Google Van Buren Township Data Center: 1 GW Michigan Project

Data Center News by Data Center News
September 25, 2026
in Project Tracker
Google Van Buren Township Data Center 1 GW Michigan Project

Google Van Buren Township Data Center 1 GW Michigan Project

Share on FacebookShare on Twitter

The Google Van Buren Township data center is a planned 1-gigawatt data center campus in Wayne County, Michigan.

Google publicly confirmed the project in March 2026 and currently lists Van Buren Township as one of its data center locations in development.

The project’s enormous electrical demand has also made it the subject of an active Michigan Public Service Commission proceeding involving special contracts between Google and DTE Energy.

The Van Buren campus is one of several large new developments tracked in our Michigan Data Center Projects tracker.

Table of Contents

Toggle
  • Google Van Buren Township Data Center at a Glance
  • Google Confirms Van Buren Township Data Center
  • A 1-Gigawatt Data Center
  • DTE Energy Will Serve the Project
  • Michigan Attorney General Challenges Contract Terms
  • Google Agreed to a Contested Regulatory Case
  • How Does Van Buren Compare With Saline Township?
  • Water Use
  • Current Status
  • Frequently Asked Questions
    • Is Google building a data center in Michigan?
    • Where is Google’s Michigan data center?
    • How much power will it use?
    • Who will supply electricity?
    • Is the project approved?
    • Is Project Cannoli Google’s project?
  • Bottom Line

Google Van Buren Township Data Center at a Glance

DetailCurrent Information
CompanyGoogle
LocationVan Buren Township
CountyWayne County
Electrical DemandApproximately 1 GW
UtilityDTE Energy
AnnouncedMarch 2026
StatusIn development
Regulatory ReviewMPSC special-contract proceeding

Google Confirms Van Buren Township Data Center

Google added Van Buren Township to its official list of North American data center locations in 2026.

The company currently classifies the facility as in development.

View Google’s current data center locations.

The project had previously appeared in public discussions under development names before Google’s identity became public.

Google’s confirmation moved the project beyond speculation and established Van Buren Township as its first publicly identified Michigan data center location.

A 1-Gigawatt Data Center

Michigan regulatory records describe the project as a 1-gigawatt data center.

One gigawatt equals:

1,000 megawatts

That is an enormous electrical load by conventional industrial standards.

For perspective, data center electricity contracts increasingly resemble the output of utility-scale generating facilities rather than ordinary commercial customers.

Actual hourly consumption may be lower than the maximum contracted or anticipated demand, but the utility must plan infrastructure around the potential load.

See How Much Power Does a Data Center Use?.

DTE Energy Will Serve the Project

Google plans to obtain electricity from DTE Energy.

The utility and Google have submitted long-term special contracts to the Michigan Public Service Commission.

Those contracts are important because data centers can require:

  • Generation
  • Transmission upgrades
  • Substations
  • Distribution infrastructure
  • Long-term capacity planning

The central regulatory question is not simply whether DTE can serve the project, but how costs and risks are allocated between Google and existing utility customers.

Michigan Attorney General Challenges Contract Terms

Michigan Attorney General Dana Nessel has participated in the MPSC proceeding reviewing Google’s contracts with DTE.

In June 2026, the Attorney General’s office argued that several contract protections should be strengthened.

Among the issues raised were:

  • Minimum monthly billing requirements
  • Exit fees if Google leaves or reduces demand
  • Tracking of transmission-related costs
  • Protection against stranded infrastructure costs

The Attorney General recommended increasing Google’s minimum monthly charge from the proposed 80% of anticipated demand to at least 90%.

Read the Attorney General’s June 2026 testimony summary.

The filing represents the Attorney General’s position in the regulatory case; it is not a final MPSC determination.

Google Agreed to a Contested Regulatory Case

When Google announced the project in March 2026, it committed to having its DTE contracts reviewed through a contested case before the MPSC.

That process allows intervening parties to:

  • Conduct discovery
  • Submit expert testimony
  • Cross-examine witnesses
  • File briefs
  • Challenge contract terms

That provides more formal scrutiny than an uncontested approval.

How Does Van Buren Compare With Saline Township?

Michigan now has two data center projects with publicly documented electrical demand around or above one gigawatt:

  • Google Van Buren Township: approximately 1 GW
  • Stargate Saline Township: 1,383 MW contracted load

Together, they illustrate the scale of electricity infrastructure being requested by Michigan’s emerging AI and hyperscale data center sector.

Read our full profile of the Stargate Saline Township Data Center.

Water Use

Public project materials reviewed for this profile do not yet provide the same level of specific cooling and water detail available for the Saline Township Stargate campus.

Google has not publicly reduced the Van Buren facility’s expected water demand to one simple daily figure in the sources reviewed here.

That is a figure worth monitoring as local permits, water agreements and final engineering information become public.

Residents should distinguish between:

  • Water capacity reserved
  • Maximum possible demand
  • Average daily consumption
  • Cooling-system consumption

See Why Data Centers Use Water for more context.

Current Status

The Google Van Buren Township data center remains in development.

Google has confirmed the project and DTE-related regulatory proceedings are underway.

Major milestones to watch include:

  • Final MPSC contract approval
  • Site-development permits
  • Substation and transmission work
  • Construction start
  • Cooling-system disclosures
  • Building plans
  • Operational timeline

Frequently Asked Questions

Is Google building a data center in Michigan?

Yes. Google currently lists Van Buren Township, Michigan, as a data center location in development.

Where is Google’s Michigan data center?

The project is in Van Buren Township in Wayne County.

How much power will it use?

Michigan regulatory filings describe the project as approximately 1 gigawatt, or 1,000 MW.

Who will supply electricity?

DTE Energy is the utility involved in the proposed special contracts.

Is the project approved?

Google has publicly confirmed the development, but important utility-contract and development processes remain underway.

Is Project Cannoli Google’s project?

Van Buren Township’s large data center development has previously been discussed under project codenames, while Google now publicly identifies Van Buren Township as one of its data center locations.

Bottom Line

The Google Van Buren Township data center is one of Michigan’s most consequential developing data center projects because of its approximately 1-GW electricity requirement.

The ongoing DTE contract proceeding will also help determine how Michigan regulates the financial and infrastructure risks created by hyperscale customers.

ShareTweet

join the DataCenterNews.org newsletter

Stay Connected

Email field is required to subscribe.

x

You Have Successfully Subscribed to the Newsletter

Data Center News

Data Center News

The Data Center News Research Desk produces research-driven coverage of data center development, power infrastructure, water use, construction, AI demand, policy, and community impacts. Our work draws on public records, government data, utility and regulatory filings, company disclosures, planning documents, and other primary sources whenever available.

Related Posts

Project Flex Data Center Lyon Township Michigan Plans & Status
Project Tracker

Project Flex Data Center: Lyon Township Michigan Plans & Status

September 25, 2026

The Project Flex data center is a proposed hyperscale campus in Lyon Township, Michigan, being developed by Verrus in partnership...

Read moreDetails
Project Cherry Blossom Data Center Frenchtown Michigan Plans
Project Tracker

Project Cherry Blossom Data Center: Frenchtown Michigan Plans

September 25, 2026

The Project Cherry Blossom data center is a proposed large-scale data center campus being developed by Cloverleaf Infrastructure in Frenchtown...

Read moreDetails
Data Center News

Data center news, projects, and analysis covering power grids, water use, AI demand, incentives, and community impact behind the world’s growing cloud infrastructure.

Navigation

  • About
  • Authors & Editors
  • Contact
  • Editorial Policy
  • Home
  • Privacy Policy
  • Terms of Service

Topics

  • AI & Cloud
  • Infrastructure & Construction
  • News
  • Policy & Community
  • Power & Grid
  • Project Tracker
  • Projects
  • Water & Environment

Join the free newsletter

Stay Connected

Email field is required to subscribe.

x

You Have Successfully Subscribed to the Newsletter

© 2026 Data Center News

No Result
View All Result
  • Home
  • News
    • Project News
  • Project Tracker
  • Power & Grid
  • Water & Environment
  • Policy & Community
  • AI & Cloud

© 2026 Data Center News