Virginia data center projects range from established hyperscale campuses in Northern Virginia to major new developments moving into Central, Southwest and Southern Virginia.
Virginia remains the most mature data center market in the United States. Loudoun County alone has hundreds of existing data center buildings, while new projects are increasingly appearing in places such as Botetourt County, Dinwiddie County and the Richmond region.
This tracker follows major data centers in Virginia, including projects that are operating, under construction, approved, moving through permitting or still seeking land-use approval.
Last updated: September 23, 2026
Data center plans can change during zoning, environmental review, permitting and construction. Project acreage, building counts, investment figures, power requirements and timelines below reflect publicly available information that could be verified at the time of publication.
Virginia Data Center Projects: Quick Navigation
Dedicated Virginia Data Center Project & Market Profiles
-
Loudoun County Data Centers: Locations, Growth, Tax Revenue & Future Plans
-
Google Botetourt County Data Center: Location, Plans & Status
-
Haven Oak Technology Park Data Center: Plans, Location & Status
-
Microsoft MNZ07 Wellington Data Center: Prince William County Plans & Status
Virginia Data Center Projects Tracker
The table below highlights several of the most significant current Virginia data center projects and markets being tracked by Data Center News.
This is not a complete inventory of every data center building in Virginia. Northern Virginia alone contains hundreds of facilities.
| Project / Market | Company / Developer | Location | Reported Scale | Status |
|---|---|---|---|---|
| Loudoun County Data Center Market | Multiple operators | Loudoun County | Approx. 233 existing buildings / 56.5M sq. ft. built or in construction | Operating / Expanding |
| Google Botetourt County Campus | Botetourt County | 312-acre site / 3 planned data center buildings | Site Work Beginning | |
| Haven Oak Technology Park | Tract / Applicant | Dinwiddie County | Approx. 986.9 acres | Proposed / Zoning Review |
| MNZ07 Wellington Data Center | Microsoft | Prince William County | Approx. 123 acres | Environmental Permitting |
| QTS Richmond 5 | QTS Richmond V, LLC | Henrico County | Approx. 44-acre site | Environmental Permitting |
Virginia’s project pipeline extends well beyond the projects shown above. Loudoun County alone reports tens of millions of additional square feet of data center space that has been approved or remains in the development process.
For projects elsewhere in the country, visit our U.S. Data Center Projects tracker.
Loudoun County Data Centers
Full market profile: Loudoun County Data Centers: Locations, Growth, Tax Revenue & Future Plans
No discussion of Virginia data center projects can begin anywhere other than Loudoun County.
Loudoun became the center of global data center development during the first quarter of the 21st century and continues to contain one of the highest concentrations of data center infrastructure anywhere in the world.
According to Loudoun County’s official data center statistics, as of March 1, 2026:
-
Approximately 233 existing data center buildings were built or in various stages of construction.
-
Those buildings represented approximately 56.5 million square feet.
-
The average existing data center contained approximately 234,000 square feet.
-
More recent data center permits since 2023 averaged closer to 339,000 square feet per building.
-
The county issued building permits for more than 10 million square feet of data center space in 2025 alone.
35.7 Million Additional Square Feet Approved or in Review
Loudoun also reported approximately 35.7 million square feet of approved-but-not-yet-built data center use.
That figure includes:
-
Approved legislative applications
-
Approved site plans without building permits
-
Site plans still under review
The county estimates that the pipeline could represent roughly 115 additional buildings, although Loudoun cautions that not every approved project will necessarily be constructed.
Additional Proposed Projects
Beyond the approved pipeline, Loudoun reported 21 legislative applications representing approximately:
-
56 potential data center buildings
-
20.7 million square feet of proposed data center use
Those projects remain subject to changes and local approval.
Why Loudoun Matters
Loudoun is important because many of the issues now emerging across the United States have already appeared there.
These include:
-
Power availability
-
Transmission construction
-
Substation siting
-
Noise
-
Residential compatibility
-
Tax revenue
-
Land-use regulation
Loudoun therefore serves as an important case study for communities considering their first major data center projects.
Loudoun County Is Changing Its Data Center Rules
Virginia’s largest data center market is also changing how future projects are approved.
In March 2025, Loudoun County changed data centers from a largely by-right use in several industrial districts to a use requiring a Special Exception.
That means many future projects now require a discretionary public approval process.
The county is continuing a second phase of its Data Center Standards and Locations initiative.
Current work includes potential standards involving:
-
Data center locations
-
Utility substations
-
Building height
-
Noise
-
On-site generation
-
Battery energy storage
-
Parking
-
Compatibility with surrounding uses
This is an important trend.
The largest U.S. data center market is no longer treating the industry simply as another industrial land use.
Prince William County Data Center Projects
Prince William County has developed into another major Northern Virginia data center market.
Like Loudoun, the county is reconsidering how and where new facilities should be approved.
Prince William uses a Data Center Opportunity Zone Overlay District, commonly called the DCOZOD.
In 2026, county officials began restructuring those rules.
Under the proposed framework, parcels remaining inside qualifying portions of the overlay can retain certain by-right development opportunities, while new projects outside the overlay would generally require a Special Use Permit.
You can follow the current process through Prince William County’s official DCOZOD review.
Microsoft MNZ07 Wellington Data Center
Full project profile: Microsoft MNZ07 Wellington Data Center: Prince William County Plans & Status
One significant current Prince William County project is Microsoft’s MNZ07 Wellington Data Center Project.
Virginia environmental records describe the proposed project as occupying approximately 123 acres.
The site is located:
-
South of Interstate 66
-
East of University Boulevard
-
North of Wellington Road
Microsoft applied for a federal Clean Water Act permit associated with impacts from development of the site.
Virginia DEQ held a public environmental review period during July and August 2026.
You can review the official MNZ07 Wellington Data Center public notice.
Google Botetourt County Data Center Campus
Full project profile: Google Botetourt County Data Center: Location, Plans & Status
Google’s Botetourt County campus represents one of the most important examples of data center development expanding beyond Northern Virginia.
Google purchased approximately 312 acres at the Botetourt Center at Greenfield in 2025.
The campus is planned as a multi-phase development.
Botetourt County says the project is expected to include three data centers.
Under the project’s development agreement, construction of the first data center is expected to begin in 2026, with the first structure expected to be ready for occupancy during 2028.
Grading Approved in August 2026
On August 26, 2026, Botetourt County announced that Google had received its initial Land Disturbance Permit.
The permit allows phased grading to begin on the 312-acre site.
That moves the project beyond a conceptual proposal and into early physical site development.
See the county’s official Google grading permit announcement.
Three Planned Data Centers
Botetourt County says each of the three planned data centers is expected to contribute at least $10 million in annual local taxation as development progresses.
The project therefore illustrates why local governments can find data centers financially attractive even when permanent employment is considerably smaller than construction employment.
Read our guide to data center property tax revenue for more examples.
Google Botetourt Data Center Power Infrastructure
The Botetourt project is also a particularly useful example of how a large data center can reshape local electrical infrastructure.
According to Botetourt County’s official electricity overview, Appalachian Power plans major upgrades associated with serving the campus.
Current plans include:
-
Upgrading approximately 17 miles of 138-kV transmission line
-
Upgrading the Cloverdale substation
-
Upgrading the Trinity substation
-
Upgrading the Mount Union substation
-
Upgrading the Botetourt substation
-
Constructing a new substation
-
Constructing a short new 138-kV transmission connection
The county says infrastructure required specifically to serve Google’s data center will be paid for by Google.
This is exactly why looking only at the data center property can give an incomplete picture of a project’s impact.
A major campus can trigger electrical construction miles away.
Read our guide to why data centers need new transmission lines.
Haven Oak Technology Park — Dinwiddie County
Full project profile: Haven Oak Technology Park Data Center: Plans, Location & Status
The proposed Haven Oak Technology Park represents another major expansion of data center development into Southern Virginia.
Dinwiddie County has received an application seeking to rezone approximately 986.9 acres near White Oak Road and Claiborne Road.
The applicant is requesting:
-
A land-use amendment
-
Rezoning to the Emerging Technologies District
-
A Conditional Use Permit for a data center campus
The project remains in the land-use process and should therefore be considered proposed rather than approved or under construction.
Haven Oak Was Revised in August 2026
The developer submitted a substantially revised proposal on August 31, 2026.
According to Dinwiddie County’s official Haven Oak project page, revisions included:
-
Removing development areas and buildings from the Core Battlefield Area on the west portion of the property
-
Changing a secondary access location
-
Restricting the campus to an air-cooled / closed-loop, non-evaporative cooling system
-
Adding an illustrative site plan
-
Reducing proposed sound limits to 52 dBA
-
Increasing vegetative buffers
-
Adding development-area setback requirements
These changes illustrate why project trackers need frequent updates.
A proposed project’s design can change substantially in response to environmental, historical, infrastructure and community concerns.
Why Haven Oak Is Particularly Important to Watch
The nearly 1,000-acre proposal touches several issues that are increasingly central to data center siting:
-
Historic resources
-
Cooling technology
-
Noise limits
-
Residential buffers
-
Large-scale land use
The developer’s move to a non-evaporative cooling system is especially notable because water use has become an important community concern around some data center projects.
Read How Much Water Does a Data Center Use? for more context.
QTS Richmond 5 Data Center — Henrico County
Full project profile: QTS Richmond 5 Data Center: Henrico County Plans & Status
Virginia’s data center industry is also expanding around the Richmond region.
QTS Richmond 5 is a proposed data center campus in Henrico County’s White Oak Technology Park.
Virginia DEQ describes the development site as approximately 44 acres near:
-
East Williamsburg Road
-
Technology Boulevard
The proposed campus includes:
-
Data center facilities
-
Utilities
-
Roads
-
Generators
-
Parking
-
Stormwater infrastructure
The project requires environmental permitting because the proposed development would affect wetlands.
Virginia DEQ conducted a public review during July and August 2026.
Review the official QTS Richmond 5 environmental notice.
Why the Richmond Region Matters
Henrico and surrounding Richmond-area markets demonstrate that Virginia data center growth is no longer exclusively a Northern Virginia story.
Developers are increasingly evaluating new markets based on:
-
Available land
-
Electrical capacity
-
Fiber access
-
Tax environment
-
Proximity to major networks
Why Does Virginia Have So Many Data Centers?
Virginia’s dominance developed from several advantages reinforcing one another over time.
Fiber Infrastructure
Northern Virginia became a major internet-interconnection hub during the early growth of the commercial internet.
That attracted:
-
Telecommunications companies
-
Cloud providers
-
Colocation providers
-
Network operators
Existing Data Center Ecosystem
Once a large concentration of data centers developed, the market became increasingly attractive to additional operators.
The region now has:
-
Experienced contractors
-
Skilled electrical trades
-
Fiber providers
-
Equipment suppliers
-
Data center specialists
Access to Large Customers
Northern Virginia is close to:
-
Washington, D.C.
-
Federal agencies
-
Major corporations
-
Large population centers
Tax Policy
Virginia has also used tax policy to encourage qualifying data center investment.
Land and Power
As the Northern Virginia market becomes more constrained, developers are looking farther south and west for:
-
Larger parcels
-
New electrical capacity
-
Less expensive land
That helps explain projects in places such as Botetourt and Dinwiddie counties.
Virginia Data Center Projects and the Power Grid
Electricity has become one of the most important constraints on future Virginia data center projects.
Modern hyperscale and AI campuses can request power measured in hundreds of megawatts.
At that scale, projects may require:
-
New substations
-
Additional transformers
-
New transmission lines
-
Rebuilt transmission lines
-
Utility easements
-
New generation resources
Our guide explaining how much power data centers use puts these numbers into context.
Nearby Power Does Not Mean Available Power
A proposed site can sit beside an existing transmission corridor and still require years of electrical work.
The utility must determine whether:
-
The transmission line has available capacity
-
The substation has sufficient capacity
-
Transformers are available
-
Reliability standards can still be met
See our data center substation guide for a detailed explanation.
Virginia Data Centers and Transmission Lines
Transmission infrastructure has become increasingly visible in Virginia’s data center debate.
New electrical demand can require utility projects extending well beyond the actual data center property.
Those projects can involve:
-
New transmission corridors
-
Taller structures
-
Expanded rights-of-way
-
Substations
-
Vegetation clearing
The Google Botetourt project provides a current example, with approximately 17 miles of transmission upgrades planned along with several substation improvements.
Read our full guide to data center transmission lines.
How Much Tax Revenue Do Virginia Data Centers Generate?
Virginia shows why tax revenue is one of the industry’s most powerful economic-development arguments.
Loudoun County
Loudoun County reports that data centers generated approximately $1.2 billion in real and personal property tax revenue during FY2026.
That represented approximately 39% of the county’s overall budget.
The adopted FY2027 budget projects approximately $1.3 billion in data center revenue.
Those figures are extraordinary and should not be treated as typical for every Virginia locality.
Loudoun contains an unusually large concentration of facilities.
Botetourt County
Botetourt County says each of Google’s planned three data centers is expected to produce at least $10 million in annual local taxation as the campus develops.
These examples demonstrate why data centers can be attractive to local governments even when the number of permanent employees is relatively modest.
Read Data Center Property Tax Revenue: How Much Does a Data Center Generate?.
How Many Jobs Do Virginia Data Centers Create?
Data center employment should always be separated into:
-
Construction jobs
-
Permanent operating jobs
-
Contractors
-
Indirect and induced employment
Large campuses can require thousands of construction workers while the permanent workforce after completion is considerably smaller.
Loudoun County reports more than 17,000 direct and indirect data center-related jobs across its broader industry ecosystem.
That includes employment beyond workers physically operating individual data center buildings.
Our guide to how many jobs data centers create explains why these categories should not be combined.
Virginia Data Center Projects and Nearby Communities
As data center construction moves closer to residential and rural areas, Virginia communities are debating several recurring issues.
Noise
Potential sources include:
-
Cooling equipment
-
Transformers
-
Generators
Read our guide to data center noise levels.
Residential Setbacks
Communities increasingly want greater separation between homes and:
-
Data center buildings
-
Generator yards
-
Cooling systems
-
Substations
See our data center setback guide.
Water
Cooling methods can dramatically change onsite water consumption.
Some Virginia proposals have responded directly to those concerns by committing to low-water or non-evaporative cooling designs.
Visual Impact
Large campuses can contain:
-
Massive buildings
-
Transmission structures
-
Substations
-
Security fencing
Construction
Multi-building projects can create years of:
-
Truck traffic
-
Earthmoving
-
Road construction
-
Utility construction
These concerns help explain why Virginia localities are increasingly reconsidering where data centers should be permitted and what conditions should apply.
How Large Are Virginia Data Center Projects?
The scale varies enormously.
Examples on this page range from:
-
A 44-acre QTS site in Henrico County
-
A 123-acre Microsoft site in Prince William County
-
A 312-acre Google campus in Botetourt County
-
A nearly 987-acre Haven Oak proposal in Dinwiddie County
Acreage alone does not determine computing capacity.
To understand the full size of a project, also look for:
-
Total square footage
-
Number of buildings
-
Megawatts
-
Number of substations
-
Generator count
-
Future phases
Read How Big Is a Data Center? Acres, Square Feet & MW Explained.
How to Track a Virginia Data Center Project
Virginia data center projects often leave a detailed public-record trail.
Start with the local city or county.
1. Search the County Planning Department
Look for:
-
Rezoning applications
-
Special-use permits
-
Special exceptions
-
Conditional-use permits
-
Site plans
2. Search Virginia DEQ
The Virginia Department of Environmental Quality publishes information on certain projects requiring environmental review or permits.
Those records can reveal:
-
Wetland impacts
-
Generator permits
-
Project acreage
-
Site location
-
Applicant
3. Search Utility Filings
Large data center loads can require proceedings before the Virginia State Corporation Commission or major utility infrastructure filings.
Search for:
-
Transmission lines
-
Substations
-
Large-load service
-
Utility projects
4. Search Building Permits
After zoning approval, building and grading permits can show whether construction is actually beginning.
Use our guide to finding data center building permits, site plans and zoning records.
5. Search by Parcel and LLC Name
Do not search only for Google, Microsoft or another recognizable operator.
Applications may be filed under:
-
Landowners
-
Development companies
-
Project LLCs
-
Engineering firms
Our guide explaining how to find out if a data center is planned near you provides a step-by-step process.
What to Ask About a Proposed Virginia Data Center
If a project is proposed in your community, ask:
-
How many acres are included?
-
How many buildings are planned at full build-out?
-
How many MW will the campus require?
-
Will a new substation be built?
-
Will transmission lines need to be upgraded?
-
Who pays for electrical infrastructure?
-
What cooling system will be used?
-
How much water will the facility consume?
-
How many generators are proposed?
-
What nighttime noise standard applies?
-
How far will buildings and equipment be from homes?
-
How many permanent jobs will be created?
-
How much annual tax revenue is projected?
-
What tax incentives are being provided?
-
Can the campus expand after approval?
See our complete 25 data center town hall questions every community should ask.
Major Virginia Data Center Regions to Watch
Virginia’s market is increasingly becoming geographically diverse.
Northern Virginia
Key markets include:
-
Loudoun County
-
Prince William County
-
Fairfax County
-
Stafford County
Richmond Region
Henrico County and surrounding areas continue attracting major digital infrastructure investments.
Southwest Virginia
Google’s Botetourt County campus demonstrates the potential for new hyperscale development farther west.
Southern Virginia
The Haven Oak proposal in Dinwiddie County demonstrates the industry’s search for very large new development sites outside established data center clusters.
How Data Center News Tracks Virginia Data Center Projects
Whenever possible, Data Center News prioritizes official and primary records, including:
-
County planning departments
-
Virginia DEQ
-
Virginia State Corporation Commission filings
-
Building and grading permits
-
Utility documents
-
Company announcements
-
Local government meeting records
Project statuses can change quickly.
A proposed project may be:
-
Revised
-
Expanded
-
Reduced
-
Approved
-
Delayed
-
Withdrawn
-
Sold
This page will be updated as significant new information becomes available.
Frequently Asked Questions About Virginia Data Center Projects
How many data centers are in Virginia?
There is no single statewide number that remains accurate for long because projects are continuously being built and expanded. Loudoun County alone reported approximately 233 existing data center buildings built or under construction as of March 1, 2026.
Where are most data centers in Virginia?
The largest concentration is in Northern Virginia, especially Loudoun County and Prince William County. Development is increasingly expanding into other parts of the state.
Why are there so many data centers in Northern Virginia?
The region combines dense fiber connectivity, a mature data center ecosystem, access to customers, established utilities and decades of accumulated infrastructure.
Are new Virginia data centers still being built?
Yes. Large projects are moving forward in both established Northern Virginia markets and emerging areas such as Botetourt, Dinwiddie and the Richmond region.
What is the Google data center project in Virginia?
Google is developing a three-data-center campus on approximately 312 acres at the Botetourt Center at Greenfield. Initial grading was authorized in August 2026.
What is Haven Oak Technology Park?
Haven Oak is a proposed approximately 986.9-acre data center campus in Dinwiddie County. The project remains in the local land-use approval process.
What is the Microsoft Wellington data center?
Microsoft MNZ07 Wellington is a proposed two-building data center campus on approximately 123 acres in Prince William County. The project remains in environmental permitting.
What is QTS Richmond 5?
QTS Richmond 5 is a proposed expansion of QTS’s White Oak Technology Park campus in Henrico County. The project-specific environmental review covers approximately 44 acres.
How much tax revenue do Virginia data centers generate?
The amount varies dramatically by locality. Loudoun County reported approximately $1.2 billion in real and personal property tax revenue from data centers in FY2026.
Do Virginia data centers require new transmission lines?
Some do. The answer depends on the project’s electricity requirements and available grid capacity. Google’s Botetourt project, for example, is associated with approximately 17 miles of planned transmission-line upgrades and multiple substation improvements.
How can I find a proposed Virginia data center near me?
Search county planning and zoning records, GIS property databases, Virginia DEQ records, building permits and electric utility filings.
Bottom Line: Virginia Remains the Center of U.S. Data Center Development
Virginia data center projects now span both the world’s most established data center market and a growing group of new communities experiencing hyperscale development for the first time.
Loudoun County remains unmatched in concentration, with hundreds of existing buildings and tens of millions of additional square feet in the development pipeline.
At the same time, projects such as:
show how Virginia’s data center map is expanding.
The most important numbers to watch are no longer simply investment dollars or building square footage.
They include:
-
MW of electricity demand
-
Transmission requirements
-
Substation infrastructure
-
Water use
-
Residential setbacks
-
Tax revenue
-
Permanent jobs
Data Center News will continue updating this Virginia data center projects tracker as major proposals move through permitting, construction and operation.
For nationwide coverage, visit our U.S. Data Center Projects tracker.