Ohio Data Center Projects: 2026 Locations & Tracker

Ohio has become one of the country’s most significant hyperscale data center markets.

Amazon Web Services, Google, Meta and Microsoft are all investing in facilities across the state, with central Ohio remaining the primary cluster and new development extending into additional counties.

At the same time, rapid load growth has pushed electricity infrastructure and cost allocation to the center of Ohio’s data center debate.

Last updated: September 14, 2026

Ohio Data Center Projects Tracker

Project / MarketCompanyLocationReported ScaleStatusPrimary Source
Fayette County ExpansionAWSFayette County~$5B first new siteDevelopmentAWS Ohio announcement
Ohio CampusesGoogleNew Albany, Columbus, Lancaster$20B+ invested statewideOperating / ExpandingGoogle Ohio data center page
Bowling Green Data CenterMetaMiddleton Township$800M+; 715,000 sq. ft.ConstructionMeta Bowling Green announcement
New Albany Data CenterMicrosoftNew AlbanyMulti-phase campusConstruction / DevelopmentMicrosoft construction updates

AWS Fayette County Expansion

AWS announced plans for another $10 billion of Ohio cloud and AI infrastructure investment, with the potential for as many as eight new sites by 2030.

The first new site is in Fayette County, where AWS says it expects approximately $5 billion of investment. Read AWS’s Ohio infrastructure announcement.

This builds on billions of dollars AWS had already announced for Ohio.

Google Ohio Data Centers

Google operates data center infrastructure in:

  • New Albany
  • Columbus
  • Lancaster

Google says it has invested more than $20 billion in Ohio since breaking ground in New Albany in 2019. View Google’s official Ohio data center page.

This concentration makes central Ohio a true hyperscale cluster rather than a collection of unrelated individual facilities.

Meta Bowling Green Data Center

Meta is building a 715,000-square-foot data center in Middleton Township near Bowling Green.

Meta says the project will represent more than $800 million of investment, support more than 1,000 construction workers at peak and create approximately 100 operational jobs. Read Meta’s Bowling Green announcement.

The difference between 1,000 construction workers and roughly 100 permanent jobs is why construction and operational employment should always be separated.

See How Many Jobs Do Data Centers Create?.

Microsoft New Albany Data Center

Microsoft continues developing its New Albany campus.

Microsoft’s July 2026 update says the current site-work phase was nearing completion, although limited work could continue and additional future phases are planned. Read Microsoft’s New Albany construction update.

The project therefore should not simply be labeled completely finished.

Ohio Data Centers and the Power Grid

Rapid data center expansion has forced Ohio utilities and regulators to address a basic question:

Who pays for grid infrastructure built for extremely large new customers?

Large campuses may require:

  • New substations
  • Transmission expansion
  • Transformers
  • Distribution upgrades
  • Generation capacity

See our guides to data center substations and why new transmission lines may be required.

AEP Ohio Data Center Tariff

Ohio regulators approved a special AEP Ohio tariff for qualifying large data center customers.

The Ohio Consumers’ Counsel says the tariff requires new large data centers to pay for at least 85% of their contracted electricity capacity for up to 12 years, even if actual usage is lower. Read the Ohio Consumers’ Counsel data center fact sheet.

The structure is designed to reduce the risk that utilities build expensive infrastructure for a customer that later reduces, delays or cancels its project.

Will Ohio Data Centers Raise Electric Bills?

The existence of large new loads does not automatically establish that a particular residential rate increase was caused by data centers.

The more useful question is cost allocation.

Communities should examine:

  • Infrastructure directly attributable to a project
  • Minimum electricity-payment commitments
  • Transmission cost allocation
  • Distribution upgrades
  • Stranded-cost protections
  • Utility forecasting assumptions

The Ohio Consumers’ Counsel explicitly advocates for policies requiring large data center customers to bear infrastructure costs associated with serving their facilities. See OCC guidance for Ohio communities.

How Big Are Ohio’s New Data Centers?

There is no single statewide size.

Projects range from individual buildings to multi-campus networks operated by the world’s largest cloud and technology companies.

Because power is increasingly the binding constraint, compare projects using:

  • MW at opening
  • MW at full build-out
  • Square footage
  • Building count
  • Acreage
  • Substation capacity

See How Big Is a Data Center?.

Ohio Data Center Tax Revenue

Major projects can expand local tax bases, but investment totals should not be confused with tax collections.

Actual fiscal impact depends on:

  • Property valuation
  • Equipment treatment
  • Tax abatements
  • Depreciation
  • School agreements
  • Infrastructure commitments

Read How Much Tax Revenue Do Data Centers Bring to a City?.

Ohio Data Center Regions to Watch

New Albany

Google and Microsoft both have major infrastructure in New Albany, while Meta also has an established Ohio presence in the area.

Columbus

The broader Columbus market remains central to Ohio’s hyperscale cluster.

Lancaster

Google identifies Lancaster as another of its Ohio data center communities.

Fayette County

AWS’s planned approximately $5 billion first new site makes Fayette County a major emerging market.

Bowling Green / Middleton Township

Meta’s $800 million-plus campus is establishing another significant data center location in northwest Ohio.

How to Track Ohio Data Center Projects

Monitor:

  1. County and municipal planning records
  2. Public Utilities Commission of Ohio proceedings
  3. AEP Ohio tariff and large-load cases
  4. Property records
  5. Building permits
  6. Environmental permits
  7. Company construction updates

Our guide to finding data center building permits, zoning records and site plans explains what to search.

Frequently Asked Questions

Where are Google’s Ohio data centers?

Google identifies New Albany, Columbus and Lancaster as Ohio data center locations. Google Ohio data center page.

How much is AWS investing in Ohio?

AWS announced another $10 billion of planned Ohio infrastructure investment, with approximately $5 billion expected at the first new Fayette County site. AWS Ohio announcement.

What is Ohio’s special data center electricity rule?

AEP Ohio’s tariff requires qualifying new large data centers to pay for at least 85% of contracted capacity for up to 12 years. Ohio Consumers’ Counsel explanation.

How large is Meta’s Bowling Green data center?

Meta says the campus will cover approximately 715,000 square feet and involve more than $800 million of investment. Meta Bowling Green project page.