Arizona Data Center Projects: 2026 Locations & Tracker

Arizona has become one of the country’s most important emerging data center markets, led primarily by development across the Phoenix metropolitan area.

The market combines established hyperscale facilities from Meta, Google and Microsoft with newer projects planning hundreds of megawatts of dedicated generation or utility capacity.

Because of Arizona’s climate and electricity needs, power and water are central to nearly every major project discussion.

Last updated: September 14, 2026

Arizona Data Center Projects Tracker

ProjectCompany / DeveloperLocationReported ScaleStatusPrimary Source
Mesa Data CenterMetaMesa$1B+; 2.5M+ sq. ft.; 200+ operational jobsOperatingMeta Mesa operating announcement
Project BaccaraTakanock / Baccara PowerWest Maricopa CountyTwo data center buildings; ~700 MW generationDevelopmentArizona Corporation Commission decision
Project BlueBeal Infrastructure / Humphrey’s Peak PowerPima CountyInitial electric load ~286 MWDevelopmentArizona Corporation Commission agreement summary
Greater Phoenix FacilitiesMicrosoftEl Mirage & GoodyearMultiple operating and developing facilitiesOperating / ExpandingMicrosoft Arizona data center page
Mesa Data CenterGoogleMesaHyperscale campusOperatingGoogle data center locations

Meta Mesa Data Center

Meta’s Mesa Data Center began serving production traffic in January 2025.

Meta says the campus will represent more than $1 billion of investment at full build-out and currently supports more than 200 operational jobs. Read Meta’s Mesa operating announcement.

Meta previously announced that expansion would bring the campus to more than 2.5 million square feet. Read Meta’s Mesa expansion announcement.

See How Big Is a Data Center? for context on comparing square footage with electrical capacity.

Project Baccara — West Maricopa County

Project Baccara is one of Arizona’s most notable emerging projects because of its planned on-site electricity generation.

The Arizona Corporation Commission approved a Certificate of Environmental Compatibility in February 2026 for approximately 700 MW of natural-gas generation associated with the planned data center complex. Read the ACC Project Baccara decision.

The project is planned to include two data center buildings in western Maricopa County.

Generation Approval Is Not the Same as Data Center Approval

This distinction needs to remain explicit.

The Arizona Corporation Commission stated that its role was to evaluate the generation and interconnection—not to approve or deny the data center itself.

Therefore:

“Power generation approved” does not mean “the entire data center is fully approved.”

That kind of distinction is exactly why DataCenterNews.org should link directly to the underlying regulatory record.

Project Blue — Pima County

Project Blue is another large Arizona development, located in the Tucson/Pima County market.

The Arizona Corporation Commission approved Tucson Electric Power’s special agreement to provide service to the planned development in December 2025.

The initial load is approximately 286 MW. Read the ACC Project Blue utility decision.

Regulators said additional renewable generation required beyond the initial amount would be paid for by the data center rather than other customers.

See our guide to how much power a 100 MW, 500 MW or 1 GW data center represents.

Microsoft El Mirage and Goodyear Data Centers

Microsoft operates data centers in El Mirage and Goodyear in the Greater Phoenix area and is continuing additional development.

Microsoft says its Arizona facilities are part of its West Valley infrastructure footprint. View Microsoft’s official Greater Phoenix data center page.

Microsoft reported approximately 430 operational employees across its Arizona facilities in its 2025 community materials.

Google Mesa Data Center

Google currently lists Mesa among its operating U.S. data center locations. View Google’s current data center locations.

Combined with Meta, Microsoft and other developers, that makes metropolitan Phoenix one of the country’s most concentrated emerging hyperscale markets.

Arizona Data Centers and Electricity

Electricity availability is one of the biggest constraints on future Arizona data center development.

Projects may require:

  • Dedicated substations
  • New transmission
  • New utility-scale generation
  • On-site generation
  • Energy storage
  • Minimum-demand agreements
  • Special large-load tariffs

Project Baccara illustrates one approach: co-located generation.

Project Blue illustrates another: a special utility-service agreement.

See our explainers on data center substations and why data centers may require new transmission lines.

Who Pays for Arizona Data Center Infrastructure?

The central ratepayer issue is not simply how much electricity a project uses.

The key question is who pays for infrastructure built specifically to serve it.

That can include:

  • Power plants
  • Substations
  • Transmission
  • Distribution equipment
  • Transformers
  • Energy storage

Arizona regulators have emphasized the principle that new large-load customers should bear costs created by their projects rather than shifting them to existing customers.

Project Blue’s utility agreement provides one current example. Read the ACC Project Blue cost-allocation discussion.

Arizona Data Centers and Water

Water receives particular attention in Arizona because major facilities are developing in an arid region.

However, it is inaccurate to assume every data center uses the same amount of water.

Cooling requirements depend on:

  • Cooling technology
  • Server density
  • Climate
  • Facility design
  • Operating temperature
  • Reclaimed-water availability
  • Closed-loop cooling

See our detailed explainer on why data centers use water and what actually gets consumed.

Arizona Data Center Jobs

Meta reports more than 200 operational jobs at its Mesa campus, while Microsoft has reported approximately 430 employees across its Arizona data center operations.

Construction workforces can be much larger but temporary.

See How Many Jobs Do Data Centers Create?.

Community Issues in Arizona

Major Arizona data center debates increasingly involve:

  • Water
  • Electricity
  • Natural-gas generation
  • Utility rates
  • Noise
  • Land use
  • Residential proximity
  • Grid infrastructure

For a broader overview, see Community Opposition to Data Centers.

Communities reviewing a proposal can also use our 25 questions to ask at a data center town hall.

Arizona Data Center Regions to Watch

Mesa

Meta and Google make Mesa one of Arizona’s most established hyperscale locations.

Goodyear and El Mirage

Microsoft has established a significant West Valley footprint.

Western Maricopa County

Project Baccara’s planned data center and approximately 700 MW generation facility make this an important development zone.

Pima County / Tucson

Project Blue represents significant expansion outside the primary Phoenix cluster.

How to Track an Arizona Data Center Project

Monitor:

  1. Arizona Corporation Commission proceedings
  2. County and municipal zoning records
  3. Power-plant siting cases
  4. Utility rate proceedings
  5. Environmental permits
  6. Property records
  7. Water-provider records
  8. Developer LLC names

Projects may appear under codenames such as Project Baccara or Project Blue before the eventual operator is fully known.

Our guides to finding planned data centers near you and finding permits and site plans explain how to search for them.

Frequently Asked Questions

Where are Arizona’s largest data center markets?

Greater Phoenix remains the state’s dominant cluster, particularly Mesa, Goodyear, El Mirage and western Maricopa County. Pima County is also emerging as a significant market.

What is Project Baccara?

Project Baccara is a planned western Maricopa County data center complex with two proposed data center buildings and approximately 700 MW of associated natural-gas generation. Arizona Corporation Commission project decision.

Has Project Baccara been fully approved?

The Arizona Corporation Commission approved the project’s power-generation Certificate of Environmental Compatibility. The Commission explicitly stated that its action was not approval or denial of the data center itself.

What is Project Blue?

Project Blue is a planned Pima County data center associated with Beal Infrastructure Group and Humphrey’s Peak Power. Its approved utility agreement begins with approximately 286 MW of electrical load. ACC Project Blue decision.

Is Meta’s Mesa data center operating?

Yes. Meta announced that the Mesa Data Center began serving production traffic in January 2025. Meta Mesa announcement.