Microsoft MNZ07 Wellington data center plans call for a two-building campus on approximately 123 acres in Prince William County, Virginia, near Gainesville. Microsoft says the site remains in the early planning and permitting stage and that data center construction has not yet begun.
The proposed project would include two one-story data center buildings, an on-site electrical substation, a water storage facility, stormwater infrastructure, fiber and electrical conduit, sanitary sewer and industrial wastewater systems. Federal and state environmental reviews also identify proposed impacts to streams and wetlands.
Last updated: September 22, 2026
Current status: Early planning / permitting
For broader context, see the Virginia Data Center Projects Tracker and the U.S. Data Center Projects Tracker.
Microsoft MNZ07 Wellington Data Center at a Glance
| Detail | Current Information |
|---|---|
| Company | Microsoft Corporation |
| Project | MNZ07 Wellington Data Center |
| Location | 13490 University Boulevard, Prince William County, Virginia |
| Site size | Approximately 123 acres |
| Buildings | Two proposed one-story data center buildings |
| Substation | On-site electrical substation proposed |
| Other infrastructure | Water storage, domestic/fire water, sanitary sewer, industrial wastewater, fiber/electrical conduit, detention ponds and stormwater systems |
| Environmental impacts under review | 955 linear feet of intermittent stream; about 1.95 acres of wetlands |
| Current status | Early planning / permitting; construction has not begun |
| MW capacity | Not publicly disclosed in the reviewed records |
Where Is the Microsoft MNZ07 Wellington Data Center?
The Microsoft MNZ07 Wellington data center is proposed at 13490 University Boulevard in Prince William County. Virginia DEQ describes the property as south of Interstate 66, east of University Boulevard and north of Wellington Road, with access from University Boulevard.
The location places the project in the Gainesville area of western Prince William County, part of Northern Virginia’s expanding data center market.
Virginia DEQ’s environmental review notice and the U.S. Army Corps of Engineers’ September 2026 public notice provide the clearest current public description.
What Is Planned at the Wellington Data Center?
The proposed Microsoft MNZ07 Wellington data center would contain two one-story buildings designed for cloud computing and data storage operations. The project also includes an on-site substation, water storage, domestic and fire-hydrant water, sanitary sewer, industrial wastewater, fiber and electrical conduit, detention ponds and stormwater systems.
Microsoft and permitting records have not disclosed a verified MW capacity. The presence of an on-site substation confirms substantial electrical infrastructure is planned, but assigning a specific power demand without a utility or company figure would be speculative.
See Data Center Substations Explained and Why Data Centers Need New Transmission Lines.
Microsoft Says Construction Has Not Started
Microsoft’s September 2026 community update says the Microsoft MNZ07 Wellington data center remains in early planning and permitting. The company says it purchased the Prince William County land in 2024 for future data center development, but construction has not begun.
Microsoft’s Wellington environmental planning update says construction timing remains a long way off while permitting, remediation coordination and environmental review continue.
See How Long Does It Take to Build a Data Center?.
Wetlands and Stream Impacts Under Review
The Microsoft MNZ07 Wellington data center requires environmental review because the proposed site plan would affect streams and wetlands. Virginia DEQ identifies proposed permanent impacts to 955 linear feet of intermittent stream, 1.82 acres of emergent wetlands and 0.13 acre of forested wetlands.
That totals roughly 1.95 acres of wetlands in addition to the stream impacts. The filings describe proposed impacts; they do not mean the impacts have already occurred.
How Much Power Will the Microsoft MNZ07 Wellington Data Center Use?
A verified power-demand figure for the Wellington data center has not been publicly disclosed. The proposal includes an on-site substation, but an on-site substation alone does not establish final MW load.
Until Microsoft, Dominion Energy, PJM, Prince William County or another authoritative source publishes a confirmed figure, the project should not be assigned an estimated MW number based only on acreage or building count.
See How Much Power Does a Data Center Use?.
What Do We Know About Water Use?
Public records identify a water storage facility, domestic and fire-hydrant water, sanitary sewer and industrial wastewater infrastructure for the Microsoft Wellington project. They do not provide a verified daily or annual cooling-water figure.
Microsoft says its infrastructure approach is intended to minimize and replenish water use, but Wellington-specific cooling technology and operational consumption have not yet been fully disclosed.
See How Much Water Does a Data Center Use?.
Jobs, Taxes and Community Benefits
Microsoft has not yet published a verified project-specific construction-job or permanent-job total for the MNZ07 Wellington project in the records reviewed.
For context, see How Many Jobs Do Data Centers Create? and Data Center Property Tax Revenue Explained.
How to Track the proposed Microsoft campus
Future Wellington data center updates are most likely to appear in Virginia DEQ environmental reviews, U.S. Army Corps permits, Prince William County records, utility filings and Microsoft community updates.
See How to Find Data Center Building Permits, Site Plans & Zoning Records.
Frequently Asked Questions About the Microsoft Wellington project
Where is the MNZ07 Wellington project?
It is proposed at 13490 University Boulevard in Prince William County, near Gainesville, Interstate 66 and Wellington Road.
How large is the Wellington site?
Approximately 123 acres.
How many buildings are planned?
Two one-story data center buildings.
Is construction underway?
No. Microsoft said in September 2026 that construction has not begun.
Will the project have its own substation?
Yes. Current plans include an on-site electrical substation.
How much power will it use?
A verified MW capacity has not been publicly disclosed.
Bottom Line
The proposed Microsoft campus is a proposed two-building Microsoft cloud campus on approximately 123 acres in Prince William County. As of September 2026, Microsoft says construction has not begun and the project remains in planning and environmental permitting.
Data Center News will continue updating this profile as Microsoft, Prince William County and environmental regulators release additional information.