Georgia data center projects are expanding rapidly as artificial intelligence, cloud computing and hyperscale development drive demand for enormous amounts of new computing infrastructure.
Georgia already hosts major data center operations from companies including Google and Meta, while new projects from OpenAI and additional Google campuses are pushing development into entirely new parts of the state.
This tracker follows major data centers in Georgia, including projects that are operating, under construction, approved, proposed or moving through local and state review.
Last updated: September 22, 2026
Data center plans can change during development, permitting and construction. Project acreage, investment, building counts, electrical requirements and completion dates below reflect the latest publicly available information that could be verified at the time of publication.
Georgia Data Center Projects: Quick Navigation
Dedicated Georgia Data Center Project Profiles
For deeper research on each major project, use the dedicated Data Center News project profiles below:
-
Project Camellia Data Center: OpenAI’s 3.2 GW Georgia Campus
-
Google Columbia County Data Center: White Oak Technology Park Plans & Status
-
Google LaGrange Data Center: Troup County Expansion & Status
-
Google Douglas County Data Center: Location, History & Water Use
-
Meta Stanton Springs Data Center: $1.5B Georgia Campus Explained
Each profile includes deeper coverage of location, project status, investment, construction, power, water, jobs and other publicly available project details.
Georgia Data Center Projects Tracker
The table below highlights several of the most significant current Georgia data center projects being tracked by Data Center News.
This is not a complete inventory of every data center building in Georgia. The Atlanta region already contains a substantial data center market, while new developments are increasingly spreading into coastal, eastern and western Georgia.
| Project | Company | Location | Reported Scale | Status |
|---|---|---|---|---|
| Project Camellia | OpenAI | Effingham County | 3.2 GW; approx. $20B reported investment; 5 phases | Development / Review |
| White Oak Technology Park / Google Columbia County | Columbia County | Large multi-building campus | Approved / Development | |
| LaGrange Data Center | LaGrange / Troup County | Existing development plus proposed 470,000-sq.-ft. expansion | Under Construction / Expansion | |
| Douglas County Data Center | Douglas County | Long-established hyperscale campus | Operating | |
| Stanton Springs Data Center | Meta | Newton County / Stanton Springs | $1.5B+ investment; 200+ operational jobs | Operating / Expanding |
For projects elsewhere in the country, visit our U.S. Data Center Projects tracker.
OpenAI Project Camellia — Effingham County
Full project profile: Project Camellia Data Center: OpenAI’s 3.2 GW Georgia Campus
Project Camellia is one of the largest announced Georgia data center projects and one of the largest AI infrastructure developments currently planned in the United States.
OpenAI announced the project on July 22, 2026.
The campus is planned for Effingham County at the existing Savannah Gateway Industrial Hub near the Savannah region.
OpenAI says the project is being designed for approximately:
-
3.2 gigawatts of electrical capacity
-
Phased power delivery from 2028 through 2032
-
A multi-phase development program
-
Closed-loop cooling intended to minimize ongoing water consumption
OpenAI describes Project Camellia as a long-term AI infrastructure project rather than one single data center building.
You can review OpenAI’s official Project Camellia announcement.
What Does 3.2 GW Mean?
Three-point-two gigawatts equals:
-
3,200 megawatts
-
3.2 million kilowatts
That places Project Camellia in an entirely different scale category from a traditional enterprise data center.
For comparison, read our guide explaining how much power a data center uses.
How Big Is Project Camellia?
Public filings and local reporting describe a very large campus at the Savannah Gateway Industrial Hub.
The broader industrial hub covers approximately 2,600 acres.
Development filings associated with Project Camellia have described approximately:
-
Four major data center buildings in early plans
-
A very large development footprint
-
Phased construction
-
Major power and utility infrastructure
The project remains subject to detailed site planning, permitting, infrastructure design and other approvals.
OpenAI itself emphasizes that significant work remains involving:
-
Site design
-
Infrastructure
-
Phasing
-
Permitting
-
Financing
-
Operating model
That is an important distinction.
Announced does not mean fully permitted or ready for construction.
Project Camellia Is Planned in Five Phases
Effingham County says Project Camellia is expected to be developed in five phases.
That means the campus will not immediately reach its full 3.2 GW scale.
Instead, capacity and taxable investment are expected to increase as additional portions of the campus are developed.
Large AI campuses increasingly follow this model:
-
Initial site infrastructure
-
First data center buildings
-
Additional electrical capacity
-
Additional buildings
-
Full campus build-out
Our guide to how long it takes to build a data center explains why major campuses can remain under development for years.
Project Camellia Power Agreement
OpenAI is contracting with Georgia Power to supply approximately 3,200 MW.
Georgia Power says the power will be delivered in phases between 2028 and 2032.
The agreement also includes up to 1,000 MW of flexible demand response.
That means Georgia Power will have the ability under certain conditions to reduce the electricity being delivered to the OpenAI facility during periods of extreme system demand.
Georgia Power describes the arrangement as one of the largest single-facility demand-response commitments in the country.
Review Georgia Power’s official Project Camellia power agreement.
Will Georgia Residents Pay for Project Camellia’s Electricity Infrastructure?
OpenAI says Georgia residents will not subsidize the project.
The company has committed to paying the full cost of:
-
Infrastructure required to serve the campus
-
Electric service
-
Project-specific power requirements
Georgia Power and state regulators have also adopted special rules for extremely large electricity customers.
This issue extends beyond Project Camellia and has become one of the most important policy questions surrounding Georgia data center projects.
Project Camellia Water Use
OpenAI says Project Camellia will use a closed-loop cooling design intended to minimize ongoing water consumption.
Closed-loop cooling does not automatically mean zero water use.
But it can substantially reduce recurring direct cooling water compared with systems relying heavily on evaporative cooling.
This distinction is particularly important for a 3.2 GW campus.
Read our guide explaining how much water a data center uses.
Project Camellia Jobs
Effingham County and project materials have described approximately 400 permanent on-site jobs associated with the development.
Construction employment is expected to be significantly larger during the build-out period.
As with all large data center projects, those numbers should be reported separately.
Permanent employment and construction employment describe two very different economic impacts.
Read How Many Jobs Do Data Centers Create?.
Project Camellia Tax Revenue
Effingham County says Project Camellia will generate local revenue through a phased Payment in Lieu of Taxes, or PILOT, structure.
Current county projections estimate approximately:
-
2027: $2.5 million for Effingham County and $3.5 million for the school district based on current land value
-
2029: approximately $10 million annually for the county and $14 million for the school district
-
2032 full build-out: approximately $27 million annually for Effingham County and $39 million for the school district
Those are projections rather than guaranteed final tax receipts.
They depend on the project developing as currently expected.
Effingham County maintains an official Project Camellia resource center with current public information.
Google Columbia County Data Center
Full project profile: Google Columbia County Data Center: White Oak Technology Park Plans & Status
Google announced in 2026 that it plans to develop a new data center in Columbia County, Georgia.
The project is associated with the White Oak Technology Park near Appling.
Google now lists Columbia County as one of its Georgia data center locations in development.
Google’s official Georgia infrastructure timeline confirms the company announced the Columbia County development in 2026.
See Google’s official Georgia data center page.
White Oak Technology Park
The underlying White Oak Technology Park proposal is extremely large.
Public planning documents have described a multi-building data center campus covering a very large development area near:
-
Appling
-
Harlem
-
Interstate 20
The project became the subject of extensive local debate over:
-
Noise
-
Residential buffers
-
Visual impact
-
Water
-
Power infrastructure
This illustrates a pattern increasingly seen across Georgia.
Large data center projects are moving into communities that previously had little or no major hyperscale development.
Columbia County Data Center Buffers and Community Concerns
Residential proximity became a major issue during Columbia County’s review of new data center proposals.
Local officials considered requirements involving:
-
Larger buffers
-
Landscape screening
-
Berms
-
Noise controls
-
Lighting restrictions
These types of requirements are becoming increasingly common as data centers move closer to established neighborhoods.
See our guide to data center setbacks near homes.
Google LaGrange Data Center — Troup County
Full project profile: Google LaGrange Data Center: Troup County Expansion & Status
Google also announced a new LaGrange data center in 2026.
LaGrange is located in Troup County southwest of Atlanta.
Google’s official Georgia data center timeline now lists LaGrange as one of its new Georgia developments.
LaGrange Expansion
Development filings in 2026 described an additional approximately 470,000-square-foot data center building planned at the site.
The proposed building would join an existing development at the campus.
Public filings described an estimated project value of approximately $1 billion for the new building.
The expansion demonstrates that the latest Georgia data center growth is not limited to the Atlanta metro region.
Google Douglas County Data Center
Full project profile: Google Douglas County Data Center: Location, History & Water Use
Google has operated data center infrastructure in Douglas County for nearly two decades.
Google says its Georgia data center presence began in Douglas County in 2003, with its data center opening in 2007.
The company later announced a $300 million expansion in 2015.
Douglas County demonstrates that Georgia is not a newcomer to data centers.
The difference today is the scale and geographic spread of new development.
Recycled Water in Douglas County
Google also began using recycled industrial water for data center cooling in Douglas County in 2012.
This provides one example of how data centers can reduce dependence on drinking-water supplies where reclaimed-water infrastructure is available.
Meta Stanton Springs Data Center
Full project profile: Meta Stanton Springs Data Center: $1.5B Georgia Campus Explained
Meta operates another major Georgia data center campus at Stanton Springs in Newton County.
Meta reports more than:
-
$1.5 billion in investment
-
1,300 skilled trade workers at peak construction
-
200+ operational jobs
The project broke ground in 2018.
Meta continues to identify Stanton Springs as an active U.S. data center location.
Stanton Springs Water Supply
Meta says its Stanton Springs Data Center receives 100% of its operational water from the Newton County Water and Sewerage Authority and does not use groundwater for operations.
According to Meta, the company pays the costs associated with:
-
Water service
-
Sewer service
-
Necessary infrastructure serving the site
You can review Meta’s 2026 explanation of water use at Stanton Springs.
Why Does Georgia Have So Many Data Center Projects?
Georgia combines several factors that make it attractive to large data center developers.
Atlanta Fiber Connectivity
Atlanta is one of the largest telecommunications and connectivity hubs in the southeastern United States.
That provides access to:
-
Major fiber routes
-
Cloud connectivity
-
Enterprise customers
-
Regional population centers
Available Land
Projects increasingly require extremely large parcels.
Georgia offers development opportunities both:
-
Near Atlanta
-
Along major interstate corridors
-
In rural and industrial markets
-
Near Savannah
Existing Technology Infrastructure
Google and Meta have already operated substantial Georgia data center infrastructure for years.
That creates an existing ecosystem of:
-
Contractors
-
Utilities
-
Engineers
-
Technology workers
-
Fiber providers
Power Availability
Electricity has become perhaps the biggest factor of all.
Georgia Power is undertaking an enormous generation expansion as large industrial loads and data centers seek to connect to the system.
Georgia Data Center Projects and the Power Grid
The scale of new Georgia data center projects is transforming electricity planning in the state.
In December 2025, the Georgia Public Service Commission approved approximately 9,985 MW of new electric generation resources.
The PSC says approximately 80% of that new generation is expected to serve data center demand.
That equates to roughly 8 GW associated with anticipated data center growth.
The expansion illustrates just how large Georgia’s future electricity requirements could become.
Why New Generation Is Needed
Large data centers can require hundreds or thousands of megawatts.
Project Camellia alone is planned for:
3,200 MW.
Serving loads at this scale can require:
-
New power plants
-
Transmission upgrades
-
Substations
-
Transformers
-
Long-term energy contracts
Our guide to data center transmission lines explains why the grid infrastructure can extend far beyond the data center site.
Will Georgia Data Centers Raise Electric Bills?
This is one of the most important questions surrounding data center development in Georgia.
The Georgia Public Service Commission says it has adopted rules intended to prevent existing residential and small-business customers from subsidizing the cost of serving data centers.
The PSC’s current position is that:
-
Existing customers should not experience rate increases caused by new data centers
-
Large-load customers must bear appropriate costs
-
Georgia Power has financial protections associated with its new generation build-out
The Commission also approved a Georgia Power base-rate freeze extending through the end of 2028.
You can review the Georgia PSC’s Data Center Fact Sheet.
Why Cost Allocation Matters
Suppose a 1 GW data center requires:
-
New generation
-
A new substation
-
Transmission upgrades
The key question is not simply:
How much does the infrastructure cost?
It is:
Who pays for it if the project is delayed, cancelled or uses less power than expected?
That question has become central to data center regulation nationwide.
Georgia Data Centers and Demand Response
Project Camellia also demonstrates another emerging strategy: flexible electricity consumption.
Under OpenAI’s agreement with Georgia Power, the facility has committed up to 1,000 MW of demand response capability.
During certain periods of system stress, the project can reduce electricity consumption.
For data centers, flexible computing workloads can potentially allow some processing to be:
-
Delayed
-
Moved
-
Temporarily reduced
This is especially relevant to some AI workloads.
It could allow the grid to serve large computing campuses more efficiently than treating every MW as completely inflexible demand.
Georgia Data Center Projects and Water Use
Water requirements vary substantially among Georgia data center projects.
Examples already show several different approaches.
Project Camellia
OpenAI says the campus will use closed-loop cooling intended to minimize ongoing water use.
Google Douglas County
Google has used recycled industrial water for cooling at its Douglas County data center since 2012.
Meta Stanton Springs
Meta says the facility uses utility-supplied water and no operational groundwater.
These examples show why communities should not assume all data centers use water the same way.
Ask specifically for:
-
Average daily consumption
-
Peak summer consumption
-
Water source
-
Cooling technology
-
Potable vs. reclaimed water
-
Groundwater use
Read How Much Water Does a Data Center Use?.
How Many Jobs Do Georgia Data Centers Create?
Employment varies dramatically by project.
OpenAI Project Camellia
Current project materials describe approximately:
-
400 permanent on-site jobs
-
A much larger temporary construction workforce during development
Meta Stanton Springs
Meta reports approximately:
-
1,300 skilled trade workers at peak construction
-
200+ operational jobs
This pattern is common.
Construction employment can significantly exceed permanent data center employment.
Read our guide to how many jobs data centers create.
Georgia Data Center Projects and Tax Revenue
Tax revenue is one of the biggest arguments local governments make in favor of data center development.
Project Camellia provides a particularly useful current example because Effingham County has published projected revenue figures.
At full build-out, current projections estimate approximately:
-
$27 million annually for Effingham County
-
$39 million annually for the Effingham County School District
Those payments reflect the project’s negotiated tax structure and should not be applied as a generic estimate for other data centers.
Tax revenue depends heavily on:
-
Property value
-
Equipment value
-
Tax rates
-
Depreciation
-
Abatements
-
Incentives
Read our full guide to data center property tax revenue.
Georgia Data Center Projects and Community Opposition
The rapid expansion of Georgia data centers has also created increasing local debate.
Common concerns include:
-
Electricity demand
-
Water use
-
Noise
-
Residential proximity
-
Tax incentives
-
Generator emissions
-
Land consumption
-
Transparency
Effingham County
Project Camellia has generated questions about:
-
How the project was initially negotiated
-
Power infrastructure
-
Water
-
Tax incentives
-
Public review
The county has since created a dedicated public resource center and held community meetings about the proposal.
Columbia County
Residents have raised concerns about several proposed data centers involving:
-
Noise
-
Buffers
-
Visual impacts
-
Neighborhood proximity
These debates show why community review increasingly focuses not simply on whether a data center is economically beneficial, but on where the project is located and how it is designed.
Read our broader guide to community opposition to data centers.
How Close Can a Georgia Data Center Be to Homes?
There is no single statewide Georgia setback that applies identically to every data center.
Distance requirements generally depend on:
-
Local zoning
-
Project-specific approvals
-
Buffers
-
Noise rules
-
Equipment placement
This can produce very different requirements from one county to another.
Residents should examine the distance between homes and:
-
Data center buildings
-
Generators
-
Cooling equipment
-
Transformers
-
Substations
See our guide to data center setbacks.
How Large Are Georgia Data Center Projects?
The latest Georgia projects demonstrate that physical size alone is no longer enough to describe a data center.
Important project metrics include:
-
Acreage
-
Building count
-
Square footage
-
Megawatts
-
Substation count
-
Generator count
Project Camellia’s 3.2 GW electrical requirement is arguably more revealing than its building square footage.
That’s because modern AI servers can concentrate enormous amounts of computing power and electricity consumption inside individual buildings.
Read How Big Is a Data Center? Acres, Square Feet & MW Explained.
Georgia Data Center Projects and Air Permits
Large data center campuses often contain many backup generators.
Those engines can trigger state or federal air-permitting requirements.
When researching a Georgia project, search environmental records for:
-
Emergency generators
-
Diesel engines
-
Natural gas engines
-
Air-quality permits
-
Fuel limits
-
Operating-hour restrictions
EPA maintains Clean Air Act resources specifically for data centers.
How to Track a Georgia Data Center Project
Georgia provides several useful sources for identifying projects before construction begins.
1. Search Local Planning Records
Start with the city or county where the site is located.
Look for:
-
Rezoning applications
-
Site plans
-
Special-use permits
-
Planning Commission agendas
-
Development agreements
2. Search Georgia Development of Regional Impact Records
Large developments can trigger Georgia’s Development of Regional Impact, or DRI, review process.
DRI records can reveal:
-
Developer
-
Location
-
Acreage
-
Square footage
-
Traffic estimates
-
Water requirements
-
Project timeline
This process has produced valuable information about several major Georgia data center projects.
3. Search Georgia Public Service Commission Records
For very large projects, utility filings can reveal:
-
Large-load contracts
-
Generation needs
-
Customer protections
-
New power infrastructure
4. Search Georgia Power Information
Georgia Power publishes information about major large-load agreements and new generation requirements.
5. Search Environmental Permits
Look for:
-
Generator permits
-
Stormwater permits
-
Wetland impacts
-
Water withdrawals
6. Search by LLC and Property Owner
A data center may not initially be filed under Google, OpenAI or Meta.
Search:
-
Property owner
-
Developer LLC
-
Applicant
-
Engineering firm
-
Parcel number
Read our complete guide to finding data center building permits, site plans and zoning records.
Questions to Ask About a Proposed Georgia Data Center
-
Who is the actual operator?
-
How many acres are included?
-
How many buildings are planned?
-
What is the maximum MW demand?
-
What generation will serve the project?
-
Are new transmission lines required?
-
How many substations are planned?
-
Who pays for power infrastructure?
-
Can residents’ electric rates be affected?
-
What cooling system will be used?
-
How much water will the project consume?
-
Will groundwater be used?
-
How many backup generators are planned?
-
What nighttime noise limits apply?
-
What setbacks apply near homes?
-
How many permanent jobs are expected?
-
What tax incentives are being provided?
-
What is the projected net local tax revenue?
See our complete 25 data center town hall questions every community should ask.
Georgia Data Center Regions to Watch
Atlanta Metro
Atlanta remains Georgia’s core data center market because of its fiber infrastructure, population and established technology ecosystem.
Douglas County
Google’s long-running campus demonstrates the area’s importance to hyperscale infrastructure.
Stanton Springs / Newton County
Meta’s campus represents another major established hyperscale location east of Atlanta.
Columbia County / Augusta Region
Google’s planned Columbia County campus creates a significant new data center cluster east of Atlanta near Augusta.
LaGrange / Troup County
Google’s LaGrange development shows continued expansion southwest of Atlanta.
Coastal Georgia / Effingham County
Project Camellia could transform Coastal Georgia into one of the country’s most important AI infrastructure markets.
How Data Center News Tracks Georgia Data Center Projects
Whenever possible, Data Center News prioritizes primary and official sources including:
-
Georgia Public Service Commission
-
Georgia Power
-
Georgia Department of Community Affairs
-
County and municipal planning records
-
Company announcements
-
Development authority records
-
Environmental permits
-
Public meeting documents
Project information can change quickly.
A Georgia data center may be:
-
Revised
-
Expanded
-
Reduced
-
Delayed
-
Approved
-
Denied
-
Withdrawn
-
Transferred to another developer
This page will be updated as significant new information becomes available.
Frequently Asked Questions About Georgia Data Center Projects
Where are data centers being built in Georgia?
Major current data center development includes Effingham County, Columbia County, LaGrange and established markets around Atlanta, Douglas County and Stanton Springs.
What is the largest new Georgia data center project?
OpenAI’s Project Camellia is among the largest publicly announced Georgia projects, with approximately 3.2 GW of planned electrical capacity.
Where is Project Camellia?
Project Camellia is planned for the Savannah Gateway Industrial Hub in Effingham County near the Savannah region.
How much power will Project Camellia use?
OpenAI is contracting with Georgia Power for approximately 3,200 MW of capacity delivered in phases between 2028 and 2032.
Is Google building new data centers in Georgia?
Yes. Google announced new Georgia data center developments in Columbia County and LaGrange in 2026, in addition to its long-established Douglas County infrastructure.
Does Meta have a data center in Georgia?
Yes. Meta operates the Stanton Springs Data Center in Newton County.
Are Georgia residents paying for data center power infrastructure?
The Georgia Public Service Commission says it has adopted protections designed to prevent existing residential and small-business customers from subsidizing costs associated with serving new data centers.
How much new electricity generation is Georgia building for data centers?
The Georgia PSC approved approximately 9,985 MW of new generation in late 2025 and says roughly 80% of that capacity is expected to serve data center demand.
Do Georgia data centers use groundwater?
It depends on the project. Meta says Stanton Springs does not use groundwater for operations, while other facilities may use different sources and cooling technologies.
How can I find a Georgia data center project near me?
Search county planning records, Georgia Development of Regional Impact filings, Georgia Public Service Commission records, environmental permits and property records.
Bottom Line: Georgia Data Center Projects Are Moving Into Multi-Gigawatt Scale
Georgia data center projects have evolved from established Atlanta-area cloud infrastructure into some of the largest AI developments currently planned in the United States.
The state’s major projects now include:
The most important issue for Georgia’s next phase of data center growth will be power.
Nearly 10 GW of new generation has already been approved, with state regulators expecting the majority of that capacity to serve data-center-related growth.
At the same time, communities are increasingly asking questions about:
-
Electric bills
-
Water
-
Noise
-
Residential setbacks
-
Tax incentives
-
Jobs
-
Transparency
The relevant question is no longer simply whether Georgia will continue attracting data centers.
It is:
How will Georgia accommodate multi-gigawatt AI infrastructure while protecting existing communities and utility customers?
Data Center News will continue updating this Georgia data center projects tracker as major developments move through planning, construction and operation.
For nationwide coverage, visit our U.S. Data Center Projects tracker.