Valara Data Center: $2.8B Spartanburg High-Performance Computing Project

Data Center News by Data Center News
September 24, 2026
in Project Tracker
Valara Data Center $2.8B Spartanburg HPC Project & Status

Valara Data Center $2.8B Spartanburg HPC Project & Status

Share on FacebookShare on Twitter

The Valara data center in Spartanburg, South Carolina, is a $2.8 billion high-performance computing development associated with NorthMark Strategies that has become one of the state’s most closely watched data center projects.

The facility is being developed at 4000 South Pine Street in Spartanburg and is notable not only for its scale, but also for its plan to produce a substantial amount of electricity on site.

South Carolina announced the project in April 2025 as NorthMark Strategies’ first operation in the state. The company said the facility would support high-performance computing workloads for businesses in engineering and technology.

Since that announcement, environmental permitting records have provided substantially more detail about how the project intends to generate power and operate.

Residents can also see Valara alongside other projects in our South Carolina Data Center Projects tracker.

Table of Contents

Toggle
  • Valara Data Center at a Glance
  • Where Is the Valara Data Center?
  • Why Valara’s Power System Is Unusual
  • Valara’s First Air Permit
  • Valara’s Second Air Permit Approved in September 2026
  • How Much Power Could the Valara Turbines Produce?
  • Public Hearing and Community Interest
  • How Many Jobs Will the Valara Data Center Create?
  • What Is the Current Status of the Valara Data Center?
  • Frequently Asked Questions
    • What is the Valara data center?
    • How much is the Valara Spartanburg project worth?
    • Where is the Valara data center located?
    • How many jobs will Valara create?
    • Does Valara generate its own electricity?
    • Were Valara’s 11 turbines approved?
  • Bottom Line

Valara Data Center at a Glance

DetailCurrent Information
ProjectValara High Performance Compute Center
Parent / DeveloperNorthMark Strategies / Valara Holdings
Location4000 South Pine Street, Spartanburg, South Carolina
Announced InvestmentApproximately $2.8 billion
Announced JobsAt least 27
UseHigh-performance computing
Power StrategySignificant on-site generation
Initial Air PermitApproved September 2025
Second Air PermitApproved September 18, 2026
StatusDevelopment / environmental permitting

The original economic-development announcement said initial operations were expected in the third quarter of 2026, followed by additional development phases.

However, project timelines can change as construction, permitting and infrastructure work progress.

Where Is the Valara Data Center?

The Valara High Performance Compute Center is located at 4000 South Pine Street in Spartanburg, South Carolina.

NorthMark selected Spartanburg after evaluating more than 100 potential locations across the United States, according to the company’s 2025 announcement.

The facility represents one of the largest announced technology investments in Spartanburg County.

South Carolina said the $2.8 billion investment is expected to create at least 27 permanent jobs, with additional regional businesses and suppliers potentially supporting maintenance and operations.

Read South Carolina’s official NorthMark announcement

Why Valara’s Power System Is Unusual

One of the most important aspects of the Valara data center is its reliance on on-site electricity generation.

Large data centers normally obtain most of their electricity from the regional utility grid, supported by dedicated substations and transmission infrastructure.

Valara is taking a different approach.

Environmental permits reviewed by the South Carolina Department of Environmental Services show plans involving permanent natural-gas generators and larger natural-gas-fired turbines.

That makes Valara particularly important for communities trying to understand how some future AI and high-performance computing campuses may attempt to address grid-capacity constraints.

For background on electrical requirements, see our guide explaining how much power a data center uses.

Valara’s First Air Permit

The South Carolina Department of Environmental Services issued Valara’s first Synthetic Minor Air Construction Permit in September 2025.

That permit authorized 24 permanent natural-gas-fired generators, each rated at approximately 2.1 MW.

The generators include emissions-control equipment and are subject to federally enforceable limits covering pollutants including nitrogen oxides, carbon monoxide and volatile organic compounds.

In April 2026, the permit was amended to allow 21 temporary natural-gas-fired generators.

SCDES states that those temporary generators cannot operate at the same time as the permanent generator system and cannot remain at the facility indefinitely.

These permit details are important because generator counts in environmental records can reveal considerably more about a data center’s power strategy than an economic-development announcement alone.

Valara’s Second Air Permit Approved in September 2026

Valara later applied for a second air permit covering a much larger generation system.

On September 18, 2026, SCDES approved a Synthetic Minor Air Construction Permit allowing Valara to construct and operate:

  • Five simple-cycle 17 MW natural-gas turbines
  • Six simple-cycle 54 MW natural-gas turbines

That represents 11 additional combustion turbines.

SCDES says the turbines will use selective catalytic reduction and oxidation-catalyst emissions controls.

The approval followed an extended public review process that included a public hearing in Spartanburg on June 25, 2026.

See SCDES’s current Valara project and permit page

How Much Power Could the Valara Turbines Produce?

The permitted turbine ratings provide an indication of the potential scale of Valara’s on-site generation.

Five 17 MW turbines equal approximately:

85 MW

Six 54 MW turbines equal approximately:

324 MW

Combined, their nameplate ratings total roughly:

409 MW

That does not necessarily mean the data center will consume 409 MW continuously.

Generator nameplate capacity, maximum facility demand and actual electricity consumption are different measurements.

Nevertheless, the permitted turbine fleet demonstrates the enormous electrical requirements that can accompany modern high-performance computing infrastructure.

Public Hearing and Community Interest

Valara’s second permit generated significant public interest.

SCDES held an availability session and public hearing at Spartanburg Memorial Auditorium in June 2026 and extended the public-comment period through July 31.

Questions surrounding projects with large on-site generating systems can include:

  • Air emissions
  • Generator operating hours
  • Natural-gas infrastructure
  • Noise
  • Water use
  • Grid impacts
  • Residential proximity
  • Emergency operations

SCDES says it reviewed comments received during the public-comment period before issuing its final permit decision.

The agency also published its response to comments and air-quality modeling information.

For communities facing similar developments, our guide to public records for data center development explains how permitting documents can reveal project details not included in public announcements.

How Many Jobs Will the Valara Data Center Create?

South Carolina’s original announcement projected at least 27 permanent jobs from the $2.8 billion project.

That relatively low permanent employment number compared with the project’s investment illustrates an important characteristic of hyperscale and high-performance computing infrastructure.

Data centers can require large numbers of workers during construction while needing far fewer employees once the facility is operating.

Readers can see similar comparisons across the state’s projects in the South Carolina Data Center Projects tracker.

What Is the Current Status of the Valara Data Center?

As of September 2026, the project has obtained major air permits associated with its on-site generation system.

The most significant recent milestone occurred on September 18, 2026, when SCDES approved the second Synthetic Minor Air Construction Permit for the 11-turbine system.

Additional local, state or operational approvals may still apply as the campus moves through development.

Frequently Asked Questions

What is the Valara data center?

Valara is a high-performance computing center being developed in Spartanburg, South Carolina, and associated with NorthMark Strategies and Valara Holdings.

How much is the Valara Spartanburg project worth?

NorthMark announced approximately $2.8 billion of investment.

Where is the Valara data center located?

The announced address is 4000 South Pine Street in Spartanburg, South Carolina.

How many jobs will Valara create?

South Carolina’s announcement projected at least 27 permanent jobs.

Does Valara generate its own electricity?

Valara has received permits covering significant natural-gas-powered on-site generation, including permanent generators and 11 combustion turbines.

Were Valara’s 11 turbines approved?

Yes. SCDES issued the relevant air construction permit on September 18, 2026.

Bottom Line

The Valara data center in Spartanburg is notable for more than its $2.8 billion announced investment.

Its extensive on-site generation system provides a real-world example of how high-performance computing campuses can attempt to secure hundreds of megawatts of electricity when grid capacity is limited or when developers want additional control over power availability.

That makes Valara one of South Carolina’s most important data center projects to follow as development continues.

ShareTweet

join the DataCenterNews.org newsletter

Stay Connected

Email field is required to subscribe.

x

You Have Successfully Subscribed to the Newsletter

Data Center News

Data Center News

The Data Center News Research Desk produces research-driven coverage of data center development, power infrastructure, water use, construction, AI demand, policy, and community impacts. Our work draws on public records, government data, utility and regulatory filings, company disclosures, planning documents, and other primary sources whenever available.

Related Posts

Project Flex Data Center Lyon Township Michigan Plans & Status
Project Tracker

Project Flex Data Center: Lyon Township Michigan Plans & Status

September 25, 2026

The Project Flex data center is a proposed hyperscale campus in Lyon Township, Michigan, being developed by Verrus in partnership...

Read moreDetails
Project Cherry Blossom Data Center Frenchtown Michigan Plans
Project Tracker

Project Cherry Blossom Data Center: Frenchtown Michigan Plans

September 25, 2026

The Project Cherry Blossom data center is a proposed large-scale data center campus being developed by Cloverleaf Infrastructure in Frenchtown...

Read moreDetails
Data Center News

Data center news, projects, and analysis covering power grids, water use, AI demand, incentives, and community impact behind the world’s growing cloud infrastructure.

Navigation

  • About
  • Authors & Editors
  • Contact
  • Editorial Policy
  • Home
  • Privacy Policy
  • Terms of Service

Topics

  • AI & Cloud
  • Infrastructure & Construction
  • News
  • Policy & Community
  • Power & Grid
  • Project Tracker
  • Projects
  • Water & Environment

Join the free newsletter

Stay Connected

Email field is required to subscribe.

x

You Have Successfully Subscribed to the Newsletter

© 2026 Data Center News

No Result
View All Result
  • Home
  • News
    • Project News
  • Project Tracker
  • Power & Grid
  • Water & Environment
  • Policy & Community
  • AI & Cloud

© 2026 Data Center News