Texas data center projects are expanding rapidly as artificial intelligence, cloud computing and hyperscale development drive unprecedented demand for new digital infrastructure.
Major technology companies including Microsoft, Google, Meta and Amazon are developing or expanding data center campuses across the state, with projects ranging from individual buildings to multi-gigawatt AI campuses.
This tracker follows major data centers in Texas, including projects that are operating, under construction, registered for construction or moving through development.
Last updated: September 21, 2026
Data center projects change frequently. Building sizes, investment figures, electrical requirements and completion dates below reflect the latest publicly available information that could be verified at the time of publication.
Texas Data Center Projects: Quick Navigation
Dedicated Texas Project Profiles
Texas Tracker Topics
Texas Data Center Projects Tracker
The table below highlights several major current Texas data center projects being tracked by Data Center News.
This is not a complete inventory of every data center in Texas. The state has a rapidly growing pipeline of hyperscale, colocation, AI and cloud infrastructure.
| Project | Company | Location | Reported Scale | Status |
|---|---|---|---|---|
| Pecos AI Data Center Campus | Microsoft | Pecos | Approx. 2 GW planned capacity | Development |
| Pecos County Data Center | Amazon Data Services | Fort Stockton / Pecos County | At least 2 registered 189,060-sq.-ft. buildings | Registered / Construction |
| Google Texas Data Centers | Armstrong & Haskell Counties | Part of $40 billion Texas investment through 2027 | Development | |
| Temple Data Center | Meta | Temple | $1.2B+ investment | Operating |
| El Paso Data Center | Meta | El Paso | 1 GW planned capacity; $10B+ investment | Under Construction |
| SAT82 | Microsoft | Castroville / Medina County | Multiple construction packages; one filing approx. 244,676 sq. ft. | Registered / Construction |
| SAT93 | Microsoft | Medina County | Approx. 245,000 sq. ft. | Registered / Future Construction |
| Project Eagle | Amazon Data Services | Boling / Wharton County | Large multi-building campus; at least 10 registered 189,060-sq.-ft. buildings identified | Registered / Construction |
| Floyd County Data Center | Amazon Data Services | Floydada | 189,060-sq.-ft. registered building | Registered / Construction |
For major projects elsewhere in the country, visit our U.S. Data Center Projects tracker.
Project names in the table link to dedicated Data Center News project profiles where deeper source-backed coverage is available. Those profiles are updated separately as permitting, construction, utility and company information changes.
Microsoft Pecos AI Data Center Campus
Read the full Microsoft Pecos Data Center project profile.
Microsoft announced one of the largest new Texas data center projects in June 2026: a major AI and cloud data center campus in Pecos.
The company says the project will add approximately 2 gigawatts of data center capacity.
That equals:
-
2,000 megawatts
-
2 million kilowatts
Microsoft described the project as one of the largest single capacity additions in its history.
A Multi-Year Development
Microsoft says the Pecos campus represents a multibillion-dollar investment expected to develop over approximately five to seven years.
The project is expected to support more than:
-
6,000 construction jobs at peak build-out
-
Hundreds of permanent operational jobs
Microsoft announced the project in its official June 2026 overview of the Pecos data center campus.
Why 2 GW Matters
A 2 GW campus illustrates how dramatically AI is changing the scale of data center development.
Large data centers were historically measured in tens of megawatts.
The newest AI campuses are increasingly measured in:
-
Hundreds of megawatts
-
1 gigawatt
-
Multiple gigawatts
For context, read our guide explaining how much power a data center uses.
Amazon Pecos County Data Center — Fort Stockton
Read the full Amazon Pecos County Data Center project profile.
Amazon Data Services has also registered major new construction in Pecos County.
Texas Department of Licensing and Regulation records identify at least two data center buildings at:
6000 TX-18, Fort Stockton, Texas
Building A
State records list:
-
189,060 square feet
-
$300 million estimated construction cost
-
New construction
-
Amazon Data Services as owner
Building B
A second project registration at the same address lists another:
-
189,060 square feet
-
$300 million estimated construction cost
-
New data center building
That means the two registered buildings alone represent approximately:
-
378,120 square feet
-
$600 million in listed construction cost
These figures come from official Texas Department of Licensing and Regulation project records.
See the official Pecos County Building B registration.
Google Texas Data Centers — Armstrong & Haskell Counties
Read the full Google Texas Data Centers project profile.
Google is undertaking one of the largest cloud and AI infrastructure investment programs in Texas.
In November 2025, Google announced plans to invest approximately $40 billion in Texas through 2027.
The investment includes new data center campuses in:
-
Armstrong County
-
Haskell County
Google also continues to expand its broader Texas infrastructure footprint.
Haskell County Data Center and Energy Infrastructure
Google says one of its new Haskell County data centers will be developed alongside a new:
-
Solar power plant
-
Battery storage facility
The company says it has contracted more than 6,200 MW of new energy generation and capacity in Texas through power purchase agreements.
Google announced the projects as part of its official $40 billion Texas infrastructure investment.
Workforce Development
Google also announced support for training more than:
-
Existing electrical workers
-
1,700 apprentices
through 2030.
This highlights an increasingly important issue in large data center markets: the availability of skilled electricians and construction labor.
Meta Temple Data Center
Read the full Meta Temple Data Center project profile.
Meta’s Temple Data Center became operational in July 2026.
Meta says the facility is its first AI-optimized data center to begin serving production traffic.
The project represents more than:
-
$1.2 billion in investment
-
1,200 skilled trade workers at peak construction
-
Almost 100 operational jobs
Meta announced that the Temple Data Center began serving traffic on July 22, 2026.
Construction Jobs vs. Permanent Jobs
Temple provides a useful real-world example of the employment pattern associated with data centers.
The project supported roughly:
-
1,200 workers during peak construction
-
100 permanent operational roles
That does not make the permanent jobs insignificant.
It demonstrates why communities should never combine construction jobs and operational jobs into one headline number.
Read our guide to how many jobs data centers create.
Meta El Paso Data Center
Read the full Meta El Paso Data Center project profile.
Meta is also building a significantly larger Texas campus in El Paso.
Meta reports that its El Paso data center represents more than:
-
$10 billion in investment
-
4,000 skilled trade workers at peak construction
-
300+ operational jobs once completed
The company broke ground on the project in 2025.
The scale of the project places El Paso among the largest Meta infrastructure investments currently underway in the United States.
Meta Fort Worth Data Center
Texas is not a new market for Meta.
The company’s Fort Worth data center dates to a 2015 groundbreaking and represents more than:
-
$1.5 billion in investment
-
1,200 skilled trade workers at peak construction
-
200+ operational jobs
Together, Fort Worth, Temple and El Paso demonstrate how Texas has evolved from an established data center market into a major AI infrastructure hub.
Microsoft Medina County Data Center Projects
Microsoft also has major new registered data center construction west of San Antonio in Medina County.
Microsoft SAT82 — Castroville
Read the full Microsoft SAT82 Data Center project profile.
Texas state records describe SAT82 as a new Microsoft data center at or near Castroville.
One project registration lists approximately:
-
244,676 square feet
-
$482.6 million estimated construction cost
-
One-story data center
-
Five colocation areas
The registered construction schedule runs from 2026 into 2028.
A separate SAT82 registration also describes another approximately 195,670-square-foot data center component.
This suggests the broader site involves multiple construction packages rather than one simple building permit.
Microsoft SAT93 — Medina County
Read the full Microsoft SAT93 Data Center project profile.
Microsoft has also registered SAT93.
State records describe it as:
-
A one-story data center
-
Approximately 245,000 square feet
-
Located on a greenfield site
-
Planned construction beginning in 2027
Texas permit records are particularly useful for uncovering projects like SAT93 before they become major public announcements.
Read our guide to finding data center building permits, site plans and zoning records.
Amazon Project Eagle — Wharton County
Read the full Amazon Project Eagle Data Center project profile.
Amazon Data Services has registered a large multi-building data center campus in Wharton County under the name Project Eagle.
Texas Department of Licensing and Regulation records now identify at least 10 Project Eagle building registrations — Buildings A through H, plus J and K — associated with the Boling-area campus. The identified primary building registrations are generally listed at approximately:
-
189,060 square feet per building
-
$300 million estimated construction cost per building
-
Amazon Data Services as owner
Across 10 identified 189,060-square-foot registrations, that represents approximately 1.89 million square feet of registered building area. The listed construction-cost figures total approximately $3.0 billion, although those permit-level estimates should not automatically be treated as Amazon’s complete campus investment because land, servers, electrical infrastructure and future phases may be accounted for separately.
The campus is being developed in phases, and additional registrations may appear as the project advances. Review the official Texas Project Eagle Building B registration as one example of the state construction records used to track the development.
Amazon Floyd County Data Center — Floydada
Read the full Amazon Floyd County Data Center project profile.
Amazon Data Services is also associated with a new registered data center in Floyd County.
The project is currently listed in Texas state records as a Confidential Data Center.
The registered Building A includes:
-
Location: Floydada
-
189,060 square feet
-
$300 million estimated construction cost
-
Amazon Data Services as owner
The registration lists construction running from 2026 into 2027.
The project demonstrates why searching state permit databases can uncover major data center development even when the project does not yet have a recognizable public brand name.
Why Does Texas Have So Many Data Center Projects?
Texas offers several characteristics that are especially attractive to hyperscale and AI developers.
Large Amounts of Land
Large AI campuses may require hundreds of acres for:
-
Data center buildings
-
Substations
-
Generators
-
Cooling infrastructure
-
Roads
-
Future expansion
Large Energy Market
Texas has one of the largest electricity markets in the country.
That provides opportunities to develop data centers close to:
-
Natural gas generation
-
Wind
-
Solar
-
Battery storage
Major Fiber and Technology Markets
Texas contains major population and technology centers including:
-
Dallas-Fort Worth
-
Austin
-
San Antonio
-
Houston
Expansion Potential
Developers searching for multi-building campus locations can often find larger greenfield parcels than are available in mature markets such as Northern Virginia.
Texas Data Center Projects and the Power Grid
Electricity is likely the most consequential issue surrounding future Texas data center projects.
ERCOT reported in early 2026 that more than 232,000 MW of proposed large-load demand was in its interconnection process.
Data centers represented approximately 72% of that proposed large-load queue.
That does not mean all 232 GW will actually be built.
Interconnection queues contain projects at very different stages of development, and some will never become operational.
But the scale demonstrates the extraordinary level of demand seeking access to the Texas grid.
Why Texas Is Changing Its Large-Load Process
In August 2026, ERCOT announced additional verification requirements before advancing data center large loads through portions of its interconnection study process.
The change reflects growing concern that utilities and grid planners need better certainty about which proposed loads are likely to become real projects.
This distinction matters because a speculative 1 GW request can affect grid planning even if the development is never constructed.
What Large Data Centers Can Require
Depending on location and size, a project may require:
-
New substations
-
Transmission upgrades
-
Additional generation
-
Battery storage
-
New utility feeders
-
Special large-load tariffs
Read our guide to why data centers need new transmission lines.
Texas Data Centers and New Power Generation
The newest generation of Texas data center development is increasingly linked directly to new power resources.
Examples include:
-
Google pairing a Haskell County data center with solar and battery storage
-
Microsoft developing a 2 GW Pecos campus
-
Large-scale power purchase agreements supporting new generation
This reflects a broader shift in the industry.
Data center site selection is no longer simply about finding a utility connection.
Developers increasingly need to answer:
Where will several hundred—or several thousand—megawatts of additional power actually come from?
What Is a 2 GW Data Center Campus?
Microsoft’s Pecos project provides a useful example.
Two gigawatts equals:
-
2,000 MW
-
2,000,000 kW
If a theoretical 2 GW load operated continuously at full capacity for an entire year, it would consume:
17.52 terawatt-hours of electricity.
Actual consumption would depend on utilization and how the announced 2 GW figure is defined.
Maximum planned capacity should not automatically be treated as constant electricity consumption.
Texas Data Center Projects and Water Use
Water is another important issue because much of Texas regularly experiences:
-
High temperatures
-
Drought
-
Rapid population growth
-
Competing water demand
Data center water use varies dramatically depending on cooling design.
Facilities may use:
-
Evaporative cooling
-
Cooling towers
-
Dry cooling
-
Hybrid cooling
-
Closed-loop liquid cooling
A project’s MW demand does not automatically tell you how much direct water it will use.
Read How Much Water Does a Data Center Use? for a detailed explanation.
What Communities Should Ask About Water
Ask for:
-
Average gallons per day
-
Peak summer gallons per day
-
Annual consumption
-
Water source
-
Potable vs. reclaimed water
-
Cooling technology
-
Drought restrictions
How Many Jobs Do Texas Data Centers Create?
Texas projects provide several real-world examples.
Microsoft Pecos
Microsoft expects:
-
6,000+ construction jobs at peak
-
Hundreds of permanent jobs
Meta Temple
Meta reports approximately:
-
1,200 workers at peak construction
-
Almost 100 operational roles
Meta El Paso
Meta expects:
-
4,000+ construction workers at peak
-
300+ operational jobs
These examples show why employment claims should always separate temporary construction employment from permanent operations.
Read our full guide to data center jobs and employment.
How Large Are Texas Data Center Projects?
There is enormous variation.
Projects on this tracker range from individual buildings of approximately 189,000 to 245,000 square feet to entire campuses measured in gigawatts.
Do not judge project scale from square footage alone.
Ask for:
-
Total acreage
-
Total building count
-
Total square footage
-
Phase 1 MW
-
Full-build-out MW
-
Substation count
-
Generator count
Read How Big Is a Data Center? Acres, Square Feet & MW Explained.
How Long Do Texas Data Center Projects Take to Build?
Construction schedules depend heavily on:
-
Project size
-
Electrical infrastructure
-
Permitting
-
Equipment availability
-
Construction labor
Microsoft’s registered Medina County projects, for example, include construction schedules stretching into 2028 and 2029.
Massive campuses can continue expanding for much longer.
Microsoft says the Pecos investment itself will unfold over approximately five to seven years.
Read our guide to how long it takes to build a data center.
Texas Data Center Construction Permits Are a Valuable Research Tool
Texas is unusually useful for data center research because the Texas Department of Licensing and Regulation maintains public project registrations.
Those records can reveal:
-
Project name
-
Owner
-
Address
-
County
-
Square footage
-
Estimated construction cost
-
Start date
-
Completion date
-
Design firm
That is how projects such as:
-
Amazon Project Eagle
-
Amazon Floyd County
-
Microsoft SAT93
can be identified before they receive extensive media coverage.
How to Track a Texas Data Center Project
1. Search Texas TDLR Records
Search the Texas Department of Licensing and Regulation Architectural Barriers database.
Useful search terms include:
-
Data Center
-
Data Centre
-
Amazon Data Services
-
Microsoft
-
Google
-
Meta
2. Search County Property Records
Use county appraisal district databases to identify:
-
Property owner
-
Parcel size
-
Land transfers
3. Search Local Planning Records
Depending on the jurisdiction, look for:
-
Site plans
-
Plat applications
-
Zoning changes
-
Development agreements
4. Search ERCOT and PUCT Records
Large-load and transmission proceedings can reveal major electrical infrastructure associated with future campuses.
5. Search Environmental Permits
Generator permits, water permits and stormwater filings can provide additional details.
For a full investigative workflow, read our guide to data center building permits, site plans and zoning records.
Questions to Ask About a Proposed Texas Data Center
-
How many acres will the campus occupy?
-
How many buildings are planned?
-
What is the maximum MW demand?
-
Does ERCOT consider the load verified?
-
Will new generation be built?
-
Are new transmission lines required?
-
How many substations are planned?
-
Who pays for grid upgrades?
-
What cooling technology will be used?
-
How much water will be consumed during peak summer conditions?
-
How many generators are planned?
-
How many permanent jobs will be created?
-
What tax incentives are provided?
-
Can the project expand later?
See our 25 questions every community should ask about a proposed data center.
Texas Data Center Regions to Watch
West Texas
Pecos, Fort Stockton and El Paso are becoming particularly important because of new hyperscale and AI investment.
San Antonio / Medina County
Microsoft continues adding major new data center capacity west of San Antonio.
Dallas-Fort Worth
DFW remains one of the country’s established major data center markets.
Central Texas
Temple now hosts Meta’s operational AI-optimized campus.
Rural Texas
Projects in Haskell, Armstrong, Floyd and Wharton counties demonstrate that the new development wave is increasingly moving into rural areas with available land and energy infrastructure.
How Data Center News Tracks Texas Data Center Projects
Whenever possible, Data Center News prioritizes primary and official sources including:
-
Texas Department of Licensing and Regulation
-
ERCOT
-
Public Utility Commission of Texas
-
County and municipal records
-
Company announcements
-
Environmental permits
-
Property records
Project information changes quickly.
A project may be:
-
Expanded
-
Delayed
-
Renamed
-
Built in multiple phases
-
Transferred to another operator
-
Cancelled
This page will be updated as significant new information becomes available.
Frequently Asked Questions About Texas Data Center Projects
Where are data centers being built in Texas?
Major current development includes West Texas, Medina County, Temple, El Paso, Wharton County, Floyd County, Haskell County and Armstrong County, alongside established markets such as Dallas-Fort Worth.
What is the largest new Texas data center project?
Among publicly announced projects, Microsoft’s Pecos campus is especially large at approximately 2 GW of planned capacity.
How much is Microsoft investing in Pecos?
Microsoft describes the Pecos project as a multibillion-dollar investment unfolding over approximately five to seven years.
Is Meta’s Temple Data Center operating?
Yes. Meta announced on July 22, 2026 that the Temple Data Center had begun serving production traffic.
How much is Meta investing in El Paso?
Meta reports more than $10 billion of investment associated with its El Paso campus.
Is Amazon building data centers in Texas?
Yes. Texas state records identify Amazon Data Services as the owner of new registered data center buildings in locations including Pecos County, Wharton County and Floyd County.
How much electricity could Texas data centers need?
ERCOT reported more than 232 GW of proposed large loads in its interconnection process in early 2026, with data centers accounting for approximately 72% of that queue. Not all requested projects will necessarily be built.
How can I find a Texas data center project near me?
Search Texas TDLR construction registrations, county property records, local planning documents, ERCOT filings and environmental permits.
Bottom Line: Texas Data Center Projects Are Entering the Gigawatt Era
Texas data center projects are rapidly increasing in both number and scale.
Current developments include:
-
Microsoft’s approximately 2 GW Pecos campus
-
Google’s Armstrong and Haskell County data center expansion within its broader $40 billion Texas investment
-
Meta’s operating Temple AI data center
-
Meta’s $10+ billion El Paso campus
-
Amazon’s Pecos County, Project Eagle and Floyd County construction projects
-
Additional Microsoft campuses near San Antonio
The defining issue for the next wave of Texas development will be electricity.
With enormous amounts of proposed data center load seeking ERCOT interconnection, the questions are increasingly:
-
Which projects are real?
-
How quickly can they connect?
-
Where will the electricity come from?
-
Who pays for the infrastructure?
At the same time, communities will continue evaluating:
-
Water use
-
Jobs
-
Tax revenue
-
Land use
-
Generator emissions
-
Transmission infrastructure
Data Center News will continue updating this Texas data center projects tracker as major developments move from proposal to construction and operation.
For nationwide coverage, visit our U.S. Data Center Projects tracker.