The Google Botetourt County data center is a planned multi-building campus at the Botetourt Center at Greenfield in Virginia.
Google is developing approximately 312 acres at the site, where Botetourt County says plans call for three data center buildings.
The Google Botetourt County data center reached an important milestone in August 2026 when the county issued the first Land Disturbance Permit, allowing phased grading work to begin. Read Botetourt County’s official grading announcement.
The county currently expects the first data center structure to be completed and fit for use during 2028. See Botetourt County’s official Google project page.
Last updated: September 15, 2026
Current status: Site preparation / grading
For other projects across the state, see our Virginia Data Center Projects tracker. For nationwide coverage, visit the U.S. Data Center Projects tracker.
Google Botetourt County Data Center at a Glance
| Detail | Current Information |
|---|---|
| Company | |
| Project | Google Botetourt County data center |
| Location | Botetourt Center at Greenfield |
| County | Botetourt County, Virginia |
| Site | Approx. 312 acres |
| Planned data centers | 3 |
| Current status | Site preparation / grading |
| First building cooling | Air cooling |
| First building target | Fit for use during 2028 |
| Development | Multi-phase |
Where Is the Google Botetourt County Data Center?
The Google Botetourt County data center is being developed at the Botetourt Center at Greenfield in Botetourt County, Virginia.
Botetourt County maintains an official Google Data Center project page containing project updates, frequently asked questions, development information and permitting details.
Google purchased approximately 312 acres at the industrial development site.
The location represents an important expansion of Virginia’s data center industry beyond its traditional Northern Virginia concentration.
Northern Virginia remains one of the world’s largest data center markets, but projects such as Google Botetourt show hyperscale development spreading into additional parts of the state.
Our Virginia Data Center Projects tracker follows these projects and their current development status.
Has Construction Started on the Google Botetourt County Data Center?
Site preparation has started moving forward, but the project’s status should be described carefully.
On August 26, 2026, Botetourt County announced that Google had satisfied county requirements for its first mass-grading package and received a Land Disturbance Permit.
The permit allows phased grading on the approximately 312-acre property. Read the county’s Land Disturbance Permit announcement.
This is more advanced than a conceptual proposal, but grading is not the same as saying all three data center buildings are under vertical construction.
The most accurate current status for the Google Botetourt County data center is:
Site preparation / grading
Environmental Permits Are Separate
The Land Disturbance Permit does not represent every approval the project may ultimately require.
Botetourt County says work can proceed in approved grading areas while streams and wetlands remain subject to additional environmental review.
Large data center projects may separately require:
- Land disturbance permits
- Wetland permits
- Stormwater approvals
- Building permits
- Air-quality permits
- Backup-generator permits
- Utility approvals
- Electrical infrastructure approvals
This is why saying a data center has been “approved” can sometimes oversimplify the actual development process.
Our guide to finding data center building permits, site plans and zoning records explains how these different approvals fit together.
When Will the Google Botetourt County Data Center Open?
Botetourt County describes the development as a multi-phase project.
According to the county’s current project timeline:
- Initial grading applications were received in February 2026
- Land-disturbance approvals were issued in August 2026
- Site grading is expected during 2026
- The first data center structure is expected to be completed and fit for use during 2028
Later phases could follow on separate schedules.
A three-building campus does not necessarily open all at once.
Instead, hyperscale developments often become operational in stages while later buildings remain under construction.
See How Long Does It Take to Build a Data Center? for more on grading, utility work, construction and commissioning timelines.
How Many Data Centers Is Google Planning in Botetourt County?
Botetourt County describes the development as a campus containing three data centers.
That distinction matters because references to the “Google Botetourt County data center” can make the project sound like a single building.
The current plan is better understood as a multi-building campus developed in phases.
Full build-out could therefore look substantially different from the first building that becomes operational.
Google Botetourt County Data Center Cooling and Water Use
Google has announced that the first data center building will use air-cooling technology.
Botetourt County includes that cooling decision in its current Google Data Center project information.
The distinction between the first building and the full campus matters.
Cooling technology for later phases should not automatically be assumed to be identical unless Google or Botetourt County confirms it.
Cooling design has a major effect on data center water consumption.
Air-cooled facilities can have very different water requirements from facilities relying heavily on evaporative cooling towers.
See How Much Water Does a Data Center Use? for a detailed explanation of different cooling systems.
How Much Water Will the Google Botetourt County Data Center Use?
A definitive full-campus water-use figure should not be assumed until the cooling design for all phases is established.
The first building’s air-cooling design should reduce cooling-related water requirements compared with some evaporative systems.
However, data centers can still require water for:
- Domestic use
- Fire protection
- Cooling-system maintenance
- Landscaping
- Other facility operations
The eventual water demand of the three-building campus should therefore be based on project-specific engineering and utility records.

How Much Power Will the Google Botetourt County Data Center Use?
A final full-build-out power figure should be based on utility or project records rather than estimated from acreage.
Large hyperscale campuses can require:
- Dedicated electrical substations
- High-voltage transformers
- Transmission infrastructure
- Redundant electrical feeds
- Backup generators
The project’s approximately 312-acre footprint does not by itself reveal how many megawatts the campus will eventually require.
Our guide How Much Power Does a Data Center Use? explains why MW has become one of the most important measurements for modern data center projects.
You can also see Data Center Substations Explained and Why Data Centers Need New Transmission Lines for the supporting infrastructure large campuses may require.
How Much Tax Revenue Could the Google Botetourt County Data Center Generate?
Botetourt County has projected significant local tax revenue once the campus becomes operational.
The county’s economic-development materials discuss revenue generated through both real estate and taxable business property, including equipment installed inside the data centers.
Those estimates should still be treated as projections rather than guaranteed collections.
Actual revenue will depend on:
- Final capital investment
- Number of completed buildings
- Installed computing equipment
- Property assessments
- Tax rates
- Depreciation
- Incentives
- Development schedule
A large headline investment does not directly equal annual tax revenue.
See Data Center Property Tax Revenue Explained for how these calculations work.
Jobs at the Google Botetourt County Data Center
The Google Botetourt County data center is expected to support substantial construction activity while the campus is being built.
Construction jobs should be separated from permanent operational employment.
A large data center can require:
- Electricians
- Equipment operators
- Concrete crews
- Pipefitters
- HVAC workers
- Network installers
- Other skilled trades
Once construction is complete, the permanent workforce is typically substantially smaller.
See How Many Jobs Do Data Centers Create? for the difference between construction jobs, permanent jobs and indirect economic-impact estimates.
Why the Google Botetourt County Data Center Matters
The project is significant for several reasons.
First, it demonstrates that Virginia’s hyperscale market is expanding beyond Northern Virginia.
Second, the campus illustrates how modern data center development proceeds through multiple independent stages:
- Site acquisition
- Planning
- Grading
- Environmental review
- Utility development
- Building construction
- Commissioning
- Operation
Third, Google’s decision to use air cooling for the first building makes the project relevant to the growing debate over data center water consumption.
The project will therefore be useful to follow as later buildings move through design and permitting.
What Happens Next?
The next major milestones to monitor include:
- Continued grading
- Environmental approvals
- Utility infrastructure
- Building permits
- Vertical construction
- Cooling decisions for later buildings
- First-building completion
- Additional campus phases
The first building is currently expected to be fit for use during 2028, but later phases may continue beyond that point.
Data Center News will update this article as new primary-source documentation becomes available.
Frequently Asked Questions About the Google Botetourt County Data Center
What is the Google Botetourt County data center?
The Google Botetourt County data center is a planned three-building hyperscale campus at the Botetourt Center at Greenfield in Virginia.
Where is the Google Botetourt County data center located?
The project is being developed at the Botetourt Center at Greenfield in Botetourt County, Virginia. See Botetourt County’s official project page.
How large is Google’s Botetourt County site?
The project covers approximately 312 acres.
How many data center buildings are planned?
Botetourt County describes the project as a three-data-center campus.
Has construction started?
The project has entered site preparation. Google received a Land Disturbance Permit in August 2026 allowing phased grading. Read the official grading announcement.
When will the Google Botetourt County data center open?
Botetourt County expects the first data center structure to be completed and fit for use during 2028.
How will Google’s Botetourt County data center be cooled?
Google says the first data center building will use air cooling. Cooling technology for later phases should be evaluated separately.
How much power will the campus use?
A reliable full-build-out MW figure should be based on current utility or project documentation rather than estimated from acreage.