South Carolina is becoming a significant hyperscale and high-performance computing market, with major projects from Google, Meta, Cielo Digital Infrastructure and NorthMark Strategies.
Projects range from conventional utility-connected hyperscale campuses to facilities proposing substantial on-site electricity generation.
That makes South Carolina a useful example of why modern projects need to be evaluated across land, power, water, permitting and community impact—not simply investment totals.
Last updated: September 24, 2026
South Carolina Data Center Projects Tracker
| Project | Company | Location | Reported Scale | Status | Primary Source |
|---|---|---|---|---|---|
| Valara High Performance Compute Center | NorthMark / Valara | Spartanburg | $2.8B announced investment | Development / Permitted | SCDES Valara project page |
| Cielo Cherokee County Data Center | Cielo Digital Infrastructure | Gaffney | $2.1B; four ~400,000-sq.-ft. facilities | Development | South Carolina announcement |
| Google Dorchester County Data Centers | Ridgeville & St. George | Original $2B announcement; 200 operational jobs | Under Construction | Google South Carolina investment update | |
| Google Moncks Corner Data Center | Moncks Corner | Original $1.3B expansion; part of newer statewide investment | Operating / Expanding | Google South Carolina investment update | |
| Meta Aiken Data Center | Meta | Aiken County | $800M+; 715,000 sq. ft.; ~100 jobs | Construction / Development | Meta Aiken announcement |
See the national Data Center Projects tracker for projects in other states.
Valara High Performance Compute Center — Spartanburg
The Valara data center in Spartanburg is a high-performance computing project associated with NorthMark Strategies and Valara Holdings.
NorthMark announced the project in April 2025 with approximately $2.8 billion of investment and at least 27 permanent jobs.
Read the official South Carolina project announcement.
Valara is particularly notable because of the scale of its planned on-site electricity generation.
South Carolina Department of Environmental Services records show that an initial air permit issued in September 2025 authorized 24 permanent natural-gas-fired generators, each rated at approximately 2.1 MW.
The permit was later amended in April 2026 to allow 21 temporary natural-gas generators, subject to operating restrictions.
Valara’s Second Air Permit Approved
Valara subsequently applied for a second air permit involving 11 natural-gas-fired turbines.
On September 18, 2026, SCDES approved the Synthetic Minor Air Construction Permit.
The approved equipment includes:
- Five 17 MW simple-cycle natural-gas turbines
- Six 54 MW simple-cycle natural-gas turbines
- Selective catalytic reduction emissions controls
- Oxidation catalyst emissions controls
The turbine nameplate ratings total approximately 409 MW.
That figure should not be interpreted as the data center’s guaranteed or continuous electricity consumption, but it demonstrates the scale of electrical infrastructure associated with the project.
SCDES issued the permit after technical review, air-quality modeling, a public hearing and an extended public-comment period.
View the current SCDES Valara permitting page.
For a detailed project profile, including the power system and permitting history, see our Valara Data Center: $2.8B Spartanburg HPC Project & Status.
Cielo Cherokee County Data Center — Gaffney
The Cielo Cherokee County data center is a planned $2.1 billion campus on Ford Road in Gaffney.
Cielo Digital Infrastructure plans approximately:
- $2.1 billion of investment
- Four data center facilities
- Roughly 400,000 square feet per building
- Approximately 1.6 million square feet combined
- A dedicated electrical substation
- Approximately 30 permanent jobs
Initial operations were announced for approximately the end of 2028.
Read South Carolina’s official Cielo announcement.
Why the Cielo Substation Matters
The dedicated electrical substation is one of the project’s most important infrastructure components.
Large data center campuses can require hundreds of megawatts of electricity, and electrical infrastructure can determine when—or whether—a campus reaches its planned capacity.
A dedicated substation can help:
- Transform transmission-level voltage
- Distribute power throughout the campus
- Connect multiple buildings
- Support phased development
- Improve electrical redundancy
See our explainer on data center substations for more background.
For the full project timeline, location and development details, see Cielo Cherokee County Data Center: $2.1B Gaffney Campus.
Google Dorchester County Data Centers
Google is developing two major Dorchester County data center campuses in South Carolina:
- Pine Hill Business Campus in Ridgeville
- Winding Woods Commerce Park in St. George
The projects were originally announced in 2024 as approximately $2 billion of new investment with roughly 200 operational jobs expected across the two campuses.
The facilities are now under construction.
Google’s Newer $9 Billion South Carolina Investment
Google significantly expanded its South Carolina investment plans after the original Dorchester announcement.
In October 2025, Google announced a new $9 billion investment in South Carolina through 2027.
The company said that investment would support:
- Continued construction of the two Dorchester County data centers
- Expansion of the existing Berkeley County campus
- Cloud infrastructure
- AI infrastructure
- Workforce-development initiatives
The $9 billion figure covers Google’s broader South Carolina infrastructure program and should not be interpreted as $9 billion assigned solely to the Dorchester County projects.
Read Google’s $9 billion South Carolina investment announcement.
For more on the two sites, see Google Dorchester County Data Centers: Ridgeville & St. George.
Google Moncks Corner Data Center — Berkeley County
Google is also continuing to expand its long-established Moncks Corner data center in Berkeley County.
Google began developing the Berkeley County campus in 2007, making it one of the company’s earlier major U.S. data center locations.
In 2024, South Carolina announced another $1.3 billion expansion at the campus.
That announcement accompanied Google’s original $2 billion Dorchester County development plan, creating an approximately $3.3 billion expansion announcement at that time.
Google has since superseded that earlier statewide investment framing with its newer $9 billion South Carolina investment plan through 2027.
The newer program includes continued expansion of Berkeley County along with construction of the two Dorchester County campuses.
This means the Lowcountry is increasingly functioning as a regional Google data center cluster, rather than a collection of isolated projects.
Read Google’s current South Carolina investment announcement.
See the complete project profile at Google Moncks Corner Data Center: Berkeley County Expansion.
Meta Aiken Data Center
Meta is developing its first South Carolina data center at Sage Mill Industrial Park in Aiken County.
The Meta Aiken data center represents:
- More than $800 million of investment
- Approximately 715,000 square feet
- Roughly 100 permanent operational jobs
- More than 1,000 construction workers expected during peak construction
- Computing infrastructure optimized for AI workloads
Meta broke ground on the project in 2024.
The company says the campus will become part of its global infrastructure supporting platforms and artificial-intelligence workloads.
Meta also plans to work with Aiken Electric Cooperative to support additional renewable energy on the grid.
Read Meta’s official Aiken Data Center announcement.
For more details on construction, jobs, AI infrastructure and the planned opening, see Meta Aiken Data Center: $800M South Carolina AI Campus.
South Carolina Data Centers and Electricity
South Carolina’s current projects illustrate several different approaches to supplying electricity to large data centers.
Valara is pursuing extensive on-site natural-gas generation.
Cielo plans a dedicated electrical substation.
Google and Meta are developing large utility-connected hyperscale campuses supported by regional electrical infrastructure.
When evaluating a proposed data center, communities should try to establish:
- Maximum expected MW demand
- Utility provider
- Substation requirements
- Transmission upgrades
- Backup generators
- On-site generation
- Minimum payment commitments
- Who pays for infrastructure upgrades
See our guides to data center electricity demand and why data centers require new transmission infrastructure.
South Carolina Data Centers and Air Quality
Valara demonstrates why environmental permit records can provide information that may not appear in economic-development announcements.
Air permits can disclose details including:
- Generator count
- Generator size
- Fuel type
- Turbine capacity
- Permitted operating conditions
- Emissions controls
- Temporary power equipment
SCDES maintains a dedicated Valara environmental project page because of the project’s permitting requirements and public interest.
The agency approved Valara’s second Synthetic Minor Air Construction Permit on September 18, 2026, authorizing 11 simple-cycle natural-gas turbines.
Jobs: Investment Does Not Equal Employment
South Carolina’s projects illustrate why investment and permanent employment should be evaluated separately.
Reported permanent employment includes approximately:
- Valara: at least 27 jobs
- Cielo: 30 jobs
- Google Dorchester County: 200 operational jobs
- Meta Aiken: approximately 100 operational jobs
These projects involve billions of dollars of capital investment but comparatively small permanent operating workforces.
That is partly because much of a data center’s investment goes toward:
- Servers and computing equipment
- Electrical systems
- Cooling infrastructure
- Buildings
- Networking equipment
- Backup power
- Utility infrastructure
Construction employment can be much higher during development but should not be confused with permanent operational employment.
See our guide explaining how many jobs data centers create.
South Carolina Data Centers and Water
Cooling systems can vary substantially between data center projects.
Communities evaluating a proposed facility should request information about:
- Average daily water consumption
- Peak summer consumption
- Cooling-system design
- Reclaimed-water availability
- Groundwater use
- Closed-loop cooling
- Planned infrastructure upgrades
A data center’s available water allocation should not automatically be interpreted as its expected daily consumption.
Cooling technology, climate, server density and operating conditions can significantly affect actual water demand.
See Why Data Centers Use Water for more technical background.
Community Concerns
Valara’s air-permit process generated significant community interest.
SCDES held a public hearing in Spartanburg in June 2026 and extended the public-comment period through July 31 before issuing the final permit decision in September.
Common questions surrounding major South Carolina data center developments include:
- Air emissions
- Natural-gas generation
- Noise
- Grid demand
- Water use
- Residential proximity
- Permanent jobs
- Tax incentives
- Utility infrastructure costs
- Construction traffic
For a broader framework, see Community Opposition to Data Centers and our 25 Questions to Ask at a Data Center Town Hall.
How to Track South Carolina Data Center Projects
Major data center announcements often provide only part of the information needed to understand a development.
For more detail, check:
- South Carolina Department of Environmental Services permits
- County planning and zoning records
- Utility and regulatory filings
- South Carolina Department of Commerce announcements
- Property ownership records
- Development agreements
- Building and site-development permits
- Public meeting agendas and minutes
Environmental permits can reveal generators, turbines and emissions equipment.
Planning records can reveal acreage, setbacks and building dimensions.
Utility filings can provide insight into substations, transmission infrastructure and projected electrical demand.
Our guides to finding data center building permits and site plans and finding a data center planned near you provide a step-by-step research process.
Frequently Asked Questions
Where are data centers being built in South Carolina?
Major current data center development includes projects in Spartanburg County, Cherokee County, Dorchester County, Berkeley County and Aiken County.
These include projects from Valara/NorthMark Strategies, Cielo Digital Infrastructure, Google and Meta.
What is the Valara data center?
The Valara data center is a high-performance computing development in Spartanburg associated with NorthMark Strategies and Valara Holdings.
The project represents approximately $2.8 billion of announced investment and includes substantial planned on-site natural-gas electricity generation.
Has Valara’s 11-turbine permit been approved?
Yes.
The South Carolina Department of Environmental Services approved the second Synthetic Minor Air Construction Permit on September 18, 2026.
The permit authorizes construction and operation of five 17 MW and six 54 MW natural-gas-fired turbines.
View the current Valara permit status.
How large is Cielo’s South Carolina data center?
The Cielo Cherokee County data center is planned to include four approximately 400,000-square-foot facilities, totaling roughly 1.6 million square feet, along with an associated electrical substation.
The announced investment is approximately $2.1 billion.
Where is Google building data centers in South Carolina?
Google operates and is expanding its existing data center campus in Moncks Corner in Berkeley County.
It is also building two new campuses in Ridgeville and St. George in Dorchester County.
Google announced a new $9 billion South Carolina investment through 2027 supporting continued construction in Dorchester County and further expansion in Berkeley County.
Is Meta building a data center in South Carolina?
Yes.
The Meta Aiken data center is under development at Sage Mill Industrial Park in Aiken County.
Meta says the approximately 715,000-square-foot facility represents more than $800 million of investment and will support approximately 100 operational jobs once completed.
Which South Carolina data center has on-site power generation?
The Valara High Performance Compute Center in Spartanburg has received permits covering substantial natural-gas-fired on-site electricity generation.
Its approved equipment includes permanent generators and 11 simple-cycle combustion turbines.
How can residents find a data center proposed near them?
Start with county planning records, environmental permits, utility filings, property records and local government meeting agendas.
Our guide to finding a data center planned near you explains the process in more detail.
Continue Tracking South Carolina Projects
Data center development can change rapidly as projects move through permitting, utility planning, construction and commissioning.
DataCenterNews.org tracks major South Carolina developments as new public records, permit decisions and project announcements become available.
Explore the dedicated profiles:
- Valara Data Center — Spartanburg
- Cielo Cherokee County Data Center — Gaffney
- Google Dorchester County Data Centers — Ridgeville & St. George
- Google Moncks Corner Data Center — Berkeley County
- Meta Aiken Data Center
You can also browse the U.S. Data Center Projects tracker for projects in other states.