Microsoft SAT93 data center plans in Medina County, Texas describe a large greenfield development with an approximately 245,000-square-foot, one-story data center.
Texas records show at least two SAT93 construction registrations. An earlier filing lists an estimated construction cost of $350 million and work extending from 2025 into 2027. A later Microsoft filing describes a 245,000-square-foot five-colocation-area building with work scheduled from 2027 into 2029. View the earlier SAT93 registration and the later Microsoft SAT93 filing.
Last updated: September 21, 2026
Current status: Registered / phased construction and future development
For other projects statewide, see our Texas Data Center Projects tracker. For national coverage, visit the U.S. Data Center Projects tracker.
Microsoft SAT93 Data Center at a Glance
| Detail | Current Information |
|---|---|
| Company | Microsoft |
| Project | SAT93 |
| Location | County Road 381, Medina County, Texas |
| Building size | Approx. 245,000 sq. ft. per major filing |
| Building type | One-story data center; later filing describes five colocation areas |
| Site type | Greenfield |
| Construction cost in major filings | $350M in earlier filing; $26M in later registration |
| Schedule | Records span 2025-2029 |
| Status | Review complete / registered |
Microsoft Sat93 Data Center: Where Is Microsoft SAT93?
State records place SAT93 on County Road 381 in Medina County. The address is part of the broader San Antonio-area data center expansion west of the city.
The Microsoft SAT93 data center profile will be updated as additional project-specific filings, utility records and company disclosures become available.
Microsoft is also developing SAT82 near Castroville, making Medina County a significant Microsoft infrastructure cluster rather than a one-project location.
How Big Is the SAT93 Data Center?
Both major filings reviewed describe approximately 245,000 square feet of data center construction.
The later registration specifies a one-story, five-colocation-area building on a new greenfield data center site. That suggests future campus infrastructure may extend beyond the building envelope itself.
Why Do the SAT93 Cost and Schedule Records Differ?
The earlier SAT93 filing lists an estimated cost of $350 million, with work beginning in May 2025 and ending in June 2027.
A later Microsoft SAT93 registration lists an estimated cost of $26 million, with work scheduled from March 2027 through April 2029.
Those differences are a good example of why a single permit record should not always be treated as the total project. Large data centers can be split into building, interior, network, electrical or later-phase construction packages.
Our guide to data center building permits and site plans explains how to interpret multi-record projects.
What Is the Current Status?
The earlier filing is marked review complete, while the later filing remains registered. Together, the records support describing SAT93 as a project with active and future construction phases rather than an operating data center.
The latest listed schedule extends into 2029, so SAT93 should continue to be monitored for additional construction registrations and utility infrastructure.
Power and Grid Infrastructure
A verified full-build-out MW figure for SAT93 was not included in the TDLR records reviewed here.
Future utility and regulatory records may reveal substations, feeders, transformers or transmission work associated with the site. See Data Center Substations Explained for the infrastructure typically required to serve very large facilities.
Water, Cooling and Environmental Information
Project-specific cooling technology and water demand were not disclosed in the public construction registrations used for this profile.
Those details should be added only when supported by utility agreements, environmental filings or Microsoft disclosures. See How Much Water Does a Data Center Use? for the key figures communities should look for.
Jobs and Economic Impact
The TDLR records do not provide a verified construction-workforce or permanent-job estimate for SAT93.
That is different from saying the project will not create jobs. It means the project-specific numbers have not been publicly established in the sources used here. When figures become available, construction and operational employment should be reported separately.
For readers tracking the Microsoft SAT93 data center, the most important next records will be construction filings, power and interconnection details, water or cooling disclosures, and confirmed build-out milestones.
Frequently Asked Questions
What is Microsoft SAT93?
SAT93 is a Microsoft data center development in Medina County, Texas.
How large is SAT93?
Major Texas filings describe a one-story data center of approximately 245,000 square feet.
Where is SAT93 located?
State records list County Road 381 in Medina County, west of the San Antonio region.
Is SAT93 under construction?
Public filings include both review-complete and future registered construction packages, with schedules extending into 2029.
How much power will SAT93 use?
A verified campus-wide MW figure has not been identified in the construction registrations reviewed here.
What other Microsoft project is in Medina County?
Microsoft also has the SAT82 data center development near Castroville.