Microsoft SAT82 data center development near Castroville, Texas appears across multiple state construction registrations, indicating a multi-package build in Medina County.
One Texas Department of Licensing and Regulation filing describes a 244,676-square-foot, one-story, five-colocation-area data center with an estimated construction cost of $482.6 million. A later filing identifies an additional 195,670-square-foot SAT82 building package with an estimated cost of $400 million. View the 244,676-square-foot SAT82 filing and the later SAT82 registration.
Last updated: September 21, 2026
Current status: Registered / construction-stage development
For other projects in the state, see our Texas Data Center Projects tracker. For nationwide coverage, visit the U.S. Data Center Projects tracker.
Microsoft SAT82 Data Center at a Glance
| Detail | Current Information |
|---|---|
| Company | Microsoft |
| Project | SAT82 |
| Location | Castroville / Medina County, Texas |
| Major registrations | 244,676 sq. ft. and 195,670 sq. ft. building packages |
| Listed construction costs | $482.6M and $400M |
| Building type | One-story, five-colocation-area data center |
| Schedule in filings | Construction activity extending into 2028 |
| Status | Review complete / registered, depending on filing |
Microsoft Sat82 Data Center: Where Is Microsoft SAT82?
The SAT82 filings place Microsoft’s development near Castroville in Medina County, west of San Antonio.
The Microsoft SAT82 data center profile will be updated as additional project-specific filings, utility records and company disclosures become available.
The older registration lists 18844 FM 1957, Castroville. A later registration lists 3580 FM 471 N. The differing addresses and project packages indicate that SAT82 should be treated as a broader site development rather than one isolated permit line.
How Big Is SAT82?
The public filings reviewed for this profile identify at least two substantial building packages:
- 244,676 square feet in the earlier filing
- 195,670 square feet in the later Microsoft SAT82 registration
These records should not automatically be added together as a definitive campus-wide total without confirming whether every registration represents distinct non-overlapping building area. The safest description is that SAT82 involves multiple large construction packages.
For context on interpreting square footage, acreage and electrical load, see How Big Is a Data Center?.
What Does the SAT82 Design Include?
Texas records describe the data center as a one-story building with five colocation areas. The later filing also references Tier II network infrastructure.
“Colo” in this construction context refers to internal data halls or colocation areas within the facility rather than necessarily indicating a retail colocation business model.
How Much Does SAT82 Cost?
The earlier 244,676-square-foot filing lists an estimated cost of $482.6 million. The later 195,670-square-foot package lists $400 million.
As with other permit values, these figures represent the estimated cost attached to individual construction registrations. They should not be presented as Microsoft’s total investment in the broader Medina County campus unless the company confirms a campus-wide number.
What Is the SAT82 Construction Timeline?
The 244,676-square-foot registration lists a construction period from April 2026 through February 2028. The later Microsoft SAT82 registration lists an August 2026 start and July 2028 completion.
That multi-year schedule is typical of major data center construction, particularly when electrical infrastructure and multiple building packages are involved. See our data center construction timeline guide.
Power and Utility Infrastructure
The TDLR records do not disclose a full SAT82 MW requirement. A project of this size can require dedicated utility equipment, but project-specific substation and transmission details should only be added once supported by utility or regulatory records.
Our guides to data center substations and transmission lines explain what to look for in future filings.
Water, Jobs and Local Fiscal Impact
Verified SAT82-specific water consumption, cooling technology, permanent job counts and tax-incentive details were not identified in the construction records used for this profile.
Those gaps matter. Project pages should distinguish known facts from information that remains undisclosed rather than borrowing assumptions from other Microsoft campuses.
Why SAT82 Matters for Medina County
SAT82 is one of multiple Microsoft projects appearing in Medina County records, including SAT93. Together, they show continued hyperscale expansion west of San Antonio.
That makes Medina County an important region to monitor for additional utility filings, substations, property transactions and road or water infrastructure tied to large data center loads.
For readers tracking the Microsoft SAT82 data center, the most important next records will be construction filings, power and interconnection details, water or cooling disclosures, and confirmed build-out milestones.
Frequently Asked Questions
What is Microsoft SAT82?
SAT82 is a Microsoft data center development near Castroville in Medina County, Texas.
How large is SAT82?
Public Texas records identify major SAT82 construction packages of approximately 244,676 square feet and 195,670 square feet.
How much does SAT82 cost?
The two identified registrations list estimated construction costs of $482.6 million and $400 million. Those are permit-level figures, not necessarily a total campus investment.
When will SAT82 be completed?
Current state registrations show construction activity extending into 2028.
How much power will SAT82 use?
A verified campus-wide MW figure has not been identified in the TDLR records reviewed for this profile.
Where can I track other Texas projects?
See the Texas tracker.