Google LaGrange data center development is expanding at 411 Pegasus Parkway in Troup County, Georgia, where Google has confirmed a new data center location and additional filings describe another major building at the campus. The project is part of Google’s broader 2026 expansion in Georgia, alongside a new Columbia County development and the company’s long-running Douglas County campus.
A Development of Regional Impact filing reported by Data Center Dynamics describes a new approximately 470,000-square-foot building valued at about $1 billion, joining an existing building at the LaGrange site. Georgia environmental records also identify a data center operation at 411 Pegasus Parkway and a permit process for emergency engines supporting the facility.
Last updated: September 22, 2026
Current status: Under construction / Expansion
See this project in context on the Georgia Data Center Projects Tracker or browse major projects nationwide on the U.S. Data Center Projects Tracker.
Google LaGrange Data Center at a Glance
| Detail | Current information |
|---|---|
| Company | |
| Location | 411 Pegasus Parkway, LaGrange, Troup County, Georgia |
| Status | Under construction / Expansion |
| Reported expansion | Approx. 470,000 sq. ft. |
| Reported expansion value | Approx. $1 billion |
| Project filing name | PRL2 |
| Air permitting | Georgia EPD record for emergency engines supporting data center operations |
| Power capacity | Not publicly disclosed by Google |
| Last updated | September 22, 2026 |
Where Is the Google LaGrange Data Center?
The LaGrange campus is located at 411 Pegasus Parkway in LaGrange, about 70 miles southwest of Atlanta in Troup County. Google officially lists LaGrange as a Georgia data center location in development on its Georgia data center page.
The location places the campus near Interstate 85 and within an established industrial area. LaGrange also operates municipal utilities, making the project’s relationship with local power and infrastructure different from projects served entirely by investor-owned utilities.
How Big Is the Google LaGrange Data Center Expansion?
The latest major filing associated with the Google project describes an additional building of approximately 470,000 square feet. Data Center Dynamics reported that KDC filed the Development of Regional Impact application for a project called PRL2 on behalf of the property owner.
The reported new building would join an existing data center building at the site and carries an estimated project value of approximately $1 billion. The filing indicated construction could continue through 2029, while additional future phases were described as speculative rather than committed.
That distinction matters for SEO and project tracking: the confirmed or filed phase should be separated from possible future build-out. Our guide to data center size, acres, square feet and MW explains why a master-planned campus can be much larger than the active construction phase.
Google LaGrange Data Center Construction Status
The Pegasus Parkway campus is not simply a proposed greenfield concept. Google has publicly confirmed LaGrange as a location in development, and reporting around the site shows active construction activity.
The project should therefore be tracked as under construction with an additional expansion phase moving through development review. The exact completion date for every phase is not yet public, and large campuses frequently change schedules as utility infrastructure, equipment procurement and building packages advance.
For context, see our guide to how long data centers take to build.
Air Permits and Backup Generators at 411 Pegasus Parkway
Georgia Environmental Protection Division records provide another useful window into the LaGrange campus. An April 2026 public advisory identifies Rosewall Pines Holdings LLC at 411 Pegasus Parkway and describes the operation as computer processing and data preparation services.
The Georgia EPD advisory says the permit application involved installation of emergency engines to support data center operations. Backup engines are common at large data centers because servers and networking equipment require highly reliable power during utility interruptions.
Generator permitting can reveal project details even when a company has not publicly released every aspect of a campus. That is one reason environmental records are included in our guide to tracking data center permits, site plans and zoning records.
How Much Power Will the LaGrange Campus Use?
Google has not publicly disclosed a final MW figure for the Google LaGrange data center. That means estimates should not be presented as confirmed project capacity.
Large hyperscale facilities can require dedicated substations, high-voltage transmission connections and substantial utility upgrades. But square footage alone cannot reliably determine electrical demand because server density varies considerably, especially as AI hardware becomes more power intensive.
Read our guide to how much power a data center uses and our explanation of data center substations for context on how large campuses connect to the grid.
What Has LaGrange Said About Electric Rates?
Local officials have presented the Google project as an opportunity to strengthen the city’s utility system after the loss of a major industrial electricity customer. When Google confirmed the location, LaGrange City Manager Patrick Bowie said the project would fill a significant gap left in the utility system and that infrastructure improvements were expected to benefit utility customers.
Google representatives also said the company would cover costs related to power and infrastructure needs at the site. Those commitments are important because one of the central community questions around data centers is whether existing customers could end up paying for generation, transmission or distribution upgrades.
Water and Cooling
Project-specific water consumption for the Pegasus Parkway campus has not been publicly disclosed in a form that supports a reliable gallons-per-day estimate.
Google has experience using recycled industrial water at its Douglas County, Georgia campus, but that does not mean the same cooling arrangement should be assumed for LaGrange. Cooling technology is site-specific and may change as individual buildings are designed.
Communities should ask for average daily demand, peak summer demand, water source and whether cooling relies on potable water, reclaimed water, dry coolers or another system. Our data center water-use guide explains the differences.
Jobs and Economic Impact
Google has not published a project-specific permanent job total for the LaGrange campus. Construction employment is likely to be much larger than the long-term operating workforce while the campus is being built.
That pattern is common across hyperscale projects. Construction requires electricians, mechanical contractors, equipment installers, civil crews and other skilled trades, while an operating campus usually requires a smaller permanent staff of technicians, engineers, security personnel and facility specialists.
See How Many Jobs Do Data Centers Create? for a breakdown of construction versus permanent employment.
What Information Is Still Unknown?
Several important facts about the Google project remain undisclosed or subject to future filings:
- Final full-build MW capacity
- Total number of committed campus buildings
- Project-specific permanent job count
- Average and peak water use
- Number and capacity of substations
- Final build-out date beyond currently filed phases
Future DRI records, environmental permits, utility records and building permits may provide more detail as construction continues.
Frequently Asked Questions About the Google LaGrange Data Center
Is Google building a data center in LaGrange, Georgia?
Yes. Google officially lists LaGrange, Georgia as a data center location in development.
Where is the Google LaGrange data center?
The project is at 411 Pegasus Parkway in LaGrange, Troup County.
How large is the new LaGrange data center building?
A 2026 development filing described an additional building of approximately 470,000 square feet, with an estimated project value of about $1 billion.
Is the Google LaGrange data center under construction?
Yes. The campus is in development with construction activity at the site, while additional phases are moving through review.
How much electricity will the Google LaGrange data center use?
Google has not publicly disclosed a confirmed full-build MW capacity for the LaGrange campus.
Does the project need backup generators?
Georgia EPD records identify a proposed permit for emergency engines supporting data center operations at 411 Pegasus Parkway.
Where can I track other Georgia projects?
Visit the Georgia Data Center Projects Tracker.