North Carolina Data Center Projects: 2026 Locations & Tracker

North Carolina data center projects are entering a new phase as artificial intelligence and cloud computing drive investment beyond the state’s established hyperscale campuses.

Google and Meta have operated major North Carolina facilities for years, while Amazon is now developing a major cloud and AI infrastructure campus in Richmond County.

The new developments show why modern data center projects increasingly need to be evaluated by their electrical capacity, substations, generators and transmission requirements rather than simply building square footage. See our guide to how big a data center can be and what MW means and our explainer on how much power a data center uses.

Last updated: September 23, 2026

Scope: This tracker covers selected major North Carolina data center projects with significant implications for power, permitting, jobs, taxes, water or surrounding communities. It is not a complete census of every facility in the state.

Dedicated North Carolina Data Center Project Profiles

For deeper coverage of each major project currently tracked on this page:


North Carolina Data Center Projects Tracker

ProjectCompany / DeveloperLocationReported ScaleStatusPrimary Source
Energy Way Tech CampusAmazon / AWSHamlet, Richmond County$10B announced investment; 500+ jobs; 588 emergency backup engines permittedPermitted / DevelopmentNC DEQ permit decision
Lenoir Data CenterGoogleLenoir, Caldwell County$4B+ invested in North CarolinaOperatingGoogle Lenoir data center page
Forest City Data CenterMetaForest City, Rutherford County$750M+ investment; 275+ operational jobsOperatingMeta U.S. data center locations

For projects across the country, see the U.S. Data Center Projects tracker.

Amazon Energy Way Tech Campus — Richmond County

Full project profile: Amazon Energy Way Tech Campus: $10B Richmond County Data Center

Amazon’s Energy Way Tech Campus near Hamlet is the most significant new North Carolina data center development currently being tracked.

North Carolina announced in June 2025 that Amazon planned approximately $10 billion of investment in cloud-computing and AI infrastructure in Richmond County, with at least 500 jobs expected. Read the North Carolina Department of Commerce announcement.

The development is located on Airport Road in Hamlet.

Amazon Air Permit and 588 Backup Engines

On August 28, 2026, the North Carolina Department of Environmental Quality issued final air-quality permits associated with the Amazon project.

Amazon’s permit allows the operation of 588 emergency backup engines. Those engines are intended primarily for outages, maintenance, testing and activation rather than routine continuous electricity production. View NC DEQ’s final Amazon permit announcement.

That distinction matters. A permitted generator count should not automatically be interpreted as the number of generators expected to operate continuously.

Duke Energy Bridge Power for the Amazon Campus

Amazon’s project also illustrates a growing data center issue: buildings can be ready before permanent electric-grid infrastructure is available.

Duke Energy Progress received a separate permit for 57 temporary bridge-power engines that can supply the campus before its permanent grid connection is complete. NC DEQ says the engines must be retired within one year after operations begin. Read the NC DEQ bridge-power permit details.

This is exactly why electrical infrastructure can determine how long it takes to build and activate a data center.

A project may have land and building approvals but still need:

  • New substations
  • Transformers
  • Transmission upgrades
  • Temporary generation
  • Backup generation
  • Utility interconnection work

See our guide to how a data center substation works.

Google Lenoir Data Center

Full project profile: Google Lenoir Data Center: $4B+ North Carolina Campus Explained

Google’s Lenoir facility is one of North Carolina’s longest-running hyperscale data center operations.

Google says it has invested more than $4 billion in North Carolina since establishing the Lenoir campus and has operated there since 2008. View Google’s official Lenoir data center page.

Lenoir demonstrates that North Carolina’s data center industry predates the current AI development boom.

What has changed is scale.

New AI campuses are increasingly measured in hundreds of megawatts or even gigawatts rather than only acres or square feet.

Meta Forest City Data Center

Full project profile: Meta Forest City Data Center: $750M+ North Carolina Campus Explained

Meta operates another major established North Carolina campus in Forest City.

Meta reports more than $750 million of investment in the facility and more than 275 operational jobs once completed. See Meta’s official U.S. data center statistics.

That comparison is useful because data centers frequently support far more workers during construction than during long-term operation.

Our guide to how many jobs data centers actually create explains the difference between:

  • Peak construction employment
  • Permanent operations jobs
  • Contractors
  • Indirect or modeled economic employment

North Carolina Data Centers and Electricity Demand

Power availability is becoming one of the defining constraints on North Carolina data center development.

Amazon’s Richmond County project combines permanent grid service, hundreds of emergency generators and temporary generation while permanent infrastructure is completed.

When researching a project, look for:

  • Maximum MW demand
  • Initial-phase MW demand
  • Full-build-out demand
  • Utility provider
  • Planned substations
  • Transmission upgrades
  • Backup-generator count
  • Temporary generation
  • Minimum utility-payment commitments

Our explainer on why data centers need new transmission lines explains how large loads can affect regional infrastructure.

Will North Carolina Data Centers Raise Electric Bills?

There is no responsible statewide yes-or-no answer.

The critical issue is who pays for the infrastructure created by a new large load.

Questions to examine include:

  • Does the developer pay for dedicated infrastructure?
  • Are minimum payments required?
  • Who bears the cost if a project is delayed?
  • Who pays if projected electricity demand never materializes?
  • Are upgrades useful to the broader grid or primarily to the data center?

Those details matter more than simply knowing how many megawatts a project requests.

North Carolina Data Centers and Water

Water consumption varies significantly by cooling system.

Before drawing conclusions about a particular North Carolina facility, look for:

  • Cooling technology
  • Average daily water demand
  • Peak summer demand
  • Potable vs. reclaimed water
  • Groundwater withdrawals
  • Closed-loop cooling
  • Cooling-tower permits

Our guide to why data centers use water and how cooling works explains why two similarly sized facilities can have very different water profiles.

Data Center Jobs in North Carolina

Amazon says its Richmond County project will create at least 500 jobs, while Meta reports more than 275 operational jobs at Forest City.

Those figures should not be directly compared with construction employment.

When evaluating a project, communities should request separate estimates for:

  1. Peak construction workers
  2. Permanent company employees
  3. Contractors
  4. Indirect jobs
  5. Temporary infrastructure work

Data Center Tax Revenue and Incentives

Large capital investments can materially increase a local property-tax base, but a headline investment figure does not equal annual tax revenue.

Actual revenue depends on:

  • Taxable assessed value
  • Personal-property treatment
  • Depreciation
  • Local rates
  • Incentive agreements
  • Exemptions
  • Infrastructure reimbursements

For context, see our guide to how much tax revenue data centers actually bring to communities.

Community Concerns in Richmond County

Amazon’s Richmond County permitting process attracted enough public interest that NC DEQ held a public hearing before issuing the permits.

The agency says additional testing, monitoring, recordkeeping and reporting requirements were added following public review. Read NC DEQ’s final permit decision.

Common concerns surrounding major North Carolina data center projects may include:

  • Electricity demand
  • Generator emissions
  • Noise
  • Water use
  • Residential proximity
  • New transmission infrastructure
  • Tax incentives
  • Permanent employment

Our guide to community opposition to data centers covers these issues nationally.

How to Track a North Carolina Data Center Project

Residents should check several different record systems.

Local Planning and Zoning

Look for:

  • Rezoning cases
  • Special-use permits
  • Site plans
  • Planning-board agendas
  • Development agreements
  • Parcel consolidations

North Carolina DEQ

Environmental permits can reveal equipment that may not appear in economic-development announcements.

Amazon’s Richmond County air permit, for example, disclosed the number of emergency engines.

Utility Records

Look for:

  • Substations
  • Transmission construction
  • Large-load agreements
  • Temporary generation
  • Utility infrastructure plans

Property Records

Projects frequently appear under an LLC or development company before the end user is publicly identified.

Our guides to finding out whether a data center is planned near you and finding data center building permits and site plans explain the process.

North Carolina Data Center Regions to Watch

Richmond County

Amazon’s Energy Way Tech Campus makes Richmond County one of North Carolina’s most important emerging AI infrastructure markets.

Caldwell County

Google’s Lenoir campus remains a major established hyperscale location.

Rutherford County

Meta’s Forest City campus remains another important western North Carolina data center anchor.

Additional Duke Energy Territory

Future development is likely to depend heavily on where utilities can deliver large blocks of electricity within acceptable construction timelines.

Frequently Asked Questions

Where are major data centers located in North Carolina?

Major locations currently tracked include Richmond County, Lenoir in Caldwell County and Forest City in Rutherford County.

What is Amazon building in Richmond County?

Amazon plans a major cloud and AI infrastructure campus near Hamlet. North Carolina announced approximately $10 billion of planned investment and at least 500 jobs. See the official state announcement.

How many generators will Amazon’s North Carolina data center have?

Amazon’s final air permit allows 588 emergency backup engines. Duke Energy separately received authorization for 57 temporary bridge-power engines. See NC DEQ’s final permit announcement.

Does Google have a North Carolina data center?

Yes. Google operates its Lenoir campus and reports more than $4 billion of investment in North Carolina. Google Lenoir data center.

Does Meta have a data center in North Carolina?

Yes. Meta operates its Forest City campus and reports more than $750 million invested there. Meta data center locations.


Bottom Line: North Carolina Data Center Projects Are Expanding Beyond Established Campuses

North Carolina’s data center market now combines long-established hyperscale campuses with a new generation of AI and cloud infrastructure projects.

The major projects currently tracked include:

The biggest issues to watch are power availability, new substations and transmission infrastructure, backup generation, water use, permanent employment, tax revenue and the timing of full utility service.

Data Center News will continue updating this North Carolina data center projects tracker as major projects move through permitting, construction and operation.

For nationwide coverage, visit the U.S. Data Center Projects tracker.