The Microsoft La Porte data center is a major cloud and artificial-intelligence infrastructure campus now under construction in La Porte, Indiana.
The project was originally announced in 2024 as a $1 billion investment involving a 245,000-square-foot data center on approximately 489 acres at Radius Industrial Park.
Microsoft broke ground on the project in June 2026.
The company’s current plans are significantly larger in employment terms than the original announcement: Microsoft now says the first phase alone is expected to create more than 600 permanent Microsoft jobs, in addition to thousands of construction jobs.
The project is one of the largest current developments in our Indiana Data Center Projects tracker.
Microsoft La Porte Data Center at a Glance
| Detail | Current Information |
|---|---|
| Company | Microsoft |
| Location | La Porte, Indiana |
| Original Site | Radius Industrial Park |
| Original Announced Investment | $1 billion |
| Original Building Plan | 245,000 sq. ft. |
| Original Site | Approximately 489 acres |
| Current First-Phase Jobs | More than 600 permanent Microsoft jobs |
| Groundbreaking | June 2026 |
| Cooling | Closed-loop liquid cooling planned |
| Status | Construction |
Where Is Microsoft’s La Porte Data Center?
Microsoft’s original project was announced for Radius Industrial Park in La Porte, Indiana.
The initial plans described:
- Approximately 489 acres
- A 245,000-square-foot data center
- Cloud computing infrastructure
- AI infrastructure
- Long-term development potential
Read the City of La Porte’s original Microsoft announcement.
Microsoft Broke Ground in June 2026
Microsoft held its official groundbreaking in June 2026.
The milestone confirmed that the project had moved from planning and approvals into active development.
Microsoft has also confirmed that Ryan Central is handling grading work at the site.
As of July 2026, site preparation continued ahead of future vertical construction.
See Microsoft’s current La Porte construction updates.
More Than 600 Permanent Jobs in the First Phase
The project’s employment outlook has changed significantly since the original announcement.
Indiana’s initial 2024 announcement projected up to 200 jobs by the end of 2032.
At the June 2026 groundbreaking, however, Microsoft said the project’s first phase is expected to create more than 600 permanent Microsoft jobs.
That newer company statement is the more current figure.
Microsoft also says thousands of construction jobs will be associated with development.
Potential permanent roles at a Microsoft data center can include:
- Critical-environment engineers
- IT technicians
- Operations managers
- Inventory technicians
- Security staff
- Site managers
Read Microsoft’s groundbreaking announcement.
Closed-Loop Liquid Cooling
Microsoft says the La Porte campus will use energy-efficient closed-loop liquid cooling.
Closed-loop systems can reduce ongoing water consumption because water circulates within the cooling system rather than being continuously evaporated.
That does not mean the entire site will use no water.
Water may still be needed for:
- Domestic uses
- Construction
- Landscaping
- Fire protection
- Other facility systems
But cooling design has a major effect on the overall water profile of a data center.
See our explainer on why data centers use water.
How Large Could the Campus Become?
The original announcement described one 245,000-square-foot data center.
Microsoft’s development plans have since expanded beyond that original single-building framing.
The company has pursued additional property and phased development around the La Porte site.
Because campus plans can evolve during rezoning and design, the safest current description is that Microsoft is building a multi-phase data center campus, with its first phase now under construction.
The original 245,000-square-foot figure should not automatically be treated as the final size of the entire campus.
Tax Agreement and Local Schools
The City of La Porte announced an updated tax agreement with Microsoft in March 2026.
The update followed Microsoft’s decision not to seek local property-tax abatements for its newer data center projects.
City officials said the revised arrangement means Microsoft will pay normal property taxes while also directing funding toward local schools.
This matters because tax treatment can materially affect the local economic impact of a data center even when investment totals are extremely large.
Read the City of La Porte’s updated Microsoft tax agreement.
Microsoft Datacenter Academy
At the groundbreaking, Microsoft also announced a partnership with Ivy Tech Community College to establish its first Microsoft Datacenter Academy in Indiana.
The program is intended to train residents for infrastructure and technology careers associated with data centers.
Training programs can be especially important in markets where multiple hyperscale operators are competing for:
- Electricians
- HVAC technicians
- Network technicians
- Critical-environment specialists
- Construction workers
Indiana now has simultaneous major projects from Microsoft, AWS, Meta and Google, increasing demand for many of the same skilled occupations.
Power Requirements
Microsoft has not reduced the current La Porte campus to one public maximum-MW figure in its main project updates.
That means power demand should not be estimated from the $1 billion investment alone.
Future utility filings, substation plans and environmental permits may provide clearer indications of eventual capacity.
Residents should watch for:
- Utility service agreements
- Substation permits
- Transmission upgrades
- Generator permits
- Maximum projected load
See our guide to how much electricity a data center uses.
Construction Status
As of Microsoft’s July 2026 update:
- Grading work was underway.
- Ryan Central was serving as the grading contractor.
- Work was concentrated on the northern portion of the site.
- Preparation for vertical construction was progressing.
- Grading was expected to continue through the remainder of 2026.
This makes La Porte an active construction project, not merely a proposed development.
Frequently Asked Questions
Who is building the La Porte data center?
Microsoft is developing the La Porte campus.
How much is Microsoft investing?
The original announcement identified approximately $1 billion of investment.
How many jobs will the project create?
Microsoft’s newest statement says the first phase is expected to create more than 600 permanent Microsoft jobs, plus thousands of construction jobs.
When did construction begin?
Microsoft held its groundbreaking in June 2026.
How big is the La Porte data center?
The original plan described a 245,000-square-foot facility on approximately 489 acres, but Microsoft’s campus plans have expanded beyond the original single-building concept.
What cooling system will Microsoft use?
Microsoft says the campus will use closed-loop liquid cooling.
Is the project still only proposed?
No. Site work and construction are underway.
Bottom Line
The Microsoft La Porte data center has evolved substantially since its original $1 billion announcement.
What began publicly as a 245,000-square-foot project has become a larger, phased campus now under construction, with Microsoft projecting more than 600 permanent jobs from the first phase alone.
Its employment scale, closed-loop cooling system, tax agreement and continuing construction make La Porte one of the Indiana projects most worth tracking through 2027 and beyond.