Meta Stanton Springs Data Center: $1.5B Georgia Campus Explained

Data Center News by Data Center News
September 22, 2026
in Project Tracker
Meta Stanton Springs Data Center $1.5B Georgia Campus Explained

Meta Stanton Springs Data Center $1.5B Georgia Campus Explained

Share on FacebookShare on Twitter

Table of Contents

Toggle
  • Meta Stanton Springs Data Center: $1.5B Georgia Campus Explained
    • Meta Stanton Springs Data Center at a Glance
    • Where Is the Meta Stanton Springs Data Center?
    • Meta Stanton Springs Data Center Investment and Jobs
    • When Did the Stanton Springs Data Center Break Ground?
    • Meta Stanton Springs Data Center Water Supply
    • Does Stanton Springs Use Groundwater?
    • Renewable Energy and Power Infrastructure
    • Water Efficiency and Site Design
    • Community Investment Around Stanton Springs
    • What Information Is Still Worth Tracking?
    • Frequently Asked Questions About the Meta Stanton Springs Data Center
      • Where is the Meta Stanton Springs data center?
      • How much has Meta invested at Stanton Springs?
      • How many jobs does the Stanton Springs data center support?
      • Does the Meta Stanton Springs data center use groundwater?
      • Who pays for the site’s water and sewer infrastructure?
      • When did the Stanton Springs data center break ground?
      • Where can I track other Georgia data centers?

Meta Stanton Springs Data Center: $1.5B Georgia Campus Explained

Meta Stanton Springs data center operations represent one of Georgia’s established hyperscale campuses, with Meta reporting more than $1.5 billion of investment, 1,300 skilled trade workers at peak construction and more than 200 operational jobs supported once completed. The campus broke ground in 2018 and continues to operate in the Stanton Springs area east of Atlanta.

The project is also a useful case study for water and infrastructure questions. Meta says the facility receives 100% of its operational water from the Newton County Water and Sewerage Authority, uses no groundwater for operations and pays the full costs associated with its water, sewer and necessary site-serving infrastructure.

Last updated: September 22, 2026
Current status: Operating / Expanding

See the facility alongside other major developments on the Georgia Data Center Projects Tracker or browse the U.S. Data Center Projects Tracker.

Meta Stanton Springs Data Center at a Glance

DetailCurrent information
CompanyMeta
LocationStanton Springs / Newton County, Georgia
StatusOperating / Expanding
Investment$1.5 billion+
Groundbreaking2018
Peak skilled trade workers1,300
Operational jobs200+ supported once completed
Operational water sourceNewton County Water and Sewerage Authority
Groundwater useMeta says none for operations
Last updatedSeptember 22, 2026

Where Is the Meta Stanton Springs Data Center?

The Meta Stanton Springs data center is located in the Stanton Springs area of Newton County, east of Atlanta. Meta’s community-grant programs also treat Jasper, Morgan, Newton and Walton counties as part of the broader Stanton Springs data center community.

The campus was originally known as the Newton Data Center. Meta’s earlier project announcement said Newton County was selected in part because of access to renewable energy, available engineering and construction talent, and local community partnerships.

Meta continues to list Stanton Springs among its active U.S. data center locations on its official data center location page.

Meta Stanton Springs Data Center Investment and Jobs

Meta says the Stanton Springs campus represents more than $1.5 billion of investment. The company’s current U.S. locations page lists approximately 1,300 skilled trade workers on site at peak construction and more than 200 operational jobs supported once completed.

Those figures illustrate the distinction between construction employment and permanent data center operations. A hyperscale campus may employ a large temporary workforce while multiple buildings and electrical systems are being constructed, while the long-term operations team is considerably smaller.

Read our guide to how many jobs data centers create for a detailed explanation of construction, indirect and permanent employment.

When Did the Stanton Springs Data Center Break Ground?

The Meta facility broke ground in 2018. Meta’s historical announcement described a 970,000-square-foot structure and said the company expected hundreds of construction and trade jobs during the initial build-out.

The campus has continued evolving since that initial phase. That is typical for hyperscale facilities: the first building may become operational while additional buildings, server halls and support infrastructure continue to be developed.

Our guide to data center construction timelines explains why large campuses can remain under development for years.

Meta Stanton Springs Data Center Water Supply

Water is one of the most closely watched issues at the Newton County campus. In April 2026, Meta published a detailed explanation of how the site is supplied.

According to Meta’s Stanton Springs water update, the facility receives 100% of the water used in operations from the Newton County Water and Sewerage Authority. Meta says it does not use groundwater for operations.

Meta also says it pays the full cost associated with water and sewer service, including new infrastructure necessary to reach and loop the site. The company says service agreements are based on water analysis and modeling used by the utility for both residential and industrial customers.

That does not mean the campus has no water footprint. It means the source and financial arrangement are clearer than at many proposed projects. See our guide to how much water data centers use for context on cooling systems and consumption.

Does Stanton Springs Use Groundwater?

Meta says the Stanton Springs campus does not use groundwater for its operations. Instead, operational water is supplied through the Newton County Water and Sewerage Authority.

This is an important local distinction because groundwater withdrawals can raise different concerns from municipal surface-water or utility-supplied systems. Residents evaluating any data center should ask not only how much water a facility will use but also where that water comes from and whether the project requires new wells or utility infrastructure.

Renewable Energy and Power Infrastructure

The Meta facility was developed with a major renewable-energy component. Meta’s original project announcement said it planned to work with Walton Electric Membership Corporation to bring hundreds of megawatts of renewable energy onto the regional grid.

Meta says its data center electricity use is matched with clean and renewable energy. That accounting does not mean the campus is electrically isolated from the regional grid or powered directly by solar panels every hour of the day. Large data centers remain dependent on utility infrastructure, substations, transmission and generation resources that keep the grid reliable around the clock.

Our guide to data center substations explains the electrical equipment that typically sits between a hyperscale campus and the wider power system.

Water Efficiency and Site Design

Meta says the Newton County campus is designed to reduce water use through site-specific efficiency measures. The company’s materials describe practices including reusing water multiple times before discharge, using native vegetation where possible and incorporating water-saving fixtures and technologies.

Meta has also set a broader corporate goal of becoming water positive in 2030, meaning it aims to restore more water than it consumes globally. Corporate restoration projects should be considered separately from direct on-site consumption: both are relevant, but they measure different things.

Community Investment Around Stanton Springs

The Stanton Springs campus is also tied to Meta’s local grant programs. The company has funded schools, nonprofits and workforce initiatives in the surrounding community, including projects focused on STEM education and digital access.

Meta’s 2026 Community Action Grants list Stanton Springs recipients such as Atha Road Elementary School, Camp Twin Lakes, Eastside High School FFA and Flint Hill Elementary. These grants are separate from property-tax revenue and should not be treated as a substitute for measuring the project’s fiscal impact on local government.

For an explanation of how local tax revenue from data centers is calculated, see our guide to data center property taxes.

What Information Is Still Worth Tracking?

Even though the Meta Stanton Springs data center is operating, several details remain useful to monitor over time:

  • Future campus expansion phases
  • Current building count and total square footage
  • Updated permanent employment
  • Annual and peak water consumption
  • Additional renewable-energy projects tied to the campus
  • New substations, generators or other electrical infrastructure

Operating data centers can continue expanding for years, so an “operating” status does not necessarily mean development at the campus is finished.

Frequently Asked Questions About the Meta Stanton Springs Data Center

Where is the Meta Stanton Springs data center?

The campus is in the Stanton Springs area of Newton County, Georgia, east of Atlanta.

How much has Meta invested at Stanton Springs?

Meta’s current U.S. data center location page lists more than $1.5 billion of investment.

How many jobs does the Stanton Springs data center support?

Meta lists 1,300 skilled trade workers at peak construction and more than 200 operational jobs supported once completed.

Does the Meta Stanton Springs data center use groundwater?

Meta says no. The company says 100% of operational water comes from the Newton County Water and Sewerage Authority.

Who pays for the site’s water and sewer infrastructure?

Meta says it pays the full cost associated with water and sewer usage, including necessary new infrastructure serving the site.

When did the Stanton Springs data center break ground?

Meta lists 2018 as the groundbreaking year.

Where can I track other Georgia data centers?

Use the Georgia Data Center Projects Tracker for current project coverage.

ShareTweet

join the DataCenterNews.org newsletter

Stay Connected

Email field is required to subscribe.

x

You Have Successfully Subscribed to the Newsletter

Data Center News

Data Center News

The Data Center News Research Desk produces research-driven coverage of data center development, power infrastructure, water use, construction, AI demand, policy, and community impacts. Our work draws on public records, government data, utility and regulatory filings, company disclosures, planning documents, and other primary sources whenever available.

Related Posts

Project Flex Data Center Lyon Township Michigan Plans & Status
Project Tracker

Project Flex Data Center: Lyon Township Michigan Plans & Status

September 25, 2026

The Project Flex data center is a proposed hyperscale campus in Lyon Township, Michigan, being developed by Verrus in partnership...

Read moreDetails
Project Cherry Blossom Data Center Frenchtown Michigan Plans
Project Tracker

Project Cherry Blossom Data Center: Frenchtown Michigan Plans

September 25, 2026

The Project Cherry Blossom data center is a proposed large-scale data center campus being developed by Cloverleaf Infrastructure in Frenchtown...

Read moreDetails
Data Center News

Data center news, projects, and analysis covering power grids, water use, AI demand, incentives, and community impact behind the world’s growing cloud infrastructure.

Navigation

  • About
  • Authors & Editors
  • Contact
  • Editorial Policy
  • Home
  • Privacy Policy
  • Terms of Service

Topics

  • AI & Cloud
  • Infrastructure & Construction
  • News
  • Policy & Community
  • Power & Grid
  • Project Tracker
  • Projects
  • Water & Environment

Join the free newsletter

Stay Connected

Email field is required to subscribe.

x

You Have Successfully Subscribed to the Newsletter

© 2026 Data Center News

No Result
View All Result
  • Home
  • News
    • Project News
  • Project Tracker
  • Power & Grid
  • Water & Environment
  • Policy & Community
  • AI & Cloud

© 2026 Data Center News