Google Dorchester County Data Centers: Ridgeville & St. George

Data Center News by Data Center News
September 24, 2026
in Project Tracker
Google Dorchester County Data Centers Ridgeville & St. George

Google Dorchester County Data Centers Ridgeville & St. George

Share on FacebookShare on Twitter

The Google Dorchester County data centers are two major hyperscale campuses being developed in Ridgeville and St. George, South Carolina.

The projects were originally announced in 2024 as part of approximately $2 billion of new Dorchester County investment, with about 200 operational jobs expected across the two facilities.

Google has since significantly increased its South Carolina investment plans.

In October 2025, the company announced an additional $9 billion investment in South Carolina through 2027 to continue construction of its Dorchester County campuses and expand its existing Berkeley County data center.

The two Dorchester projects are now under active construction and represent a major expansion of Google’s cloud and AI infrastructure in South Carolina.

They are also tracked in our South Carolina Data Center Projects directory.

Table of Contents

Toggle
  • Google Dorchester County Data Centers at a Glance
  • Where Are Google’s Dorchester County Data Centers?
    • Ridgeville
    • St. George
  • Google’s Original $2 Billion Dorchester County Announcement
  • Google Later Announced Another $9 Billion in South Carolina
  • Are the Dorchester County Data Centers Under Construction?
  • Water Use and the Dorchester County Projects
  • Why Google Is Expanding in South Carolina
  • Jobs and Economic Impact
  • Current Status
  • Frequently Asked Questions
    • Where is Google building data centers in Dorchester County?
    • How much is Google investing?
    • How many jobs will Google’s Dorchester data centers create?
    • Are the projects under construction?
    • What will the facilities support?
  • Bottom Line

Google Dorchester County Data Centers at a Glance

DetailCurrent Information
CompanyGoogle
CountyDorchester County
LocationsRidgeville and St. George
Ridgeville SitePine Hill Business Campus
St. George SiteWinding Woods Commerce Park
Original Dorchester InvestmentApproximately $2 billion
Original Operational JobsApproximately 200
Broader 2025 SC Investment$9 billion through 2027
PurposeCloud and AI infrastructure
StatusUnder construction

Where Are Google’s Dorchester County Data Centers?

Google is developing two separate campuses.

Ridgeville

The Ridgeville facility is located within Pine Hill Business Campus.

The site expands Google’s presence west of its long-established Berkeley County data center in Moncks Corner.

St. George

The second campus is being developed at Winding Woods Commerce Park in St. George.

Together, the projects establish Dorchester County as another major Google infrastructure location in South Carolina.

See Google’s official South Carolina data center information

Google’s Original $2 Billion Dorchester County Announcement

South Carolina announced the two campuses in September 2024.

At that time, Google said the facilities represented approximately:

  • $2 billion of investment
  • 200 new operational jobs

The campuses were intended to support growing demand for Google Cloud, Search, Maps and artificial-intelligence services.

Google already operated a major data center complex in neighboring Berkeley County, making the new projects an expansion of an established regional infrastructure footprint rather than Google’s entry into South Carolina.

Google Later Announced Another $9 Billion in South Carolina

The project’s investment story changed significantly in October 2025.

Google announced plans to invest an additional $9 billion in South Carolina through 2027.

The company said that investment would:

  • Continue construction of the two Dorchester County data centers
  • Expand Google’s Berkeley County data center
  • Support cloud infrastructure
  • Support AI infrastructure
  • Fund related workforce initiatives

The newer $9 billion commitment should not simply be added to the original $2 billion Dorchester announcement as though both figures describe separate completed investments.

Instead, the $9 billion figure represents Google’s broader, newer South Carolina investment program covering multiple facilities and years.

Read Google’s $9 billion South Carolina investment announcement

Are the Dorchester County Data Centers Under Construction?

Yes.

Dorchester County states that both campuses are under active construction.

That moves the projects beyond the planning and announcement stage.

Construction of a hyperscale data center campus can involve:

  • Mass grading
  • Roads
  • Stormwater infrastructure
  • Electrical substations
  • Utility extensions
  • Fiber
  • Cooling infrastructure
  • Data center buildings
  • Backup-power systems

Campuses are often activated in phases rather than opening all at once.

Water Use and the Dorchester County Projects

Water has become one of the most common community questions surrounding data center development.

Dorchester County says the Google campuses will be served by multiple regional water sources.

Actual data center water consumption depends heavily on cooling technology and operating conditions, so infrastructure availability should not be confused with actual consumption.

Important numbers for communities to monitor include:

  • Average gallons per day
  • Peak summer demand
  • Cooling-system design
  • Potable versus non-potable water
  • Reclaimed-water use
  • Expected wastewater flows

Our guide explaining why data centers use water provides technical background on how cooling design affects consumption.

Why Google Is Expanding in South Carolina

Google has operated in South Carolina since breaking ground on its Berkeley County data center in 2007.

The company’s expanding regional footprint now includes data center campuses across both Berkeley and Dorchester counties.

Google reports that it has invested more than $13 billion in South Carolina since establishing its first data center there.

The state also benefits from fiber and subsea cable infrastructure that helps connect cloud facilities to Google’s broader network.

Jobs and Economic Impact

The original Dorchester County announcement projected approximately 200 permanent operational jobs.

Construction employment is separate and can be much larger during peak development.

This difference is important when evaluating economic-development announcements.

A multi-billion-dollar data center investment does not necessarily translate into thousands of permanent jobs because much of the capital goes toward:

  • Buildings
  • Servers
  • Networking hardware
  • Electrical equipment
  • Cooling systems
  • Substations
  • Backup systems

Current Status

As of 2026:

  • The Ridgeville campus is under construction.
  • The St. George campus is under construction.
  • Google is continuing development as part of its $9 billion South Carolina investment program through 2027.

The two campuses therefore represent active development rather than speculative proposals.

Frequently Asked Questions

Where is Google building data centers in Dorchester County?

Google is building at Pine Hill Business Campus in Ridgeville and Winding Woods Commerce Park in St. George.

How much is Google investing?

The original Dorchester County announcement represented approximately $2 billion. Google later announced a broader $9 billion South Carolina investment through 2027 covering continued Dorchester development and Berkeley County expansion.

How many jobs will Google’s Dorchester data centers create?

The original announcement projected approximately 200 permanent operational jobs.

Are the projects under construction?

Yes. The Dorchester County campuses are under active construction.

What will the facilities support?

Google says its South Carolina infrastructure supports growing cloud and artificial-intelligence demand.

Bottom Line

Google’s Dorchester County data centers are transforming Ridgeville and St. George into important parts of the company’s expanding South Carolina infrastructure network.

Rather than isolated facilities, the two campuses are now part of a much larger regional buildout spanning Dorchester and Berkeley counties and backed by Google’s latest $9 billion investment plan through 2027.

ShareTweet

join the DataCenterNews.org newsletter

Stay Connected

Email field is required to subscribe.

x

You Have Successfully Subscribed to the Newsletter

Data Center News

Data Center News

The Data Center News Research Desk produces research-driven coverage of data center development, power infrastructure, water use, construction, AI demand, policy, and community impacts. Our work draws on public records, government data, utility and regulatory filings, company disclosures, planning documents, and other primary sources whenever available.

Related Posts

Project Flex Data Center Lyon Township Michigan Plans & Status
Project Tracker

Project Flex Data Center: Lyon Township Michigan Plans & Status

September 25, 2026

The Project Flex data center is a proposed hyperscale campus in Lyon Township, Michigan, being developed by Verrus in partnership...

Read moreDetails
Project Cherry Blossom Data Center Frenchtown Michigan Plans
Project Tracker

Project Cherry Blossom Data Center: Frenchtown Michigan Plans

September 25, 2026

The Project Cherry Blossom data center is a proposed large-scale data center campus being developed by Cloverleaf Infrastructure in Frenchtown...

Read moreDetails
Data Center News

Data center news, projects, and analysis covering power grids, water use, AI demand, incentives, and community impact behind the world’s growing cloud infrastructure.

Navigation

  • About
  • Authors & Editors
  • Contact
  • Editorial Policy
  • Home
  • Privacy Policy
  • Terms of Service

Topics

  • AI & Cloud
  • Infrastructure & Construction
  • News
  • Policy & Community
  • Power & Grid
  • Project Tracker
  • Projects
  • Water & Environment

Join the free newsletter

Stay Connected

Email field is required to subscribe.

x

You Have Successfully Subscribed to the Newsletter

© 2026 Data Center News

No Result
View All Result
  • Home
  • News
    • Project News
  • Project Tracker
  • Power & Grid
  • Water & Environment
  • Policy & Community
  • AI & Cloud

© 2026 Data Center News