioritize:
- City and county planning department filings
- Zoning applications, site plans and rezoning cases
- State environmental agency permits and public notices
- Public utility commission dockets and decisions
- Building and grading permit databases
- Utility filings and transmission applications
- Announcements published directly by the developer or operator
We do not publish a data center project entry without at least one linked primary source. Where a figure comes from a developer’s own announcement rather than a government record, that distinction matters because announced figures and permitted figures can differ.
Project details can also change substantially during development. Developers may add or remove buildings, revise acreage, change cooling technology, modify electrical demand, add phases, transfer ownership or withdraw a project entirely.
That is why this page carries a visible last-updated date and why project entries link directly to the underlying source whenever possible.
Major Data Center Projects in the U.S.
The table below highlights significant data center projects currently tracked by Data Center News across the states with dedicated project trackers. It includes proposed developments, active permitting, construction and operating campuses.
| Data Center Project | Company | Location | Reported Scale | Status | Primary Source |
|---|---|---|---|---|---|
| Haven Oak Technology Park | Tract / Applicant | Dinwiddie County, Virginia | Approx. 986.9 acres | Proposed / Zoning review | Dinwiddie County application documents |
| Botetourt County Data Center Campus | Botetourt County, Virginia | 312-acre multi-phase site | Site preparation | Botetourt County project page | |
| Pecos Data Center Campus | Microsoft | Pecos, Texas | Approx. 2 GW planned capacity | Development | Microsoft announcement |
| Temple Data Center | Meta | Temple, Texas | $1.2B+ investment | Operating | Meta operating announcement |
| Project Camellia | OpenAI | Effingham County, Georgia | Approx. 3.2 GW contracted load | Development | OpenAI announcement |
| Energy Way Tech Campus | Amazon Data Services | Hamlet / Richmond County, North Carolina | $10B announced investment; 588 permitted emergency engines | Permitted / Development | NC DEQ permit decision |
| Valara High Performance Compute Center | Valara Holdings / NorthMark Strategies | Spartanburg, South Carolina | $2.8B announced investment | Environmental permitting | South Carolina DES project page |
| Lebanon Data Center | Meta | Lebanon, Indiana | Approx. 4M sq. ft.; $10B+ | Under construction | Meta announcement |
| Fayette County Data Center Expansion | Amazon Web Services | Fayette County, Ohio | Approx. $5B planned investment | Development | AWS Ohio investment announcement |
| Bowling Green Data Center | Meta | Middleton Township, Ohio | 715,000 sq. ft.; $800M+ | Under construction | Meta Bowling Green announcement |
| Saline Township AI Data Center | Green Chile Ventures / Oracle | Washtenaw County, Michigan | Approx. 1,383 MW contracted maximum load | Development / Utility approved | Michigan Public Service Commission decision |
| Project Baccara | Takanock / Baccara Power | Western Maricopa County, Arizona | 2 planned data center buildings; approx. 700 MW on-site generation | Development / Generation approved | Arizona Corporation Commission decision |
The table is intentionally selective. Each dedicated state tracker contains additional projects, locations and supporting records.
Data Center Projects by State
Data Center News maintains dedicated project trackers for nine major U.S. data center markets. Each state page provides deeper coverage of individual projects, developers, permitting status, electricity requirements, water, jobs, taxes and local issues.
- Virginia data center projects — Loudoun County, Prince William County, Botetourt County, Dinwiddie County, Henrico County and other Virginia markets.
- Texas data center projects — Pecos, Fort Stockton, Temple, El Paso, Medina County, Wharton County, Floyd County and additional Texas projects.
- Georgia data center projects — Effingham County, Columbia County, LaGrange, Douglas County, Stanton Springs and the Atlanta region.
- North Carolina data center projects — Richmond County, Lenoir, Forest City and other North Carolina data center markets.
- South Carolina data center projects — Spartanburg, Cherokee County, Dorchester County, Berkeley County and Aiken County.
- Indiana data center projects — Lebanon, New Carlisle, Fort Wayne, Michigan City, Morgan County, La Porte and other emerging markets.
- Ohio data center projects — New Albany, Columbus, Lancaster, Fayette County and Bowling Green.
- Michigan data center projects — Saline Township, Van Buren Township and Michigan’s emerging large-load AI infrastructure market.
- Arizona data center projects — Mesa, Goodyear, El Mirage, western Maricopa County, Pima County and the Greater Phoenix market.
Virginia Data Center Projects
Virginia remains the most mature major data center market in the United States. Northern Virginia, particularly Loudoun County, contains one of the largest concentrations of digital infrastructure in the world, while development is increasingly spreading into other parts of the state.
According to Loudoun County’s official data center statistics, the county reported approximately 233 existing data center buildings built or in various stages of construction as of March 1, 2026, along with tens of millions of additional square feet in the development pipeline.
Major projects outside the traditional Northern Virginia cluster include Google’s 312-acre Botetourt County campus and the nearly 987-acre proposed Haven Oak Technology Park in Dinwiddie County.
View the complete Virginia Data Center Projects tracker →
Texas Data Center Projects
Texas has become one of the largest expansion markets for AI and hyperscale data centers, with projects spreading across metro areas and rural parts of West, Central and South Texas.
Microsoft announced a major Pecos campus in June 2026 with approximately 2 GW of planned capacity. Microsoft says the multibillion-dollar project will develop over several years.
Meta’s Temple Data Center began serving production workloads in July 2026, while its much larger El Paso campus remains under construction. Google is also pursuing a major Texas expansion that includes new campuses in Armstrong and Haskell counties.
Texas illustrates why modern projects need to be evaluated by electricity capacity as well as building size.
View the complete Texas Data Center Projects tracker →
Georgia Data Center Projects
Georgia has become another major AI and hyperscale growth market.
OpenAI announced Project Camellia in Effingham County in July 2026. The company says it is contracting for approximately 3.2 GW of electricity to be delivered in phases between 2028 and 2032. Review OpenAI’s Project Camellia announcement.
Data center growth is also influencing statewide utility planning. The Georgia Public Service Commission’s data center fact sheet describes significant new electricity generation associated with projected data center demand.
Other tracked Georgia markets include Columbia County, Douglas County, LaGrange, Stanton Springs and the broader Atlanta region.
View the complete Georgia Data Center Projects tracker →
North Carolina Data Center Projects
North Carolina combines long-established hyperscale campuses from Google and Meta with a new wave of AI and cloud infrastructure development.
The largest current project is Amazon’s Energy Way Tech Campus near Hamlet in Richmond County. North Carolina announced approximately $10 billion of planned investment, while the state’s final air permit authorizes up to 588 emergency backup engines.
Duke Energy also received a separate permit for temporary generation intended to provide bridge power before the permanent grid connection is ready. Review the North Carolina DEQ permit decision.
The project demonstrates why residents researching a proposed data center should look beyond the main buildings. Supporting infrastructure may require separate permits for generators, substations, transmission lines and temporary power.
For additional context, see our guides to data center substations and data center construction timelines.
View the complete North Carolina Data Center Projects tracker →
South Carolina Data Center Projects
South Carolina is attracting hyperscale, high-performance computing and AI infrastructure projects across both the Upstate and Lowcountry.
One of the state’s most closely watched projects is the Valara High Performance Compute Center in Spartanburg. NorthMark Strategies announced approximately $2.8 billion of investment, while the project’s proposed on-site electricity generation has required significant environmental review.
The South Carolina Department of Environmental Services maintains a dedicated Valara project page with permitting and public-participation information.
Other major developments include Cielo Digital Infrastructure in Cherokee County, Google’s Dorchester and Berkeley County campuses, and Meta’s Aiken County project.
View the complete South Carolina Data Center Projects tracker →
Indiana Data Center Projects
Indiana has rapidly become one of the Midwest’s most important new data center markets.
Meta broke ground on its Lebanon campus in February 2026. The company says the campus will span roughly 4 million square feet, represent more than $10 billion of investment and support approximately 4,000 construction workers at peak and more than 300 operational jobs. Review Meta’s Lebanon announcement.
Amazon Web Services has separately announced approximately $11 billion of planned investment in northern Indiana, while Google has projects in Fort Wayne, Michigan City and Morgan County. Microsoft is developing a campus in La Porte.
Indiana also demonstrates the growing land-use debate around hyperscale development. Boone County enacted a temporary moratorium on new data center applications in unincorporated parts of the county while reviewing its planning standards.
View the complete Indiana Data Center Projects tracker →
Ohio Data Center Projects
Ohio has become a major hyperscale market centered on central Ohio, with significant infrastructure from Amazon Web Services, Google, Meta, Microsoft and other operators.
AWS has announced another $10 billion of planned Ohio cloud and AI infrastructure investment, potentially expanding to as many as eight new sites through 2030. The first new site is in Fayette County, where AWS says it expects approximately $5 billion of investment. Review AWS’s Ohio investment announcement.
Meta is also building a 715,000-square-foot data center in Middleton Township near Bowling Green. Meta reports more than $800 million of planned investment and approximately 100 operational jobs once completed. See Meta’s Bowling Green project announcement.
Ohio has also become an important case study in data center electricity policy as regulators and utilities address how the costs of new substations, transmission and other grid infrastructure should be allocated.
View the complete Ohio Data Center Projects tracker →
Michigan Data Center Projects
Michigan’s emerging data center market is being shaped by unusually large AI-related electricity requirements.
The Michigan Public Service Commission approved special DTE Electric contracts associated with a proposed data center in Saline Township with a maximum load of approximately 1,383 MW.
The project is being developed by Green Chile Ventures, an Oracle subsidiary, in connection with Oracle, OpenAI and Related Digital. The Commission imposed additional safeguards intended to prevent other utility customers from bearing costs associated with serving the project. Read the Michigan PSC decision.
The state has also approved battery-storage projects associated with the campus, and updated emergency procedures require qualifying large-load customers such as the Saline facility to be curtailed before ordinary customers during certain grid emergencies.
Google is separately developing a data center in Van Buren Township, making southeast Michigan another market to watch closely.
View the complete Michigan Data Center Projects tracker →
Arizona Data Center Projects
Arizona has developed into one of the country’s most important hyperscale expansion markets, particularly across Greater Phoenix.
Meta and Google operate major facilities in Mesa, while Microsoft has infrastructure in Goodyear and El Mirage. Newer developments are increasingly defined by their electricity requirements.
Project Baccara in western Maricopa County is planned to include two data center buildings and approximately 700 MW of associated natural-gas generation. The Arizona Corporation Commission approved the generation project’s Certificate of Environmental Compatibility in February 2026.
The Commission explicitly noted that its action concerned the project’s power generation and interconnection—not approval or denial of the data center itself.
Project Blue in Pima County provides another example of large-load development, with an initial utility-service requirement of approximately 286 MW.
Arizona projects make both water consumption and electricity infrastructure especially important areas to monitor.
View the complete Arizona Data Center Projects tracker →
Data Center Project Status: What Each Stage Means
An announcement does not mean a data center will necessarily be built. Establishing where a project sits in the development process is one of the most important things to do before evaluating a claim about it.
| Status | What It Means |
|---|---|
| Proposed | A developer has publicly identified a project or submitted an early application. The project may still require rezoning, special-use approval, environmental permits, utility agreements and site-plan approval. |
| Permitting / Under Review | The project has entered formal regulatory or local-government review. Applications may include zoning, building, air-quality, wetland and stormwater permits. |
| Approved | A significant land-use or project approval has been granted. Approval does not necessarily mean construction is imminent. |
| Site Preparation | Grading, clearing, utility relocation or other preliminary physical work has begun. |
| Under Construction | Physical construction of data center buildings or major supporting infrastructure is underway. |
| Partially Operational | One portion of a multi-phase campus is operating while additional buildings or phases remain under construction. |
| Operating | The facility is serving production workloads. |
| Withdrawn, Denied or On Hold | The project is not currently advancing as originally proposed. Projects can be denied, withdrawn, redesigned, delayed, sold or cancelled. |
How to Find Data Center Projects Near You
Large data center projects often create a public-record trail long before construction begins, sometimes under a project codename or LLC that does not immediately identify the eventual operator.
The records most likely to identify a project early include:
- County GIS and property ownership records
- Planning and zoning applications
- Rezoning and special-use cases
- Planning Commission agendas and meeting packets
- Site plans
- Building and grading permits
- Air-quality and stormwater permits
- Wetland permits
- Utility filings
- Substation and transmission applications
- Economic-development agreements
Two Data Center News guides walk through the process in detail:
- How to Find Out If a Data Center Is Planned Near You
- How to Find Data Center Building Permits, Site Plans & Zoning Records
Searching only for Amazon, Google, Microsoft, Meta or another recognizable operator can miss a project entirely. Developers commonly use holding companies, project LLCs or codenames during early development.
What to Establish About Any Data Center Project
Do not evaluate a data center project from its headline investment figure alone. The information that actually determines local impact includes:
- Developer and operator. These may be different companies.
- Exact parcel. Identify the specific property rather than only the nearest city.
- Acreage. Determine the total development footprint at full build-out.
- Building count and square footage. Distinguish phase one from the eventual campus.
- Megawatts. Separate initial electrical demand from maximum planned demand.
- Serving utility. Determine which electric company is responsible for service.
- Substations and transmission. Establish what new electrical infrastructure is required.
- Cooling technology. Different cooling systems can produce very different water requirements.
- Water source. Determine whether the project relies on potable water, reclaimed water, groundwater or another supply.
- Generator count. Check permitted generator numbers, fuel type and runtime limits.
- Construction jobs. Separate temporary construction employment from permanent operations.
- Permanent jobs. Look for expected long-term staffing rather than total economic-impact estimates.
- Tax revenue. Use actual projected recurring local revenue after exemptions and incentives rather than total project investment.
- Expansion rights. Determine whether approval covers only the first building or an entire future campus.
- Current status. An announcement, permit approval and construction start are different milestones.
- Last verified date. Data center plans change quickly, so old project figures can become misleading.
For a structured list of questions to use during a public hearing or community meeting, see our 25 data center town hall questions every community should ask.
Data Center Project Research Guides
These Data Center News explainers cover the technical and policy issues that repeatedly appear around major projects:
- How Big Is a Data Center? Acres, Square Feet & MW Explained
- How Much Power Does a Data Center Use?
- Data Center Substations Explained
- Why Do Data Centers Need New Transmission Lines?
- How Long Does It Take to Build a Data Center?
- How Much Water Does a Data Center Use?
- How Many Jobs Do Data Centers Create?
- Data Center Property Tax Revenue Explained
- Data Center Setbacks: How Close Can a Data Center Be to Homes?
- Community Opposition to Data Centers
- How to Find Data Center Building Permits, Site Plans & Zoning Records
- How to Find Out If a Data Center Is Planned Near You
Data Center Projects: Frequently Asked Questions
What counts as a data center project?
A data center project is a proposed, permitted, under-construction or operating facility built to house computing infrastructure together with the supporting infrastructure it requires.
A single project can include multiple data center buildings, substations, backup generators, cooling systems, water connections, energy-storage systems and transmission lines. These components may be reviewed and permitted separately.
Which states does Data Center News currently track?
Data Center News currently maintains dedicated state project trackers for Virginia, Texas, Georgia, North Carolina, South Carolina, Indiana, Ohio, Michigan and Arizona.
Where are the most data center projects being built?
Virginia and Texas remain major established markets, while development is expanding rapidly into states including Georgia, North Carolina, South Carolina, Indiana, Ohio, Michigan and Arizona.
Increasingly, developers are following available electrical capacity, transmission access, suitable land and realistic time-to-power rather than population alone.
Does “proposed” mean a data center will definitely be built?
No.
A proposed project can still be revised, delayed, denied, withdrawn or cancelled. An announcement, a land-use approval, an environmental permit and a construction start are separate milestones.
How do I find data center projects near me?
Start with your county or municipality’s planning applications, rezoning cases, Planning Commission agendas and GIS property records. Then check building permits, environmental permits and electric-utility filings.
Projects often appear under placeholder names or LLCs before the eventual operator is publicly identified. See How to Find Out If a Data Center Is Planned Near You for a step-by-step process.
How large are current data center projects?
There is no standard size.
A facility may be a single building requiring a few megawatts or a multi-building AI campus requiring hundreds or thousands of megawatts.
Because electricity has become one of the primary constraints on new development, modern hyperscale projects are increasingly described using megawatts or gigawatts rather than square footage alone. See How Big Is a Data Center? for examples.
Why do reported data center project figures change?
Projects evolve during development.
Announced figures generally reflect a developer’s intentions. Permitted figures reflect what a regulator has authorized. Construction records may then reveal a different first-phase size.
Developers can also change building counts, campus acreage, electrical demand, cooling technology, generator numbers, construction schedules and expansion plans.
Always check what type of figure is being reported and when it was last verified.
Do data centers use a lot of electricity?
Some do.
Large hyperscale and AI campuses can require hundreds of megawatts or more than one gigawatt of capacity. That can require new substations, transmission infrastructure, generation or energy storage.
See How Much Power Does a Data Center Use? for a detailed explanation.
Do data centers use a lot of water?
Water use varies significantly by project and cooling design.
Two facilities with similar electrical capacity can have very different water requirements depending on climate, cooling technology, server density and whether reclaimed water or closed-loop cooling is used.
See How Much Water Does a Data Center Use?.
How many permanent jobs do data centers create?
Permanent staffing varies widely and is generally much smaller than the temporary construction workforce.
That is why construction workers, permanent company employees, contractors and indirect economic-impact estimates should be reported separately.
See How Many Jobs Do Data Centers Create?.
Where does Data Center News get project information?
We prioritize official planning records, environmental permits, utility filings, public utility commission dockets, building and grading permits, development agreements and direct company announcements.
Major project entries on this page include a link to an underlying primary source.
How often is the U.S. data center projects tracker updated?
Entries are updated when a project reaches a meaningful new milestone or when significant new public documentation becomes available rather than on a fixed schedule.
The last-updated date at the top of this page reflects the most recent revision of the tracker.
How do I report an error or submit a project?
Email info@datacenternews.org with the page URL and any supporting government, regulatory, utility or company documentation.
Why We Track Data Center Projects
Information about a single large data center project is often scattered across planning applications, meeting packets, regulatory filings, property records, utility documents, environmental permits and company announcements.
Most of those records are public. Very few are organized in a way that makes the entire project easy to understand.
This tracker brings that information together in a format that can be read and compared while keeping the underlying source one click away.
The goal is not to argue for or against data center development. It is to make it easier to distinguish between:
- What has been officially documented
- What a developer has publicly announced
- What regulators have actually approved
- What has entered construction
- What remains uncertain
As more U.S. communities encounter hyperscale and AI infrastructure for the first time, those distinctions are becoming increasingly important.