The Project Flex data center is a proposed hyperscale campus in Lyon Township, Michigan, being developed by Verrus in partnership with property owner Walbridge.
Plans call for approximately 1.8 million square feet of data center space across six buildings on roughly 180 acres near New Hudson in Oakland County.
Verrus projects approximately 210 permanent jobs and up to 2,000 union construction jobs if the development moves forward.
The project received conditional site-plan approval in September 2025 but remains subject to additional review and permitting.
Project Flex is tracked alongside other major developments in our Michigan Data Center Projects tracker.
Project Flex at a Glance
| Detail | Current Information |
|---|---|
| Developer | Verrus |
| Property Partner | Walbridge |
| Location | Lyon Township / New Hudson |
| County | Oakland County |
| Site | Approximately 180 acres |
| Buildings | Six |
| Total Building Area | Approximately 1.8 million sq. ft. |
| Permanent Jobs | ~210 projected |
| Construction Jobs | Up to ~2,000 projected |
| Utility | DTE Energy |
| Backup Strategy | Battery energy storage |
| Status | Proposed / Conditional approval |
Where Is the Project Flex data center?
The proposed campus is located on the east side of Milford Road, south of the Huron Valley Trail and New Hudson Drive West in Lyon Township.
Access is planned through the Ambassador Parkway area from South Hill Road.
Lyon Township describes the property as roughly 180 acres.
Read Lyon Township’s official Project Flex FAQ.
How Large Is the Project Flex data center?
The proposed campus includes:
- Six data center buildings
- Approximately 1.8 million square feet total
- A utility substation
- Supporting electrical and cooling infrastructure
That would make Project Flex one of Michigan’s larger proposed multi-building data center campuses by physical size.
See Verrus’s official Project Flex overview.
Who Is Verrus?
Verrus is the applicant and proposed data center developer.
The company was launched by Sidewalk Infrastructure Partners, an infrastructure investment platform.
Walbridge owns the property and is working with Verrus on the proposal.
Project Flex is designed around a concept Verrus describes as more flexible interaction with the power grid than traditional hyperscale facilities.
The project’s name refers to its proposed ability to reduce or “flex” electricity consumption during periods of grid stress.
Conditional Site-Plan Approval
The Lyon Township Planning Commission conditionally approved the Project Flex site plan on September 8, 2025.
However, conditional approval did not authorize immediate construction.
Township officials said the project remained subject to conditions including:
- Energy audit review
- Sound study review
- Final permitting
- Other engineering and planning requirements
A building permit cannot be issued until applicable conditions have been satisfied.
Read Lyon Township’s January 2026 project-status statement.
How Many Jobs Would Project Flex Create?
Verrus says the development would support approximately:
- 210 permanent jobs
- Up to 2,000 union construction jobs
Those are developer projections for the proposed development.
Permanent and temporary construction employment should be treated separately.
Projected Tax Revenue
Verrus’s 2026 Community Benefits Framework projects approximately $300 million in tax revenue over 17 years for:
- Lyon Township
- Local schools
- Oakland County
- Regional services
The company says it is not seeking a local tax abatement or incentive.
Those numbers are projections rather than realized tax revenue and depend on the project being developed as proposed.
Read Project Flex’s Community Commitments.
Water Use
Verrus says Project Flex’s cooling design would use approximately 99% less water than older legacy data center designs.
The developer has also proposed permanent public monitoring of water use.
Project-specific cooling details should ultimately be evaluated against final engineering documents and actual operating data.
Still, the proposal is designed around lower consumptive water use than conventional evaporative cooling.
See Why Data Centers Use Water.
Battery Storage Instead of Traditional Diesel Backup
One of Project Flex’s more distinctive design commitments involves backup power.
Verrus says the campus would rely primarily on battery energy storage rather than conventional diesel backup generators.
The developer says it has not applied for standard backup-generator permits and would only use small life-safety generators required by fire codes.
That approach, if implemented as proposed, would distinguish Project Flex from many hyperscale campuses that use large fleets of diesel generators.
Battery storage is also central to Verrus’s claim that the campus could reduce demand during periods of grid stress.
DTE Energy and the Utility Substation
The project includes a dedicated utility substation and is expected to be served by DTE Energy.
Large data centers often require custom utility infrastructure because electricity demand can be substantially larger than conventional commercial developments.
Important issues to monitor include:
- Maximum MW demand
- Interconnection agreement
- Substation design
- Transmission requirements
- Who pays for upgrades
- Minimum billing commitments
The final electricity-demand figure has not been publicly established in the primary materials used here.
Noise and Community Concerns
Project Flex has generated substantial community opposition and public participation.
Residents have raised concerns about:
- Noise
- Water
- Battery safety
- Electricity demand
- Residential proximity
- Construction impacts
- Land use
- Property values
Verrus says it has revised the project in response to community feedback and has proposed public monitoring of both noise and water use.
Because the project is still in review, some design details may continue to change.
Current Status
The Project Flex data center remains proposed.
It received conditional site-plan approval in September 2025, but additional review, permit conditions and engineering requirements remain before construction can proceed.
The project should therefore not be described as operating or fully approved for construction.
Frequently Asked Questions
What is Project Flex?
Project Flex is a proposed six-building hyperscale data center campus being developed by Verrus in Lyon Township, Michigan.
Where is Project Flex located?
The site is near New Hudson, east of Milford Road and south of the Huron Valley Trail in Lyon Township.
How large is it?
Plans call for approximately 1.8 million square feet across six buildings on roughly 180 acres.
How many jobs would it create?
Verrus projects approximately 210 permanent jobs and up to 2,000 union construction jobs.
Will the Project Flex data center use diesel generators?
Verrus says the campus would use battery energy storage instead of traditional diesel backup generators, aside from life-safety equipment required by code.
Has Project Flex been approved?
The Lyon Township Planning Commission granted conditional site-plan approval in September 2025, but additional conditions and permits remain.
Is construction underway?
The project is still best classified as proposed/development-stage rather than active vertical construction.
Bottom Line
The Project Flex data center is one of Michigan’s largest proposed data center campuses by building area.
Its six-building, 1.8-million-square-foot design, battery-based backup strategy, projected 210 permanent jobs and ongoing community review make it a particularly important project to monitor as Michigan develops rules around large-scale data center growth.