Loudoun County data centers form what the county describes as the highest concentration of data centers anywhere in the world. As of March 1, 2026, Loudoun reported approximately 233 existing or under-construction data center buildings representing about 56.5 million square feet.
The market is still expanding. Loudoun also reported about 35.7 million square feet of approved but not yet built data center use, potentially representing roughly 115 additional buildings, plus 21 legislative applications representing another 56 potential buildings and 20.7 million square feet.
Last updated: September 22, 2026
Market status: Operating / expanding / increasingly regulated
See the Virginia Data Center Projects Tracker and U.S. Data Center Projects Tracker.
Loudoun County Data Centers at a Glance
| Metric | Current Information |
|---|---|
| Existing / under-construction buildings | Approx. 233 |
| Existing / under-construction floor area | Approx. 56.5 million sq. ft. |
| Approved but not yet built | Approx. 35.7 million sq. ft. |
| Potential additional buildings in approved pipeline | Approx. 115 |
| Legislative applications | 21 applications / approx. 56 buildings / 20.7 million sq. ft. |
| FY 2026 data center tax revenue | Approx. $1.2 billion |
| Share of FY 2026 county budget | 39% |
| FY 2027 projected data center revenue | Approx. $1.3 billion / 40% of budget |
| Jobs | More than 17,000 direct and indirect data-center-related jobs |
| Existing and proposed substations | 95 as of March 1, 2026 |
Why Are There So Many Loudoun County Data Centers?
Loudoun County data centers grew around one of the internet’s most important connectivity corridors. Loudoun traces its modern data center story to Northern Virginia’s early commercial internet-exchange infrastructure in the 1990s and the arrival of major internet companies in Ashburn.
Over time, the region combined dense fiber, carrier connectivity, available land, power infrastructure, an experienced technology workforce and proximity to Washington, D.C. Those advantages helped create the market widely known as Data Center Alley.
Loudoun County’s official Data Centers: The Loudoun Story page provides the county’s current totals and historical background.
How Many Data Centers Are in Loudoun County?
As of March 1, 2026, Loudoun County data centers included approximately 233 buildings that were already built or in various stages of construction. Together, those facilities represented roughly 56.5 million square feet.
The county says the average existing data center is about 234,000 square feet, while newer buildings permitted since 2023 average closer to 339,000 square feet. Loudoun issued permits for more than 10 million square feet of data center space in 2025 alone, the highest one-year amount in county history.
See How Big Is a Data Center? Acres, Square Feet & MW Explained.
How Much More Loudoun Data Center Development Is Approved?
The development pipeline is much larger than the current 233-building count. Loudoun reports about 35.7 million square feet of approved data center use that is not yet built.
That approved pipeline includes legislative approvals, approved site plans without building permits and site plans still under review. The county estimates it could amount to roughly 115 additional buildings, while cautioning that not every approved project will ultimately be constructed.
Another 21 legislative applications represent approximately 56 potential buildings and 20.7 million square feet of proposed data center use.
How Much Tax Revenue Do Loudoun County Data Centers Generate?
Loudoun County data centers generated approximately $1.2 billion in real and personal property tax revenue in Fiscal Year 2026, according to the county. That represented about 39% of Loudoun County’s total budget.
The adopted FY 2027 budget projects approximately $1.3 billion in data center revenue, or about 40% of the county budget.
Those numbers illustrate both the economic importance of the industry and the county’s concern about becoming too dependent on a single sector. See Data Center Property Tax Revenue Explained.
How Many Jobs Do Loudoun County Data Centers Support?
Loudoun County reports more than 17,000 direct and indirect data-center-related jobs. That includes permanent operations as well as specialized construction trades, technology services, professional services and security.
Job claims should still distinguish permanent operating jobs from temporary construction employment. See How Many Jobs Do Data Centers Create?.
Loudoun Eliminated By-Right Data Center Development
The rules governing future Loudoun County data centers changed significantly in 2025. The county says it eliminated by-right data center development and now requires future proposals to obtain Special Exception approval in areas where they were previously allowed automatically.
A Special Exception requires a public review process and a Board of Supervisors decision. That gives the county more ability to evaluate compatibility, impose conditions and consider community impacts before approving new development.
Loudoun County Data Centers and the Power Grid
Power availability has become one of the biggest constraints on future Loudoun County data centers. Loudoun says PJM data indicates data centers in the county cumulatively use at least 3 GW of power at any given time.
As of March 1, 2026, the county reported 95 existing and proposed substations. Many data center projects are now paired with substation applications because nearby distribution infrastructure is not always sufficient to serve new loads.
Loudoun says a data center requiring 100 MW or more may need multiple substations. The county is also planning more proactively for transmission corridors as demand grows.
See Loudoun County’s Energy Issues & Considerations, plus our guides to data center substations and transmission lines.
Backup Generators and On-Site Power
Loudoun reports more than 4,000 backup generators currently permitted to serve more than 200 data centers. The county says most are tested periodically and used during outages or other limited conditions, but generator noise and emissions have become major local issues.
Loudoun has also begun evaluating new forms of on-site generation because data center demand is growing faster than some transmission and substation upgrades can be completed.
See Data Center Noise Levels Explained.
Noise Around Loudoun data centers
Noise is one of the most persistent community concerns surrounding Data Center Alley facilities. Potential sources include cooling systems, transformers and backup generators.
The county says generator noise can sometimes be audible from several miles away under certain conditions. Loudoun continues evaluating additional standards as part of its broader data center policy work.
Why Loudoun Is Rewriting Its Data Center Rules
The county says data center density has intensified concerns about water use, noise, air quality, community aesthetics, land values and energy infrastructure. In response, Loudoun is shifting from a growth-oriented framework toward more strategic management of future development.
The county’s ongoing Data Center Standards and Locations project is expected to shape future rules for siting, design, substations, energy systems and compatibility with surrounding communities.
How to Track the Loudoun market
Loudoun provides unusually detailed public resources for following its data center market. Useful sources include the county’s data center dashboard, LandMARC planning records, Special Exception applications, site plans, building permits, State Corporation Commission transmission cases and Virginia DEQ environmental records.
See How to Find Data Center Building Permits, Site Plans & Zoning Records.
Frequently Asked Questions About the county’s data centers
How many data centers are in Loudoun County?
As of March 1, 2026, Loudoun County reported approximately 233 existing or under-construction data center buildings.
How much data center space is in Loudoun County?
About 56.5 million square feet is built or under construction, with another 35.7 million square feet approved but not yet built.
How much tax revenue do data centers generate?
Loudoun reported approximately $1.2 billion in data center real and personal property tax revenue in FY 2026, equal to about 39% of the county budget.
How many jobs do Loudoun data centers support?
The county reports more than 17,000 direct and indirect data-center-related jobs.
How many substations are in Loudoun County?
Loudoun reported 95 existing and proposed substations as of March 1, 2026.
Can new data centers still be built in Loudoun County?
Yes, but the approval process is more restrictive than it was historically. The county eliminated by-right data center development in 2025 and requires Special Exception approval for future proposals in affected areas.
Bottom Line
Loudoun data centers remain the defining example of large-scale data center concentration in the United States. The county reports approximately 233 existing or under-construction buildings and 56.5 million square feet, with tens of millions of additional square feet still approved or seeking approval.
The same industry generated about $1.2 billion in local tax revenue in FY 2026, but its continued expansion has intensified debate over substations, transmission lines, generators, noise and land use. Loudoun is now moving toward tighter long-term management of where and how future data centers are built.


