The Stargate Saline Township data center is a massive artificial-intelligence infrastructure campus under construction in Washtenaw County, Michigan.
Known as The Barn, the development is being built by Related Digital for Oracle as part of Oracle and OpenAI’s Stargate AI infrastructure partnership.
The campus carries a reported $16 billion financing package, includes three approximately 550,000-square-foot data center buildings, and has a contracted electrical load of 1,383 megawatts.
Construction began in 2026, and the project has quickly become one of the largest individual data center developments in Michigan.
See it alongside other major projects in our Michigan Data Center Projects tracker.
Stargate Saline Township Data Center at a Glance
| Detail | Current Information |
|---|---|
| Project | The Barn / Stargate Michigan |
| Developer | Related Digital |
| Future Operator | Oracle |
| AI Customer | OpenAI |
| Location | Saline Township, Washtenaw County |
| Financing / Project Value | $16 billion financing announced |
| Electrical Load | 1,383 MW contracted |
| Campus Capacity | More than 1 GW |
| Buildings | Three data center buildings |
| Building Size | ~550,000 sq. ft. each |
| Site | Approximately 250 acres |
| Construction Jobs | 2,500+ union jobs |
| Permanent On-Site Jobs | 450+ |
| Status | Under construction |
What Is the Stargate Michigan Project?
The Saline Township campus is part of the larger Stargate initiative, an effort by OpenAI and Oracle to build large-scale AI computing infrastructure across the United States.
Related Digital is developing the Michigan site specifically for Oracle.
Oracle says it will ultimately operate the data center and equip it with infrastructure supporting OpenAI’s AI workloads.
Read OpenAI’s official Michigan Stargate announcement.
The project was originally announced as a multi-billion-dollar, more-than-1-gigawatt campus.
In April 2026, Related Digital announced that financing had been secured for a $16 billion project, backed by equity from Related Digital and Blackstone-affiliated funds along with long-term debt financing anchored by PIMCO-managed funds.
Read Related Digital’s financing announcement.
How Large Is the Saline Township Data Center?
The campus includes three single-story data center buildings of roughly 550,000 square feet each.
That puts the core data center footprint at approximately:
1.65 million square feet
The project is being developed on roughly 250 acres.
Related Digital has also committed to preserving more than 750 acres of nearby open space, farmland and wetlands.
Each building is expected to be LEED certified.
For context on how those numbers compare with other campuses, see How Big Is a Data Center?.
The Project Has a 1,383 MW Electric Load
The Michigan Public Service Commission approved special contracts associated with a 1,383-megawatt data center load.
That makes Saline Township one of the clearest examples of how AI infrastructure can create electricity demand on the scale of a major power plant.
A 1,383 MW contract does not necessarily mean the campus will consume 1,383 MW continuously.
However, it represents the scale of capacity DTE must be prepared to serve.
Read the Michigan Public Service Commission’s data center contract decision.
See How Much Power Does a Data Center Use? for more context on MW and annual electricity consumption.
Who Pays for the Power Infrastructure?
Power costs became one of the central issues surrounding the project.
OpenAI, Related Digital and Oracle say the project will pay for the infrastructure needed to serve the campus rather than passing project-specific costs to existing DTE customers.
DTE is supplying the project using existing resources supplemented with new battery energy storage financed by the project.
The MPSC also imposed consumer protections when approving the contracts.
Those protections include conditions intended to prevent other DTE customers from bearing unrecovered costs associated with the campus.
Battery Storage for the Campus
The scale of the project has also driven major battery-storage development.
The MPSC approved battery projects associated with the Saline campus, with Green Chile Ventures—the Oracle-affiliated customer entity—responsible for development costs under the approved arrangement.
Battery storage can help DTE manage the campus’s large load while also improving system flexibility.
This is an important distinction from on-site natural-gas generation projects such as Valara in South Carolina.
The Saline campus is instead tied to utility-supplied electricity and large-scale battery storage.
Water Use and Closed-Loop Cooling
The project team says The Barn will use a closed-loop, air-cooled system.
OpenAI says the cooling design uses water at levels comparable to a typical office building.
Related Digital similarly says the design is intended to protect Michigan’s local water resources and the Great Lakes.
Closed-loop cooling dramatically changes the water profile compared with evaporative cooling, but it does not mean the overall campus uses zero water.
Domestic, fire-protection and other uses may still require water.
See Why Data Centers Use Water.
Jobs at the Saline Township Campus
The project team expects:
- More than 2,500 union construction jobs
- More than 450 permanent on-site jobs
- Approximately 1,500 jobs county-wide supporting the project
- Additional indirect employment
By August 2026, Related Digital said more than 1,800 skilled tradespeople were working on the campus and had logged more than one million union craft hours.
Those construction jobs should be separated from permanent operating jobs when assessing the project’s long-term employment impact.
See How Many Jobs Do Data Centers Create?.
Community Investments
The project team has announced several local investments.
These include:
- $10 million toward expansion and modernization of the Saline Recreation Center
- Approximately $14 million in direct fire-service and other community investments
- Farmland and open-space preservation commitments
These community contributions are separate from the project’s tax obligations and infrastructure spending.
When Will the Stargate Michigan Campus Open?
Oracle currently says the Saline Township campus was contracted in October 2025 and that customer delivery begins in the second half of 2027.
Oracle also reported in August 2026 that its network core was ahead of schedule.
All three primary data center buildings are under construction.
See Oracle’s current data center construction status.
Current Status
The Stargate Saline Township data center is under active construction.
Construction began in 2026, major financing has been secured, utility contracts have been approved, and the first customer delivery is currently targeted for the second half of 2027.
Frequently Asked Questions
What is the Stargate Saline Township data center?
It is a large AI data center campus being developed by Related Digital for Oracle as part of Oracle and OpenAI’s Stargate infrastructure program.
How much is the project worth?
Related Digital announced financing for a $16 billion project in April 2026.
How much power will it use?
DTE’s approved contracts cover a 1,383 MW data center load.
How large is the campus?
Plans include three approximately 550,000-square-foot data center buildings on roughly 250 acres.
How many jobs will it create?
The project team expects 2,500+ union construction jobs and more than 450 permanent on-site jobs.
Does it use a lot of water for cooling?
The project team says the campus will use closed-loop, air-cooled cooling designed to use water at levels comparable to an office building.
When will it open?
Oracle says customer delivery is expected to begin in the second half of 2027.
Bottom Line
The Stargate Saline Township data center is one of the largest AI infrastructure projects underway in Michigan.
Its $16 billion financing, 1,383 MW contracted electric load, three-building campus and Stargate connection make it a defining project for understanding how AI data centers are changing Michigan’s electricity, infrastructure and economic-development landscape.