The Haven Oak Technology Park data center is a proposed large-scale campus covering approximately 986.9 acres in Dinwiddie County, Virginia.
The property is located near the intersection of White Oak Road and Claiborne Road. The applicant is seeking to rezone the property to Dinwiddie County’s Emerging Technologies District and obtain a Conditional Use Permit allowing development of a data center campus.
Dinwiddie County maintains a dedicated Haven Oak Technology Park application page containing the zoning application, concept plans, proposed conditions, traffic study, sound assessment and other project records.
A major revised submission was filed on August 31, 2026, changing the proposed cooling system, sound limits, setbacks, buffers and portions of the development area.
Last updated: September 15, 2026
Current status: Proposed / zoning review
For other major developments in the state, see our Virginia Data Center Projects tracker. You can also compare Haven Oak with projects nationwide in our U.S. Data Center Projects tracker.
Haven Oak Technology Park at a Glance
| Detail | Current Information |
|---|---|
| Project | Haven Oak Technology Park |
| Location | Dinwiddie County, Virginia |
| Approximate site | 986.9 acres |
| Area | White Oak Road / Claiborne Road |
| Applicant contact | Tract |
| Proposed use | Data center campus |
| Land-use request | Rezoning + Conditional Use Permit |
| Proposed cooling | Air-cooled / closed-loop, non-evaporative |
| Revised sound limit | 52 dBA |
| Current status | Proposed / zoning review |
| Latest major revision | August 31, 2026 |
Where Is the Haven Oak Technology Park Data Center?
Dinwiddie County says the Haven Oak application covers approximately 986.9 acres near White Oak Road and Claiborne Road.
The proposal is still in the land-use process.
That distinction is important because a proposed project is not the same as an approved or under-construction data center.
The current application asks the county to:
- Rezone the property to the Emerging Technologies District
- Approve a Conditional Use Permit
- Allow development of a data center campus
The county’s official Haven Oak application repository should be treated as the primary source for the project’s current zoning status and latest plans.
If you are researching another proposed project, our guide to finding data center building permits, site plans and zoning records explains how to distinguish a proposal from an approval.
What Changed in the August 2026 Haven Oak Revision?
The August 31 revised submission made several meaningful changes to the proposal.
According to Dinwiddie County, the applicant:
- Removed development areas and buildings from the Core Battlefield Area on the West Bay
- Adjusted the secondary access location
- Restricted the campus to an air-cooled / closed-loop non-evaporative cooling system
- Added an illustrative site plan
- Lowered the proposed sound limit to 52 dBA
- Increased vegetative buffers
- Added development-area setback requirements
Those revisions are listed directly in the county’s August 31 project materials.
This is why older maps or descriptions of Haven Oak may no longer accurately represent the current proposal.
Large data center applications frequently change as developers respond to planning review, environmental constraints and community concerns.
Haven Oak Cooling and Water Use
One of the most significant changes is the proposed restriction to an air-cooled / closed-loop non-evaporative cooling system.
That could materially reduce cooling-related water consumption compared with a facility that relies heavily on evaporative cooling towers.
It does not, however, mean the project would use zero water.
A data center campus may still require water for:
- Domestic use
- Fire suppression
- Initial cooling-system filling
- Maintenance
- Landscaping
- Other support functions
The actual water impact should therefore be based on project-specific engineering and utility records rather than a generic estimate.
Our guide to how much water a data center uses explains why cooling technology can dramatically change water demand.
Haven Oak Noise Limit
The revised proposal lowered the proposed sound limit to 52 dBA.
Noise is one of the most common issues raised when large data centers are proposed near homes or rural property.
Potential sources include:
- Cooling equipment
- Transformers
- Backup generators
- Mechanical equipment
- Construction
- Truck traffic
The Haven Oak application also includes an environmental sound assessment.
For broader context, see our guide to data center setbacks and proximity to homes and our analysis of community opposition to data centers.

Battlefield Area Changes
The August revision removed development areas and buildings from the Core Battlefield Area on the West Bay.
This demonstrates why concept plans should be treated as evolving documents rather than final blueprints.
Data center layouts can change because of:
- Historic resources
- Wetlands
- Environmental review
- Community feedback
- Noise
- Traffic
- Utility infrastructure
- Required buffers and setbacks
Data Center News will use the latest public submission when tracking Haven Oak rather than relying on earlier concept plans.
How Large Is Haven Oak Technology Park?
At approximately 986.9 acres, Haven Oak is a very large land-use proposal.
But acreage by itself does not tell us how much computing infrastructure will ultimately be built.
Important figures still worth tracking include:
- Final building count
- Total square footage
- Initial electrical demand
- Full-build-out MW
- Substation capacity
- Backup-generator capacity
- Number of development phases
A 1,000-acre campus does not necessarily consume more electricity than a much smaller, denser project.
Our guide How Big Is a Data Center? Acres, Square Feet & MW Explained explains why acreage and electrical capacity measure different things.
How Much Power Will Haven Oak Use?
A reliable full-build-out MW figure should not be published until it can be supported by a current public record.
Estimating Haven Oak’s electricity demand solely from its acreage would be speculation.
As the project advances, the most useful records to monitor will include:
- Utility interconnection documents
- Substation applications
- Transmission filings
- Backup-generator permits
- Air permits
- Revised concept plans
Large campuses can require extensive electrical infrastructure beyond the property itself.
Our explainers on data center substations and why data centers need new transmission lines explain what to look for.
Haven Oak Traffic Study
The project’s official filing includes a Traffic Impact Analysis, which is available through the county’s Haven Oak document repository.
Construction typically produces much more traffic than long-term data center operation because construction requires:
- Large numbers of tradespeople
- Heavy equipment
- Concrete trucks
- Material deliveries
- Excavation
- Utility work
Operational staffing is usually much smaller.
That is one reason employment and traffic estimates should clearly distinguish between construction and permanent operation.
Why Haven Oak Has Generated Community Interest
Dinwiddie County says the project has generated significant public interest, which led the county to create a dedicated project page containing documents, communications and meeting notices.
Issues worth following include:
- Land use
- Cooling
- Water
- Noise
- Traffic
- Historic resources
- Electricity demand
- Buffers
- Residential setbacks
- Tax revenue
- Permanent employment
Residents participating in future hearings may also find our 25 questions to ask at a data center town hall useful.
What Happens Next?
Haven Oak should currently be described as a proposed data center campus undergoing land-use review.
Potential future milestones include:
- Planning Commission action
- Board of Supervisors consideration
- Rezoning approval or denial
- Conditional Use Permit approval or denial
- Environmental permits
- Utility approvals
- Grading permits
- Building permits
- Construction
Approval at one stage does not mean every later permit has been granted.
That distinction is especially important when reading headlines describing a data center as “approved.”
Frequently Asked Questions About Haven Oak Technology Park
What is Haven Oak Technology Park?
Haven Oak Technology Park is a proposed data center campus in Dinwiddie County, Virginia covering approximately 986.9 acres.
Where would the Haven Oak data center be located?
Dinwiddie County identifies the property as being near the intersection of White Oak Road and Claiborne Road. View the county’s project documents.
Has Haven Oak Technology Park been approved?
It should currently be described as proposed and undergoing land-use review, not as an operating data center or completed campus.
How will Haven Oak be cooled?
The August 31 revised application restricts the proposal to an air-cooled / closed-loop non-evaporative cooling system.
What is the proposed Haven Oak noise limit?
The revised application lowered the proposed sound limit to 52 dBA.
How large is Haven Oak Technology Park?
The current application covers approximately 986.9 acres.
Where can I track other Virginia data center projects?
See the Virginia Data Center Projects: 2026 Locations & Tracker for current projects across the state.