Indiana has rapidly become one of the Midwest’s most important emerging data center markets.
Amazon Web Services, Google, Meta and Microsoft are all developing major infrastructure in the state, with several projects measured in billions of dollars.
The scale ranges from Google’s operational Fort Wayne campus to Meta’s roughly four-million-square-foot Lebanon campus, AWS’s $11 billion St. Joseph County development and Microsoft’s expanding La Porte project.
Indiana also illustrates how modern data center development increasingly depends on electricity capacity, transmission infrastructure, water, tax policy and community agreements—not simply available land.
Last updated: September 25, 2026
Indiana Data Center Projects Tracker
| Project | Company | Location | Reported Scale | Status | Primary Source |
|---|---|---|---|---|---|
| Meta Lebanon Data Center | Meta | Lebanon, Boone County | $10B+; ~4M sq. ft.; 300+ operational jobs | Construction | Meta Lebanon announcement |
| AWS New Carlisle Data Center | AWS | New Carlisle / St. Joseph County | $11B; 1,000+ direct jobs announced | Construction / Development | AWS Indiana announcement |
| Google Fort Wayne Data Center | Fort Wayne, Allen County | $2B announced investment; up to 200 jobs | Operating | Google Indiana data centers | |
| Google Michigan City Data Center | Michigan City, LaPorte County | Former industrial site under redevelopment | Development | Google Michigan City page | |
| Google Morgan County Data Center | Morgan County | Construction began in 2026 | Construction | Google Morgan County page | |
| Microsoft La Porte Data Center | Microsoft | La Porte | $1B+ original investment; 600+ permanent jobs expected in first phase | Construction | Microsoft La Porte updates |
For nationwide coverage, see the U.S. Data Center Projects tracker.
Meta Lebanon Data Center
The Meta Lebanon Data Center is one of the largest data center developments announced in Indiana.
Meta broke ground in February 2026 on the Boone County campus.
The company says the project will include approximately:
- $10 billion+ of investment
- Roughly 4 million square feet
- Approximately 4,000 skilled-trade workers at peak construction
- More than 300 operational jobs
Meta’s official Lebanon announcement says the campus will support the company’s expanding AI and computing infrastructure.
Indiana has separately described the broader campus as covering approximately 1,500 acres and containing multiple buildings. Read the Indiana Economic Development Corporation announcement.
The scale makes the Lebanon project important not just as a real-estate development, but as a major electricity and infrastructure project.
Read the full profile: Meta Lebanon Data Center: $10B Indiana AI Campus Explained.
Meta Lebanon Energy Commitments
Meta says it has worked with Boone Power and Wabash Valley Power Alliance to prepare for the campus’s electricity requirements.
The company says it intends to pay the full cost associated with energy used by the facility rather than shifting those costs to existing customers. See Meta’s Lebanon energy commitments.
Meta has also committed to contributing $1 million annually for 20 years to the Boone County Community Trust for energy-cost assistance.
For context on electrical demand, see How Much Power Does a Data Center Use?.
Meta Lebanon Water Commitments
Meta says it plans to restore 100% of the water consumed by the campus to local watersheds and pay the full cost of water and wastewater service required for the development.
Water-restoration commitments should be distinguished from actual facility consumption.
Important measurements to watch include:
- Average daily water consumption
- Peak summer demand
- Cooling-system design
- Wastewater requirements
- Water restored elsewhere in the watershed
See Why Data Centers Use Water for more background.
Boone County Data Center Moratorium
On June 15, 2026, Boone County commissioners approved a one-year moratorium on new data center development applications in unincorporated Boone County.
The moratorium runs from June 16, 2026 through June 15, 2027. Read Boone County’s official announcement.
The geographic limitation is important.
The action is not a statewide Indiana data center ban, and it should not automatically be described as stopping Meta’s already announced Lebanon project.
The moratorium instead gives county officials time to review future land-use and development standards for new applications.
AWS New Carlisle Data Center — St. Joseph County
The AWS New Carlisle Data Center development is an approximately $11 billion Amazon Web Services project in St. Joseph County.
AWS announced the investment in 2024 and later participated in a groundbreaking near New Carlisle.
The company says the development is expected to create at least:
- 1,000 direct jobs
- More than 3,000 full-time-equivalent jobs on an annual average basis when broader supply-chain and community effects are included
Those figures measure different things and should not be treated as interchangeable.
The campus is associated with the Indiana Enterprise Center and is expected to be developed over multiple years.
Read Amazon’s official $11 billion Indiana announcement.
Read the full project profile: AWS New Carlisle Data Center: $11B Indiana Campus.
AWS Infrastructure and Development
AWS committed up to $7 million toward road infrastructure improvements surrounding the St. Joseph County project.
Large campuses of this scale can require extensive:
- Electrical substations
- Transmission infrastructure
- Road improvements
- Fiber connectivity
- Water infrastructure
- Construction staging
- Backup generation
See our guide to why data centers require new transmission infrastructure.
AWS Also Announced Another $15 Billion in Indiana
AWS later announced an additional $15 billion investment in Northern Indiana for new cloud and AI data center campuses.
That newer investment is separate from the original $11 billion St. Joseph County project.
Amazon says the additional development is expected to add approximately 2.4 GW of data center capacity across new sites.
The figures therefore should not be described as a single $26 billion New Carlisle campus.
Instead:
- $11B: St. Joseph County / New Carlisle project
- $15B: additional Northern Indiana expansion
That distinction matters when tracking individual projects.
Google Fort Wayne Data Center
The Google Fort Wayne Data Center is now operational.
Google broke ground on the $2 billion campus in 2024 near East Tillman Road and Adams Center Road in Fort Wayne.
Indiana originally said the development was expected to create up to 200 jobs. Read Indiana’s official Google Fort Wayne announcement.
Google now identifies Fort Wayne as its operating Indiana data center, while Michigan City and Morgan County remain in development. View Google’s current Indiana data center locations.
Read the full profile: Google Fort Wayne Data Center: $2B Indiana Campus & Status.
Fort Wayne Energy and Workforce Development
When announcing the facility, Google said it was collaborating with Indiana Michigan Power on clean-energy resources associated with the region’s growing electricity needs.
Google also partnered with Ivy Tech Community College and workforce organizations through its Skilled Trades and Readiness Program.
Large data centers create demand for occupations including:
- Electricians
- HVAC technicians
- Facilities technicians
- Network specialists
- Mechanical trades
- Construction workers
That workforce demand is becoming increasingly important as several hyperscale companies build simultaneously across Indiana.
Google Michigan City Data Center
The Google Michigan City Data Center is being developed at the former Federal-Mogul industrial property at 402 Royal Road.
The site was previously known through local development records as Project Maize.
Rather than constructing solely on undeveloped land, the project involves redevelopment and remediation of a long-dormant industrial site.
Google now identifies Michigan City as an official Indiana data center location in development. View Google’s Michigan City project page.
Read the full profile: Google Michigan City Data Center: Royal Road Project & Status.
Former Federal-Mogul Site
The Michigan City project is notable because of its adaptive reuse.
The property already had:
- Electrical infrastructure
- Water connections
- Wastewater access
- Industrial buildings
- Transportation access
Local project records describe an existing structure of roughly 380,000 to 400,000 square feet. See Michigan City’s Project Maize records.
Plans have also included a customer-owned electrical substation and supporting mechanical and electrical infrastructure.
Environmental Remediation
Because the property was previously industrial, site preparation has included environmental remediation.
That makes environmental records especially important for understanding the project.
Residents evaluating redevelopment of former industrial properties should review:
- Soil testing
- Groundwater records
- Cleanup plans
- Indiana Department of Environmental Management records
- Construction permits
- Site-development plans
See our guide to finding data center building permits and site plans.
Google Morgan County Data Center
Google announced its Morgan County Data Center in 2025, and construction began in 2026.
The project remains in development.
Google says AES Indiana will provide electricity to the campus.
The company also says it will pay the full cost of electricity and infrastructure upgrades required specifically to serve the facility. Read Google’s Morgan County project information.
Read the full profile: Google Morgan County Data Center: Indiana Construction & Status.
Morgan County Water Use
Google has published more detailed water information for Morgan County than is available for many hyperscale developments.
The company says:
- It will not use on-site groundwater for cooling.
- Its planned cooling system will not consume municipal water for cooling.
- Google will pay for water and wastewater upgrades required specifically for the site.
- Verified water-use information will be included in future environmental reporting.
That does not mean the entire facility will use zero water.
Domestic, construction and other operational needs may still require water.
See Why Data Centers Use Water for more context.
Noise Standards
Morgan County’s data center standards also include operational noise limits.
Google says its designs target roughly 60 to 65 dBA at the property boundary.
Noise can come from:
- Cooling equipment
- Pumps
- Fans
- Transformers
- Backup generators
See our guide to data center noise levels.
Microsoft La Porte Data Center
The Microsoft La Porte Data Center is under construction in northwest Indiana.
The project was originally announced as a roughly $1 billion development involving a 245,000-square-foot facility on approximately 489 acres. Read the City of La Porte’s original announcement.
Microsoft officially broke ground in June 2026.
The project has since grown beyond the employment assumptions in the original announcement.
Microsoft now says the first phase is expected to create more than 600 permanent Microsoft jobs, along with thousands of construction jobs. Read Microsoft’s groundbreaking announcement.
Read the full profile: Microsoft La Porte Data Center: $1B+ Indiana Campus & Status.
La Porte Construction Status
Microsoft’s 2026 construction updates say grading and site preparation are underway.
Ryan Central has been identified as the contractor handling grading work.
Current work includes preparing the site for future vertical construction. See Microsoft’s La Porte construction update.
The project should therefore be classified as under construction, not simply proposed or in early development.
Microsoft La Porte Cooling
Microsoft says the campus will use closed-loop liquid cooling technology.
Closed-loop systems can reduce ongoing water consumption because cooling water is recirculated rather than continuously evaporated.
That does not mean the campus will require no water, but cooling design can materially change the water profile of a data center.
See Why Data Centers Use Water.
Microsoft Datacenter Academy
Microsoft also announced a partnership with Ivy Tech Community College to establish its first Microsoft Datacenter Academy in Indiana.
The program is intended to build local skills for positions associated with data center operations and infrastructure.
Indiana Data Center Electricity Demand
Power availability is becoming one of the central issues shaping Indiana data center development.
The state’s major projects include:
- A Meta campus exceeding $10 billion
- An $11 billion AWS campus
- Additional AWS development expected to add 2.4 GW
- Three Google locations
- Microsoft’s growing La Porte campus
Electricity questions communities should examine include:
- Maximum MW demand
- Utility provider
- Substation requirements
- Transmission upgrades
- New generation
- Backup generators
- Infrastructure costs
- Whether existing ratepayers share upgrade costs
See How Much Power Does a Data Center Use? and Why Do Data Centers Need New Transmission Lines?.
Indiana Data Center Tax Incentives
Indiana has used data center tax policy aggressively to attract major projects.
Meta’s Lebanon agreement includes a performance-based sales-tax exemption with a long initial term and potential extensions tied to investment thresholds. See Indiana’s Meta incentive details.
Large data center incentives can involve:
- Sales-tax exemptions
- Property-tax agreements
- Infrastructure support
- Development agreements
- Workforce incentives
The value of incentives should be compared with actual long-term tax revenue rather than simply the project’s headline investment.
See How Much Tax Revenue Do Data Centers Bring to a City?.
Jobs vs. Capital Investment
Indiana’s projects provide a useful illustration of why capital investment and permanent employment should be evaluated separately.
Current announced figures include approximately:
- Meta Lebanon: 300+ operational jobs
- AWS St. Joseph County: at least 1,000 direct jobs
- Google Fort Wayne: up to 200 jobs originally announced
- Microsoft La Porte: 600+ permanent Microsoft jobs expected in the first phase
Construction employment can be much larger.
Meta alone expects approximately 4,000 workers at peak construction, while Microsoft says La Porte will generate thousands of construction jobs.
These jobs are economically significant, but temporary construction employment should not be presented as permanent data center employment.
Read our guide to data center jobs and realistic employment numbers.
Indiana Data Centers and Water
Water requirements differ significantly by cooling design.
Communities evaluating Indiana projects should look for:
- Cooling technology
- Average daily consumption
- Peak summer consumption
- Groundwater withdrawals
- Municipal water use
- Reclaimed water
- Wastewater requirements
- Infrastructure upgrades
- Watershed-restoration commitments
Meta has announced water-restoration commitments in Lebanon.
Google says Morgan County will not consume municipal water for cooling.
Microsoft says La Porte will use closed-loop liquid cooling.
Those approaches are not identical and should be evaluated separately.
See Why Data Centers Use Water for additional background.
Indiana Data Center Construction and Infrastructure
The current Indiana market includes projects at very different stages.
Operating
Under Construction / Active Development
- Meta Lebanon Data Center
- AWS New Carlisle Data Center
- Google Morgan County Data Center
- Microsoft La Porte Data Center
Development / Site Redevelopment
Status matters because an announcement does not guarantee that a campus will reach its full planned build-out.
Projects can change due to:
- Electricity availability
- Transmission timelines
- Financing
- Customer demand
- Permitting
- Environmental reviews
- Local opposition
- Construction costs
DataCenterNews.org tracks these projects as additional permits, utility filings and construction updates become available.
How to Track Indiana Data Center Projects
For new or expanding Indiana projects, monitor:
- County planning commissions
- City zoning and development records
- Indiana Economic Development Corporation
- Utility filings
- Indiana Department of Environmental Management
- Property records
- Construction updates
- Tax-incentive agreements
- Substation and transmission filings
- Local government meeting agendas
For projects that have not yet been publicly branded, see our guides to finding planned data centers near you and finding building permits and site plans.
Frequently Asked Questions
What are the largest Indiana data center projects?
Major projects include Meta’s Lebanon campus, the AWS New Carlisle project, Google facilities in Fort Wayne, Michigan City and Morgan County, and Microsoft’s La Porte campus.
AWS has also separately announced another $15 billion of investment across additional Northern Indiana data center sites.
How large is Meta’s Lebanon data center?
Meta says the Lebanon campus will span approximately 4 million square feet and represent more than $10 billion of investment.
The company expects more than 300 operational jobs and approximately 4,000 construction workers at peak.
Did Boone County ban data centers?
No.
Boone County enacted a temporary moratorium on new data center applications in unincorporated Boone County. Read Boone County’s announcement.
It is not a statewide Indiana ban.
Is Google’s Fort Wayne data center operating?
Yes.
Google currently identifies Fort Wayne as operational.
Michigan City and Morgan County remain in development. View Google’s Indiana locations.
Where is Google building data centers in Indiana?
Google currently identifies Indiana data center locations in:
Fort Wayne is operational, while Michigan City and Morgan County remain in development.
Is Google building a data center in Michigan City?
Yes.
Google has identified property on Royal Road in Michigan City for data center development.
The site is the former Federal-Mogul industrial property previously associated with Project Maize. See Google’s Michigan City project page.
Is Google building a data center in Morgan County?
Yes.
Google announced the Morgan County project in 2025 and says construction began in 2026. See Google’s Morgan County project page.
How much is AWS investing in Indiana?
AWS’s original St. Joseph County project represents approximately $11 billion of planned investment.
Amazon later announced an additional $15 billion of investment in new Northern Indiana data center campuses.
Those are separate investment programs.
Is Microsoft building a data center in La Porte?
Yes.
Microsoft broke ground on the La Porte project in June 2026.
The company says the first phase is expected to create more than 600 permanent Microsoft jobs, in addition to thousands of construction jobs. Read Microsoft’s project announcement.
Which Indiana data centers are already operating?
Among the projects tracked on this page, Google’s Fort Wayne Data Center is currently operating.
The other major campuses remain under construction or in development.
Explore Indiana Data Center Projects
Read the dedicated project profiles:
- Meta Lebanon Data Center: $10B Indiana AI Campus Explained
- AWS New Carlisle Data Center: $11B Indiana Campus
- Google Fort Wayne Data Center: $2B Indiana Campus & Status
- Google Michigan City Data Center: Royal Road Project & Status
- Google Morgan County Data Center: Indiana Construction & Status
- Microsoft La Porte Data Center: $1B+ Indiana Campus & Status
You can also browse the U.S. Data Center Projects tracker for projects in other states.